VANCOUVER, British Columbia, May 15, 2023 (GLOBE NEWSWIRE) -- Ascot Resources Ltd. (TSX: AOT; OTCQX: AOTVF) (“Ascot” or the “Company”) is pleased to announce the Company’s unaudited financial results for the three months ended March 31, 2023 (“Q1 2023”), and also to provide a construction update on the Company’s Premier Gold Project (“PGP” or the “project”), located on Nisga’a Nation Treaty Lands in the prolific Golden Triangle of northwestern British Columbia. For details of the unaudited condensed interim consolidated financial statements and Management's Discussion and Analysis for the three months ended March 31, 2023, please see the Company’s filings on SEDAR (www.sedar.com).
Derek White, President and CEO, commented, "As a result of the construction financing closed earlier this year, and also the momentum started with last year’s construction season, work crews have hit the ground running in the first quarter of 2023 with much progress being made in many areas. In mid-January contractors started inside the mill building and progressed piping and equipment installations, and outdoor construction has recently been advancing the new water treatment plant and associated infrastructure. As of Q1 2023, detailed engineering stands at 99% complete, major procurement is over 95% complete, and project construction excluding mine development is at 35%. We plan to further ramp-up construction efforts in the coming months with the mobilization of the earthworks and underground mining contractors and continue to advance project development towards initial gold pour in early 2024.”
All amounts herein are reported in $000s of Canadian dollars (“C$”) unless otherwise specified.
Q1 2023 AND RECENT HIGHLIGHTS
PROJECT CONSTRUCTION
Upon securing the new project financing in January 2023, Ascot re-engaged various contractors to progress activities in the mill building for the remainder of mill construction scope. Starting from approximately 65 people working at site at the end of January, there are now approximately 130 workers on site, and this will continue to increase with the mobilization of earthworks and mining contractors in the coming months to a peak of approximately 200 workers on site.
At the end of Q1 2023, detailed engineering was at 99% completion. Major procurement was more than 95% complete. Key orders remaining in the plant relate mostly to piping, instrumentation and bulk consumables.
Mechanical work continued in the mill; various trommels, dust collection and chute infrastructure were installed around the SAG and Ball mills. The Intensive Leach Reactor was assembled. Electricians continued installing electrical cabinetry, pulling wire, installing cable trays, and working in the MCC room. Concrete and structural steel contractors also have been restarted and their scope updated for the mill completion. Crews have also made progress on the new water treatment plant (“WTP”) and associated infrastructure, including the tailings thickener, lime silos, moving bed bio-reactor (“MBBR”) tanks, and clarifier foundation pedestals.
The earthworks contract was signed in March 2023. In order to de-water the tailings facility for the required upcoming earthworks, an additional temporary water treatment plant has been mobilized to site. This temporary de-watering will occur for a period of approximately 4-6 weeks. By the end of May 2023, the earthworks contractor will be mobilized to re-start work on the Cascade Creek Diversion Channel (“CCDC”) and tailings facility, which is anticipated to be completed by October 2023.
At the end of Q1 2023, overall construction excluding mine development was at 35.3% completion. By the end of 2022, Ascot had invested a total of approximately C$153 million in construction of PGP. By March 31, 2023, Ascot had spent C$173 million on the project. Ascot’s cash balance at March 31, 2023 was C$149 million.
UNDERGROUND MINE DEVELOPMENT
Mine plan and sequencing optimization were completed in October 2022, developing a plan to minimize upfront development while accessing early ore in an optimized sequence starting at Premier Northern Lights (“PNL”) then ramping up production at Big Missouri (“BM”), while developing over to Silver Coin (“SC”), where the upper levels of the deposit will be initially developed to maximize ore tonnage per linear metre. Based on the recently completed plan, we anticipate starting mine development in late July 2023 with the collaring of the PNL ramp portal, while development will recommence at BM in late September 2023, after completion of the plug on the 2350 level in August 2023. Engineering on a pipe and valve assembly for the 2350 plug design that was approved in February 2023 is in progress.
