Exceptional PEA Results for the Marimaca Project including US$524 million post-tax real NPV8 and 33.5% IRR

2020-08-04 / @nasdaq

 

VANCOUVER, British Columbia, Aug. 04, 2020 (GLOBE NEWSWIRE) -- Marimaca Copper Corp. (“Marimaca Copper” or the “Company”) (TSX: MARI) is pleased to announce the results of the Preliminary Economic Assessment (“PEA”) for the Company’s flagship Marimaca Copper Project (“Marimaca” or “the Project”), located in northern Chile. The study confirmed that the Project has the potential to be a very low capital and operating cost copper producer. The Company will host a webinar to present the results of the study on Wednesday the 9th of September 2020.

Highlights

  • US$524 million post-tax NPV8 (real) assuming a US$3.15/lb flat long-term copper price
    • Payback of 2.6 years
    • Post-tax IRR of 33.5%
  • US$640 million post-tax NPV8 (real) assuming a US$3.45/lb flat long-term copper price
    • Payback of 2.4 years
    • Post-tax IRR of 38.0%
  • Average annual steady state EBITDA of US$169 million

  • Pre-production capital cost of US$285 million
    • Capital intensity of US$7,125/tonne of copper production capacity
    • Assumes mining fleet is purchased via lease to own to minimize upfront capital costs
  • Profitability Index (NPV/Capex) of 1.8x

  • Life of mine average all-in-sustaining cash costs of US$1.29/lb of copper1
    • Life of mine average C1 Cash Costs of US$1.22/lb of copper2
  • Conventional open pit mining focused exclusively on oxide mineralization
    • Life of mine stripping ratio of 0.84:1
    • Highest grade feed materials available in first five years of production resulting in improved payback and overall economics
  • Conventional heap leach, SX-EW, processing circuit
    • Projected average life of mine metallurgical recoveries in heap leach of approximately 76% of total copper supported by data from several metallurgical testing programs
    • Process makes use of readily available sea water
  • Average annual steady state copper production over first 6 yrs of close to 40,000 tonnes of cathode
    • Total mine life of 12 years
    • Total recovered copper of approximately 430,000 tonnes over the life of mine
  • Significant ongoing exploration potential for both oxide and sulphide mineralization which could substantially extend the mine life of the Project

The Preliminary Economic Assessment is considered preliminary in nature and includes Inferred Mineral Resources that are considered too speculative, geologically, to have the economic considerations applied that would enable classification as Mineral Reserves. There is no certainty that the conclusions within the PEA will be realized. The PEA is based on the material assumptions outlined in this document. These include assumptions about the availability of funding. While the Company considers all of the material assumptions to be based on reasonable grounds, there is no certainty that they will prove to be correct or that the range of outcomes indicated by the PEA can be achieved.

No mineral reserves have been estimated for the project. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability.

Luis Tondo, CEO of Marimaca Copper commented:

“The exceptional results of the PEA have confirmed our belief that Marimaca is a development stage copper project of the highest quality. Its pre-production capital costs places it in the very lowest tranche of projects in the copper development space, while its low operating costs, which places it in the bottom quartile of operating copper mines globally, means that the project will be profitable even in lower copper price environments.

“The Marimaca Project is substantially more de-risked than a typical PEA level project due, primarily, to the significant amount of technical work we have already completed, which includes four phases of metallurgical testing, geotechnical studies, nearly 100,000 metres of drilling over the Project and engagement with various input providers for the Project.

“In a commodity which is dominated by large, technically challenging projects in difficult jurisdictions, that carry with them a level of development and operating risk commensurate with their size and complexity, Marimaca represents a copper development project at the other end of the spectrum. Marimaca is a project, located in a tier 1 mining jurisdiction, that can be both financed and built with lower levels of execution risk, and which provides a platform for Marimaca Copper to become a mid-tier copper producer in the future.”

