Braveheart Resources Provides Update on Hydroelectric Facilities Study for Bull River

2020-12-07 / @newsfile

 

Calgary, Alberta--(Newsfile Corp. - December 7, 2020) - Braveheart Resources Inc. (TSXV: BHT) (OTCQB: RIINF) ("Braveheart" or the "Company") announces that following receipt of a positive System Impact Study ("SIS") from British Columbia Hydro and Power Authority ("BCH") in May 2020 (See media release May 15, 2020) it further engaged BCH in August 2020 to complete a Facilities Study ("FS") for upgrading the hydroelectric capacity at the Bull River Mine project ("BRM"). Braveheart is proposing to reconnect to an existing 66kV power line that is immediately adjacent to the property. This power line is the same line that supplied hydroelectric power to the site during previous operations up until 2013.

The SIS determined that it is technically feasible to interconnect the proposed BRM load of 7.5 MVA to the BCH transmission system. The FS is required to further define interconnection requirements and establish a timetable for BCH's ability to meet the Company's proposed service date. BCH is currently on schedule to complete the FS and deliver a draft report by late January 2021. BCH has assigned a connection queue position for Braveheart's facility in June 2021. BCH's estimate for system reinforcements and revenue metering associated with the reconnection is $300,000. The cost estimate has an accuracy range of +100/-35%.

The BRM is currently connected to grid power which is sufficient to continue with care and maintenance activities including dewatering of the underground mining infrastructure. Once the connection to the 66 kV power line is completed, Braveheart will have sufficient grid power to operate the 700 tonne per day conventional crushing and milling circuit and advance underground mining activities. In August 2019, the Company secured a 10 MVA replacement transformer for the surface substation. The Company plans to move the transformer from Manitoba to the mine site in British Columbia in the second quarter of 2021.

The hydroelectric reconnection project is one of four key surface upgrades that are required to make the mill facility operational. In addition to commissioning of the new substation and reconnection to the 66 kV power line, the Company plans to complete in parallel the installation of a flotation circuit and a filtration circuit in the mill and civil works associated with the development of a dry stack tailings storage facility ("TSF").

Ian Berzins, President and CEO commented, "The FS is the final technical study that needs to be completed by BCH. Upon completion of the FS, the Company will have invested $360,000 in the hydroelectric reconnection project in terms of the transformer procurement cost and technical studies, representing approximately 50% of the total cost of the project. Once reconnected to the 66 kV power line, the BRM will be de-risked from the perspective of power supply".

Qualified person

Braveheart's disclosure of a technical or scientific nature in this news release has been reviewed and approved by Ian Berzins P.Eng., ICD.D, who serves as President, Chief Executive officer and a Director of the company and is a qualified person under the definition of National Instrument 43-101.

About Braveheart Resources Inc.

Braveheart is a Canadian based junior mining company focused on building shareholder value through exploration and development in favourable and proven Canadian mining jurisdictions. Braveheart's main asset is the Bull River Mine project near Cranbrook, British Columbia which has a current mineral resource containing copper, gold and silver.

Contact Information
Braveheart Resources Inc.
Ian Berzins
President & Chief Executive Officer
M: +1-403-512-8202
admin@braveheartresources.com
Website: www.braveheartresources.com

For more investor information, please contact Braveheart at:

Kevin Shum
O: +1-647-725-3888 Ext 702
M: +1-604-376-0323
E: kevin@jeminicapital.com
E: info@jeminicapital.com

We seek Safe Harbor.

Caution Regarding Forward-Looking Information

This news release includes certain information that may constitute "forward-looking information" under applicable Canadian securities legislation. Forward-looking information includes, but is not limited to, statements about strategic plans, future work programs and objectives and expected results from such work programs. Forward-looking information necessarily involve known and unknown risks, including, without limitation, risks associated with general economic conditions; inability to access sufficient capital from internal and external sources, and/or inability to access sufficient capital on favourable terms; and other risks.

Forward-looking information is necessarily based upon a number of estimates and assumptions that, while considered reasonable, are subject to known and unknown risks, uncertainties, and other factors which may cause the actual results and future events to differ materially from those expressed or implied by such forward-looking information and the risks identified in the Company's continuous disclosure record. There can be no assurance that such information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. Accordingly, readers should not place undue reliance on forward-looking information. All forward-looking information contained in this news release is given as of the date hereof and is based upon the opinions and estimates of management and information available to management as at the date hereof. The Company disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, except as required by law.

Neither the TSX Venture Exchange nor its Regulation Service Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this new release.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/69662

Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok