VANCOUVER, British Columbia, Jan. 03, 2019 (GLOBE NEWSWIRE) -- Amerigo Resources Ltd. ("Amerigo" or the "Company") (TSX: ARG) is pleased to announce that Minera Valle Central (“MVC”), the Company’s 100% owned operation located near Rancagua, Chile, has successfully met the completion tests set out in the $35.3 million finance agreement under which the expansion project was financed by Scotiabank Chile and Export Development Canada.
The Cauquenes Phase Two project completion tests included production, costs, commercial, environmental compliance and mechanical completion targets over a sixty-day period. The project’s $1.5 million concentrate regrind mill was removed from the Phase Two completion timeline and is expected to be installed in Q2 2019.
On December 6, 2018, Chile’s President Sebastián Piñera visited MVC to attend a ceremony celebrating the start up of the new process plant. President Piñera highlighted the innovative work carried out by MVC in the treatment of waste material from mining operations. “This new project means not only a leap into the future, but also a very important investment,” said the President at the ceremony, in which he was accompanied by Chile’s Minister of Mining, Baldo Prokurica. "It brings value and quality of life to the inhabitants of the O'Higgins Region,” Mr. Piñera added. The official press release from the President’s Office can be found at https://prensa.presidencia.cl/fotonoticia.aspx?id=88172
Rob Henderson, Amerigo’s President and CEO, stated, “We are very pleased that President Piñera has recognised MVC’s significant contribution to the Chilean economy. We have successfully completed the work to develop the historic Cauquenes tailings deposit and this investment will enable MVC to produce substantially more copper at lower cash costs. In 2019, MVC expects to produce 80 to 85 million pounds of copper and 2.5 million pounds of molybdenum at a cash cost of $1.30 to 1.45/lb Cu.”
About Amerigo and MVC
Amerigo Resources Ltd. is an innovative copper producer with a long-term relationship with Corporación Nacional del Cobre de Chile (“Codelco”), the world’s largest copper producer.
Amerigo produces copper concentrate at the MVC operation in Chile by processing fresh and historic tailings from Codelco’s El Teniente mine, the world's largest underground copper mine. Tel: (604) 681-2802; Fax: (604) 682-2802; Web: www.amerigoresources.com; Listing: ARG:TSX.
For further information, please contact:
Cautionary Note Regarding Forward-Looking Information
This news release contains certain forward-looking information and statements as defined in applicable securities laws (collectively referred to as "forward-looking statements"). These statements relate to future events or the Company’s future performance. All statements other than statements of historical fact are forward-looking statements. The use of any of the words "anticipate", "plan", "continue", "estimate", "expect", "may", "will", "project", "predict", "potential", "should", "believe" and similar expressions is intended to identify forward-looking statements. Although the Company believes that these assumptions were reasonable when made, because these assumptions are inherently subject to significant uncertainties and contingencies which are difficult or impossible to predict and are beyond the Company’s control, the Company cannot assure that it will achieve or accomplish the expectations, beliefs or projections described in the forward-looking statements. These forward-looking statements involve known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such statements. These forward-looking statements include but are not limited to, statements concerning:
Inherent in forward-looking statements are risks and uncertainties beyond our ability to predict or control, including risks that may affect our operating or capital plans; risks generally encountered in the permitting and development of mineral projects such as unusual or unexpected geological formations, negotiations with government and other third parties, unanticipated metallurgical difficulties, delays associated with permits, approvals and permit appeals, ground control problems, adverse weather conditions, process upsets and equipment malfunctions; risks associated with labour disturbances and availability of skilled labour and management; fluctuations in the market prices of our principal commodities, which are cyclical and subject to substantial price fluctuations; risks created through competition for mining projects and properties; risks associated with lack of access to markets; risks associated with availability of and our ability to obtain both tailings from Codelco’s Division El Teniente’s current production and historic tailings from tailings deposit; risks with respect to completion of all phases of the Cauquenes expansion, the ability of the Company to draw down funds from bank facilities and lines of credit, the availability of and ability of the Company to obtain adequate funding on reasonable terms for expansions and acquisitions, including all phases of the Cauquenes expansion; mine plan estimates; risks posed by fluctuations in exchange rates and interest rates, as well as general economic conditions; risks associated with environmental compliance and changes in environmental legislation and regulation; risks associated with our dependence on third parties for the provision of critical services; risks associated with non-performance by contractual counterparties; title risks; social and political risks
associated with operations in foreign countries; risks of changes in laws affecting our operations or their interpretation, including foreign exchange controls; and risks associated with tax reassessments and legal proceedings. Many of these risks and uncertainties apply not only to the Company and its operations, but also to Codelco and its operations. Codelco’s ongoing mining operations provide a significant portion of the materials the Company processes and its resulting metals production, therefore these risks and uncertainties may also affect their operations and in turn have a material effect on the Company.
Actual results and developments are likely to differ, and may differ materially, from those expressed or implied by the forward-looking statements contained in this news release. Such statements are based on a number of assumptions which may prove to be incorrect, including, but not limited to, assumptions about:
Future production levels and cost estimates assume there are no adverse mining or other events which significantly affect budgeted production levels.
We caution you that the foregoing list of important factors and assumptions is not exhaustive. Other events or circumstances could cause our actual results to differ materially from those estimated or projected and expressed in, or implied by, our forward-looking statements. Except as required by law, we undertake no obligation to update publicly or otherwise revise any forward-looking statements or the foregoing list of factors, whether as a result of new information or future events or otherwise.