Figure 1: 2026 Projected All-in-Sustaining Cash Cost Curve:
https://www.globenewswire.com/NewsRoom/AttachmentNg/897d8c4f-96af-4c1a-899b-a11f075647de 

Executive Summary of Preliminary Economic Assessment

The Preliminary Economic Assessment (“PEA”) for Marimaca was completed by Ausenco Engineering in conjunction with several Qualified Persons in various technical fields including NCL Ingeniería y Construcción SpA (“NCL”) for mining and mine design and mineral resource estimation, and Jo Loyola Consultores de Procesos SpA (“JLCP”) on metallurgy and process design.

The PEA was prepared in accordance with the requirements of the National Instrument 43-101, Standards of Disclosure for Mineral Projects, (“NI43-101”) and is based on a Mineral Resource Estimate (“MRE”) completed by NCL, which comprised 70 million tonnes, with an average grade of 0.60% total copper within the Measured & Indicated Categories of mineral resources (approximately 420Kt of contained copper), and 40 million tonnes with an average grade of 0.52% total copper within the Inferred Category of mineral resources (approximately 224kt of contained copper) (refer release on 2 December 2019). The Preliminary Economic Assessment is considered preliminary in nature and includes Inferred Mineral Resources that are considered too speculative, geologically, to have the economic considerations applied that would enable classification as Mineral Reserves. There is no certainty that the conclusions within the PEA will be realized. The PEA is based on the material assumptions outlined in this document. These include assumptions about the availability of funding. While the Company considers all of the material assumptions to be based on reasonable grounds, there is no certainty that they will prove to be correct or that the range of outcomes indicated by the PEA can be achieved.

No mineral reserves have been estimated for the project. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability.

Marimaca is amenable to bulk, open pit, mining methods and this study contemplates an owner operated fleet utilising a leasing option to minimise upfront capital costs associated with fleet purchase. The deposit’s favourable geometry provides the Project with a low life of mine strip ratio of 0.84:1 as well as higher average grade in the first five years of mine life. This shortens the capital payback period and improves overall economics for the Project.

Due to the oxide resource, processing is via a standard heap leach and Run-of-Mine (“ROM”) leach using sulphuric acid and seawater followed by conventional solvent extraction and electrowinning to produce an average of nearly 40,000 tonnes per annum of high grade copper cathode during steady state production. Heap leach pads are designed as dynamic leach pads where leach residue, known as ripios, are removed after the leaching cycle and stored in a dedicated waste facility. ROM leach pads are designed as static leach pads, with stack height increasing over the life of the mine.

Average recovery over the life of mine for the heap leach is estimated to be approximately 76% of total copper, and ranges from a high of approximately 82% in the pure oxide zones (brochantite / atacamite), which make up the majority of the project, down to approximately 49% in the enriched mineral subzone, which comprises a much smaller proportion of the overall mineable resource. Recovery over the life of mine for the ROM leach is estimated to be approximately 40% of total copper, comprising 9% of the estimated total copper cathode produced during the life of mine.

Summary of Economic Assumptions and Results

Copper Price AssumptionUS$3.15/lb flat real
Pre-Tax NPV8 & IRRUS$757 million  /  39.9%
Post-Tax NPV8 & IRRUS$524 million  /  33.5%
Payback Period from First Production2.6 years
Pre-Production Capital CostsUS$285 million3
Life of Mine Sustaining CapitalUS$66 million
Ave. Annual Steady State EBITDAUS$169 million
Life of Mine C1 Operating CostsUS$1.22/lb of copper4
Life of Mine All-in-Sustaining Cash CostsUS$1.29/lb of copper5
Mine Life12 years
Ave. Annual Metal Production (first 6 years)Approximately 40,000 tonnes
Ave. Annual Metal Production Life of Mine (incl. ramp up)35,600 tonnes
Steady State Average Process Recovery (Heap and ROM)76%  /  40%

Table 1: Summary of Economic Assumptions and Results

Economics and Sensitivity Analysis

Copper Price
US$/lb
Post-Tax NPV8
Base Case
US$ millions
Post-Tax NPV8
Capex (-10%)
US$ millions
Post-Tax NPV8 Capex (+10%)
US$ millions
Post-Tax NPV8
Opex (-10%)
US$ millions
Post-Tax NPV8 Opex (+10%)
US$ millions
Base Case
IRR
(%)
2.8540843438145536028.6%
3.0046649243951441831.1%
3.1552455049857247633.5%
3.3058260855663053535.7%
3.4564066661468859238.0%

Table 2: Sensitivity Analysis to Copper Price, Life of Mine Capital and Operating Costs

PRELIMINARY ECONOMIC ASSESSMENT OF THE MARIMACA COPPER PROJECT

Geology and Mineral Resource Estimate

The Marimaca Project comprises a dominant structural feature of broad zones of sheeted dykes and fracture zones, oriented north-north-east and dipping 45-60o to the east, which host copper mineralisation at surface. The location of the Marimaca deposit is interpreted to be controlled by a dilational structural jog and the Company believes that this control applies both to the MOD and to its downwards continuation into the sulphide zone. There is strong evidence that the oxide zones encountered at surface were generated as a result of the in-situ oxidation of primary sulphide minerals, mostly chalcopyrite.

The PEA is based on the MRE, which was released to the market in January 2020 (refer to release on 2 December 2019). The PEA includes Inferred Mineral Resources that are considered too speculative, geologically, to have the economic considerations applied that would enable classification as Mineral Reserves. There is no certainty that the conclusions within the PEA will be realized. The PEA is based on the material assumptions outlined in this document. These include assumptions about the availability of funding. While the Company considers all of the material assumptions to be based on reasonable grounds, there is no certainty that they will prove to be correct or that the range of outcomes indicated by the PEA can be achieved.

No mineral reserves have been estimated for the project. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability.

The MRE was based on 346 reverse circulation holes (“RC”) and 39 diamond holes (“DD”) for a total of 91,210m drilled between 2016 and 2019 and was completed at a range of Cut-Off grades by independent consultants NCL Ingeniería y Construcción SpA (“NCL”). To demonstrate reasonable prospects for eventual economic extraction, a series of Lerchs-Grossmann pit shell optimizations was completed by NCL, utilizing appropriate operating costs, recoveries obtained from metallurgical test work, and a long term US$3.00/lb copper price. The resources were estimated only for oxide, mixed, wad and enriched copper mineralization which can be processed by heap leaching (HL) and run of mine (ROM) dump leaching followed by solvent-extraction and electrowinning to produce copper cathode. Primary sulphide mineralization occurring in deeper parts of the deposit, which are within the constraining pit shell, is not included in the MRE or for the purposes of this PEA.

Cut-off

grade

(% CuT)
MeasuredIndicatedMeasured + IndicatedInferred
Mineral
kt
CuT
(%)
CuS
(%)
Mineral
kt
CuT
(%)
CuS
(%)
Mineral
kt
CuT
(%)
CuS
(%)
Mineral
kt
CuT
(%)
CuS
(%)
0.4014,4030.810.5530,6000.740.4845,0030.760.5023,6070.700.40
0.3017,8650.720.4940,2530.640.4258,1180.670.4433,4100.600.35
0.2220,7210.660.4449,6660.570.3770,3870.600.3943,0150.520.31
0.1822,0720.630.4254,1090.540.3576,1810.570.3747,1640.490.29
0.1023,0870.610.4157,6190.520.3380,7060.540.3550,6410.470.27

Table 3: NI43-101 Mineral Resource Estimate at Various Cut-off Grades

* CuT means total copper and CuS means acid soluble copper. Mineral resources that are not mineral reserves do not have demonstrated economic viability. Mineral resource technical and economic parameters included: copper price US$3.00/lb; mining cost US$2.00/t; HL processing cost including G&A US$9.00/t; ROM processing cost including G&A US$2.50/t; selling cost US$0.07/lb Cu; heap leach recovery 76% of CuT; ROM recovery 40% of CuT and a 44°-46°pit slope angle

The deposit has a significant higher-grade zone which occurs from surface in its southern extent and provides a logical target for the early years of mine life at Marimaca. The average grade expected during the first five years of mine life is 0.78% total copper and is dominantly comprised of the main oxide mineral sub-zones of brochantite, atacamite and chrysocolla.

Significant potential exists to increase oxide resources within proximity to Marimaca, but also in the broader claims packages that surround this exciting project. Furthermore, the Company has recently released the results of a high-resolution, drone mounted, magnetic survey, which indicates substantial potential for sulphide mineralization below the Marimaca Oxide Deposit (refer to announcement on 14 July 2020).