Limitations on ore storage on surface have resulted in a realignment of the mine plan. The initial focus in PNL will be “just in time” with long-hole drilled inventory blasted as required, while more priority will be put on BM in the early plan because material can be stored in the Dago Pit and brought to the temporary mill pad from there. The realignment of the mine plan is expected to complete by the end of mid-June 2023.
A consultant continued work on underground ventilation plans in Ventsim for all three mine areas, developing a unique plan to use the historical workings in conjunction with a “pull” system near the PNL portal. This work and the SC/BM system will be finalized and added to the updated mine plan.
Ascot is currently in the process of finalizing a mining contract with a mine contractor for development and initial production, this process will be completed during Q2 2023.
Mine development will progress throughout 2023 and delivery of ore is expected to commence late in the fourth quarter of 2023, enabling the start of mill commissioning and first gold pour in early 2024.
FINANCIAL RESULTS FOR THE THREE MONTHS ENDED MARCH 31, 2023
The Company reported a net loss of $7,589 for Q1 2023 compared to $1,370 for Q1 2022. The higher net loss in Q1 2023 is driven by a $4,202 loss on extinguishment of Senior Debt, $1,430 change in fair value of derivatives and $1,127 in fees and expenses associated with Stream.
LIQUIDITY AND CAPITAL RESOURCES
As at March 31, 2023, the Company had cash & cash equivalents of $149,261 and working capital of $131,631 excluding the current portion of the credit facilities. In Q1 2023, the Company issued 109,208,928 common shares, 400,000 stock options, and 18,963 Deferred Share Units. Also, 500,000 stock options expired unexercised and 55,530 stock options and 653,398 Restricted Share Units were exercised in Q1 2023.
MANAGEMENT’S OUTLOOK FOR 2023
With the financing package closed on January 19, 2023, the Company believes that it has sufficient funding to complete construction of the Project and achieve first gold production in early 2024. The key activities for 2023 include:
2023 AGM PRESENTATION WEBCAST
Ascot’s Annual General Meeting (“AGM”) is taking place on Thursday, June 22 at 10:00 AM PST. Please join President & CEO Derek White for a presentation via webcast at 1:15 PM PST for the results of the AGM and an overview of Ascot’s progress and plans in 2023. Please join 5 to 10 minutes prior to the scheduled time.
Time: Thursday, June 2022, 2023, at 1:15PM PT
Webcast: http://services.choruscall.ca/links/ascot20230622.html
Telephone: toll free Canada/USA 1‐800‐319‐4610; International 1‐604‐638‐5340
CONSTRUCTION PROGRESS PHOTOS
Figure 1 – Mill building mechanical equipment installation
https://www.globenewswire.com/NewsRoom/AttachmentNg/e0ae5785-ebfa-48dd-9246-cb8d3ceef739
Figure 2 – Mill building top floor mechanical equipment installation
https://www.globenewswire.com/NewsRoom/AttachmentNg/b0a3a11e-7e93-4db2-b981-f1002bda4925
Figure 3 – Tailings thickener construction
https://www.globenewswire.com/NewsRoom/AttachmentNg/6de1c984-f2b0-4bc0-888b-178f2f985875
Figure 4 – Temporary WTP for tailings facility Spring water discharge
https://www.globenewswire.com/NewsRoom/AttachmentNg/817cfbc6-c1c7-4a95-9e0e-262d43eca61f
Figure 5 – New WTP lime silos installed
https://www.globenewswire.com/NewsRoom/AttachmentNg/3ba67c39-9a30-4691-99cd-9c6559bb9685
Figure 6 – New WTP clarifier foundation pedestals installed
https://www.globenewswire.com/NewsRoom/AttachmentNg/cbe0e9c6-5c3f-4037-955e-82378a7feea4
Figure 7 – New WTP MBBR tanks installed
https://www.globenewswire.com/NewsRoom/AttachmentNg/5c626b63-e90d-410f-af37-a50837a00dac
Figure 8 – Electrical substation foundation construction
https://www.globenewswire.com/NewsRoom/AttachmentNg/d9bbc00f-cdc4-4ae7-aee6-605141a4bae8
Qualified Person
John Kiernan, P.Eng., Chief Operating Officer of the Company is the Company’s Qualified Person (QP) as defined by National Instrument 43-101 and has reviewed and approved the technical contents of this news release.
On behalf of the Board of Directors of Ascot Resources Ltd.
“Derek C. White”
President & CEO
For further information contact:
David Stewart, P.Eng.
VP, Corporate Development & Shareholder Communications
dstewart@ascotgold.com
778-725-1060 ext. 1024
About Ascot Resources Ltd.
Ascot is a Canadian junior exploration and development company focused on re-starting the past producing Premier gold mine, located on Nisga’a Nation Treaty Lands, in British Columbia’s prolific Golden Triangle. Ascot shares trade on the TSX under the ticker AOT. Concurrent with progressing the development of Premier, the Company continues to successfully explore its properties for additional high-grade underground resources. Ascot is committed to the safe and responsible development of Premier in collaboration with Nisga’a Nation as outlined in the Benefits Agreement.
For more information about the Company, please refer to the Company’s profile on SEDAR at www.sedar.com or visit the Company’s web site at www.ascotgold.com, or for a virtual tour visit www.vrify.com under Ascot Resources.
The TSX has not reviewed and does not accept responsibility for the adequacy or accuracy of this release.
Cautionary Statement Regarding Forward-Looking Information
All statements and other information contained in this press release about anticipated future events may constitute forward-looking information under Canadian securities laws ("forward-looking statements"). Forward-looking statements are often, but not always, identified by the use of words such as "seek", "anticipate", "believe", "plan", "estimate", "expect", "targeted", "outlook", "on track" and "intend" and statements that an event or result "may", "will", "should", "could" or "might" occur or be achieved and other similar expressions. All statements, other than statements of historical fact, included herein are forward-looking statements, including statements in respect of the advancement and development of the PGP and the timing related thereto, the exploration of the Company’s properties and management’s outlook for the remainder of 2023 and beyond. These statements involve known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward-looking statements, including risks associated with the business of Ascot; risks related to exploration and potential development of Ascot's projects; business and economic conditions in the mining industry generally; fluctuations in commodity prices and currency exchange rates; uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; the need for cooperation of government agencies and indigenous groups in the exploration and development of properties and the issuance of required permits; the need to obtain additional financing to develop properties and uncertainty as to the availability and terms of future financing; the possibility of delay in exploration or development programs and uncertainty of meeting anticipated program milestones; uncertainty as to timely availability of permits and other governmental approvals; risks associated with COVID-19 including adverse impacts on the world economy, construction timing and the availability of personnel; and other risk factors as detailed from time to time in Ascot's filings with Canadian securities regulators, available on Ascot's profile on SEDAR at www.sedar.com including the Annual Information Form of the Company dated March 23, 2023 in the section entitled "Risk Factors". Forward-looking statements are based on assumptions made with regard to: the estimated costs associated with construction of the Project; the timing of the anticipated start of production at the Project; the ability to maintain throughput and production levels at the Premier Mill; the tax rate applicable to the Company; future commodity prices; the grade of Resources and Reserves; the ability of the Company to convert inferred resources to other categories; the ability of the Company to reduce mining dilution; the ability to reduce capital costs; and exploration plans. Forward-looking statements are based on estimates and opinions of management at the date the statements are made. Although Ascot believes that the expectations reflected in such forward-looking statements and/or information are reasonable, undue reliance should not be placed on forward-looking statements since Ascot can give no assurance that such expectations will prove to be correct. Ascot does not undertake any obligation to update forward-looking statements. The forward-looking information contained in this news release is expressly qualified by this cautionary statement.