Figure 2: Plan View and Long Section of Mineral Resource Estimate Highlighting High Grade Zones from Surface:
https://www.globenewswire.com/NewsRoom/AttachmentNg/5785acc6-b876-4397-8d8f-b4f656f64d55

Mining

The Marimaca Oxide Deposit commences at surface and its geometry means that it is amenable to bulk, open pit, mining methods, which have been contemplated for the purposes of this study. The study considers an owner operated mining fleet based on lease to own contracts with reputable heavy equipment providers.

The mine will utilise convention drilling, blasting and shovel loading into trucks on bench heights of 10-20 m depending on location within the open pit. The mine plan was designed to deliver a consistent production profile of approximately 40,000 tonnes per annum of copper cathode during steady state operations.

The open pit was designed based on eight phases of development targeting the higher grade, dominantly oxide, mineralisation in the central portion of the deposit area in the early years of the mine life and gradually expanding, and deepening the pit, over the mine life.

Due to the higher grade of the early years of mine life, the heap leach production tonnes in years 1 to 5 are designed to average approximately 5.4Mtpa before increasing from year 6 onwards to approximately 9.0Mtpa of material. The ROM leach production was designed to be variable to minimize the use of stockpiles, which can add complexity to the mine planning and management, and ranges from a low side of 588ktpa up to a maximum of 6Mtpa of ROM leach material.

Figure 3: Open Pit Development Phases:
https://www.globenewswire.com/NewsRoom/AttachmentNg/d99e868b-a34d-4ea9-9c2b-bc5218e204be 

The open pit has a low life of mine strip ratio (including pre-stripping) of 0.84:1. The strip ratio has decreased from the mineral resource estimate (at a cut-off of 0.22% total copper) because, in mine planning, it was noted that numerous areas of mineralized waste (less than 0.22% total copper) are mined in the proposed PEA mine plan. Although they may be considered as marginal on the heap leach, these tonnes are considered to be economic on the ROM leach, where the additional costs of crushing and agglomeration are removed. As a result, these tonnes, which would have previously been classified as waste, have now been classified as mineable resource for the purposes of copper production.

Figure 4: Life of Mine Production Plan:
https://www.globenewswire.com/NewsRoom/AttachmentNg/ac87d17a-2062-44e8-86ec-8d0e9d21c298 

Based on the geotechnical information obtained from the extensive drilling campaigns conducted at Marimaca, the mining area was divided into three clear geotechnical zones. In Zone 1, due to favorable geotechnical conditions the overall pit slope angle was designed at approximately 52 degrees utilising double benching at 20 m heights and face angle of 75 degrees. In Zone 2, the overall pit slope angle was reduced to approximately 42 degrees utilising 10 m bench heights and a bench face angle of 70 degrees. Zone 3 was similar to Zone 2, but with a bench face angle of 75 degrees, which slightly increased the overall slope angle to nearly 45 degrees.

In general, the rocks encountered in the hanging and footwall zones appear to show a good degree of competency, but further geotechnical work will be required to confirm these design parameters for future studies.

Figure 5: Open Pit Geometry:
https://www.globenewswire.com/NewsRoom/AttachmentNg/1ed6b18f-195f-4d5c-b6dd-edd36b952f57 

Metallurgical Testing

The Company has completed three phases of metallurgical test work between April 2017 and March 2018, with a fourth phase completed in July 2020. The results of Phases 1, 2 and 3 were included in the NI43-101 Definitive Feasibility Study for Marimaca 1-23, released on the 29th of June 2018. Phase 4 metallurgical testing is underway.

These tests have been carried out by Geomet S.A., a well-known Chilean laboratory with considerable experience in metallurgical programs for copper deposits in Chile. Phase 4 has been designed and executed under the supervision of Marcelo Jo of Jo & Loyola Process Consultants, who has 35 years’ experience in processing. He is supported by Randolph E. Scheffel, a Consultant Metallurgical Engineer with over 45 years’ experience in copper processing.

The tests in Phases 1, 2 and 3 were completed on materials obtained from Marimaca to characterise the metallurgical response of the deposit to different operational conditions. Samples were selected to consider the various mineral subzones defined at Marimaca, classified based on dominant mineralogy, including oxide, wad, mixed and enriched. The first three phases were performed on a variety of parameters including agglomeration conditions, granulometry, column height, irrigation rates and acid consumption. These tests were followed up with more detailed analysis including bottle roll Iso-pH tests. For these tests, samples were also selected to consider the various mineral subzones defined at Marimaca including oxide, wad, mixed and enriched.

The fourth phase program comprised broader, more detailed and rigorous tests, including mini and full-scale column tests with and without seawater.

While the PEA has been based, primarily, on the metallurgical results from Phases 1, 2 and 3 metallurgical programs (refer to announcement from 24 June 2020), the recent results from the Phase 4 program have confirmed that the material from Marimaca is amenable to heap leaching with sulphuric acid, with relatively fast leach kinetics, industry average acid consumption, relative to similar materials, and expected recoveries of approximately 76% of total copper across the life of mine. Recoveries are variable across mineral sub-zones and are expected to be highest in the dominant brochantite/atacamite zones, at approximately 82% of total copper, and lowest in the enriched zones, at approximately 49%. The LOM recoveries for the ROM leach is expected to be 40%.

Processing

The PEA contemplates the recovery of copper using a conventional heap and ROM leach followed by standard solvent extraction and electrowinning to produce high grade copper cathode. Due to the desert location, with limited flora and fauna, the project considers the use of seawater, pumped less than 25km from the coast, meaning no local aquifers will be exploited.

Figure 6: Schematic Overview of Heap Leach Solvent Extraction-Electrowinning Processing of Copper Ores at Marimaca:
https://www.globenewswire.com/NewsRoom/AttachmentNg/1857cde4-d009-433a-b652-e7d4bcae105f 

Coarse heap leach material is trucked from the open pit to be fed directly into the primary crushing plant. It is then crushed using a two-stage crushing process in closed circuit with screens to achieve sizing of P80 passing half an inch following which it is sent for agglomeration using sulphuric acid diluted with seawater. Given the low quantity of fine materials and clays observed in the mineral types to be mined at Marimaca, it is expected that the risk of generation of impermeable layers and occurrence of channelling, which can negatively impact heap leach recoveries, will be minor. Agglomeration is used primarily to create an agglomerated material with fines attaching to the coarser material, which also improves stability and to add sulphuric acid to the heap leach material prior to stacking on the leach pads. Lower grade ROM material, which is not considered to be economic through the crushing and agglomeration steps, is sent directly to the ROM leach pads without further preparation.

Figure 7: Mass Flow Diagram of Liquids in Heap and ROM Leach:
https://www.globenewswire.com/NewsRoom/AttachmentNg/c60073d3-cf1d-4a2c-90be-d6d1dff9417c 

A stack height of 4 metres was considered as the design basis for the heap leach pad(s) and up to 20 metres high for the ROM leach pads. The ROM leach pad is designed to be a permanent pad, while the heap leach pads are designed to be on-off (dynamic) pads, which have become very common in heap leach operations in Chile, where the leached residues (known as ripios) are removed from the pads and stored in a dedicated waste facility.

The leaching pad areas will be designed in two stages based on the feed grade delivered from the mine plan. In the first stage, which is designed for the higher-grade materials available in the first five years of mine life, the design contemplates 11 leach pads with a total surface are of 308,000 m2. In the second phase, which includes years six to twelve, an additional 7 leach pads are constructed, increasing the total surface area to 504,000 m2. The larger footprint takes into account the higher tonnage and lower expected grade which will be processed during the second half of the mine life in order to ensure a consistent production profile of approximately 40,000 tonnes of copper per annum is delivered to the SX-EW plant. Both heap and ROM leach pads are irrigated using a conventional recycled raffinate from the solvent extraction phase with additional sulphuric acid added as required based on the acid consumption profile of the various mineralogies being treated. Leaching occurs in two cycles of approximately 52 and 40 days respectively for total leaching time of 92 days. Following the first cycle, an Intermediate Leach Solution (“ILS”) is recirculated through the heap leach before sending the Pregnant Leach Solution (“PLS”) to the SX-EW plant for final processing.

The main water consumption of the project it is related to the heap leaching process. The Company will utilize seawater with an average rate of 0.25 m3/t for oxide feeds, 0.28 m3/t for sulphide feeds, and 0.125 m3/t of ROM leach feed. Considering seasonal fluctuations as well as other requirements of water and the variation in amount of material treated annually, a nominal feed rate of up to 100 l/s is being considered for sea water supply.

The main power consumption of the project will be related to the Electrowinning process. The Company will utilize an average of 123 MWh/year during the first 5 years, increasing to an average of 143 MWh/year for the remaining project life.

Material Storage Facilities

The Company is proposing the use of on/off leach pads which will necessitate the development of a separate waste dump facility for the storage of the ripios or leached residue. These have been designed using standard Chilean protocols, to minimise potential leakage into the surrounding environment of any residues which may present an environmental risk.

The ripios waste dumps will have approximately a total lined base surface of 1,500,000 m2. The stack height of the ripios storage facilities will be increased over the 12-year life of the mine and will house approximately 88 million tonnes of material stored and requiring future rehabilitation.

Two mine waste storage facilities areas, to be located to the west and south of the pit, were designed for the project. The facilities were designed in 40 m lifts. Each lift will be constructed at an approximate angle of repose of 37°.

A ROM pad area was designed in a flat valley, located in between the mine waste storage facilities, where the ROM leach process will take place. The leaching of this lower grade material is planned in 10-20 m lifts. The design of the facility was developed every three 10 m lifts at an approximate angle of repose of 37° and a set-back of 27 m, resulting in an overall slope angle no higher than 22° and a maximum slope height of 100 m.

The mine plan considers the stockpiling of some lower grade material for later re-handling at the end of the life of mine to the primary crusher for heap leaching. The low-grade stockpile was designed at the toe of the south waste storage facility at an approximate angle of repose of 37° and a total height of 50 m.

Infrastructure & Location

Marimaca benefits from an outstanding location, proximate to all infrastructure required to develop an open pit, SX-EW copper mine. Infrastructure requirements include water supply, power supply, access roads, sulphuric acid supply and other facilities.

Power Supply

The PEA contemplates that the power required for the project will be taken from the national grid, which provides stable, low cost, electricity. The most convenient connection will be with an existing 110 kV line, which runs approximately 7 km to the north of the proposed plant site at its closest point. For this PEA it is assumed a 7 km, 110 kV, spur line will be built to the main mine substation, which will be placed close to the SX/EW plant at the Marimaca plant site. The substation will be 30 MW capacity with a step down from 110kV to 23 kV for distribution around the plant site.

Water Supply

Marimaca Copper has approached several utility companies in the Mejillones area, which are offering to build, maintain and operate a pipeline from their sea water intake to the Marimaca leaching facility and sell the water to the project at the plant site. The PEA contemplates the installation of a 6 km long pipeline extending from an existing third-party seawater pipeline and will discharge into the main water reservoir at Marimaca. The head pond has been designed with a capacity of 40,000 m3, which represents 5 days of water feed at normal operating rates. From the head pond, water will be distributed to the different centers within the broader processing facility. One center will contain a small reverse osmosis plant to produce fresh water which will be required for a small number of processing stages as well as other installations.

Figure 8: Map Showing Proximity to Key Infrastructure for Marimaca:
https://www.globenewswire.com/NewsRoom/AttachmentNg/45e844f8-b1bc-4471-a389-8435acbecc5e 

Site Layout and Infrastructure

The PEA contemplates the leach pads, ripios dumps and process plant infrastructure being located in a valley to the west of the Marimaca deposit. The valley provides a relatively flat area, which will minimize the requirement for cut and fill earthworks, while providing sufficient space for the various components of the mine site.

Figure 9: Mine Site Layout:
https://www.globenewswire.com/NewsRoom/AttachmentNg/c2fd15d6-8672-4951-abf5-74a72fa0e029

Roads

The Project benefits from several roads which fall under the responsibility of the local and regional government and, therefore, are not required to be upgraded or maintained by Marimaca Copper. Marimaca is accessible from Route 1, which is a paved highway that joins Antofagasta and Mejillones to the cities further to the north. The Mejillones Route B-240, which is a non-paved road branches off Route 1 to the east.

Approximately 10 km to the east of the junction of Route 1 and the B-240, there is an existing gravel road which branches to the south and leads to the proposed Marimaca plant site, which is approximately 7 km to the south. A similar standard is anticipated to be used for the construction of internal roads which connect the different mine and plant installations. The haulage road which mine trucks will use to carry the material from the mine to the primary crusher is included as part of the mine design.

Figure 10: Non-Paved B-240 Road with Bischofite Covering (Left) and Road to Proposed Plant Site (Right):
https://www.globenewswire.com/NewsRoom/AttachmentNg/e524b943-047e-48f5-8f72-0b198e223f09

Capital and Operating Costs

The projected pre-production capital costs for Marimaca, which will be incurred over a 2-year construction period, were estimated on the basis of information from a variety of sources including direct equipment quotes, derivation from first principles and factoring from comparable benchmarks, and are summarized in the following table:

ITEMCOST ESTIMATE
US$ millions
Mining Equipment6$14.0
Mine Development$9.2
Crushing & Agglomeration$22.7
Leaching$43.5
SX-EW Plant$81.1
Infrastructure (incl acid tanks, power supply, buildings)$14.7
Sub Total Direct$185.1
Indirect Costs$42.6
Contingency$56.9
Total Pre-Production Capital Cost$284.7

Table 4: Summary of Estimated Pre-Production Capital Costs

ITEMCost Estimate
US$ / tonne of material processed
Cost Estimate
US$ / lb of Copper
Mining (incl. grade control, drill & blast, load and haul)$3.19$0.44
Processing Costs (incl crushing, acid, SX-EW and ripios disposal)$4.95$0.69
G&A$0.54$0.09
Total Operating Cost$8.68$1.22

Table 5: Summary of Estimated Average Life of Mine Operating Cost per Tonne of Material Processed

The Preliminary Economic Assessment is considered preliminary in nature and includes Inferred Mineral Resources that are considered too speculative, geologically, to have the economic considerations applied that would enable classification as Mineral Reserves. There is no certainty that the conclusions within the PEA will be realized. The PEA is based on the material assumptions outlined in this document. These include assumptions about the availability of funding. While the Company considers all of the material assumptions to be based on reasonable grounds, there is no certainty that they will prove to be correct or that the range of outcomes indicated by the PEA can be achieved. 

No mineral reserves have been estimated for the project. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability.

Technical Reporting and Qualified Persons

The NI43-101 technical report will be released within 45 days of this news release and will be available for review on Marimaca’s website and SEDAR. The technical report will be authorised and signed off by the following Qualified Persons:

Qualified PersonCompanyPEA SectionProfessional Affiliation / Registration
Francisco CastilloAusenco Chile LtdaChapters 1 to 3 and 17 to 27Competent person in mining engineering N° register 179 Chile
Robin KalancheyAusencoChapters 17, 21 and 22Competent person in metallurgical engineering Canada
Luis OviedoNCL Ingeniería y Construcción SpAChapters 4 to 12 and 14Competent person in geology N° register 013 Chile
Carlos GuzmanNCL Ingeniería y Construcción SpAChapter 15 and 16Competent person in mining engineering FAusIMM N° register 229036 Australia
Marcelo Jo LópezJo y Loyola Process ConsultingChapter 13Competent person in extractive metallurgy N° register 360 Chile

The QPs confirm that they have visited the Marimaca Project, have verified, and are responsible for, the information contained in this news release and consent to its publication.

Contact Information

For further information please visit www.marimaca.com or contact:

Tavistock
+44 (0) 207 920 3150
Jos Simson/Emily Moss
marimaca@tavistock.co.uk

Forward Looking Statements

This news release includes certain “forward-looking statements” under applicable Canadian securities legislation. These statements relate to future events or the Company’s future performance, business prospects or opportunities. Forward-looking statements include, but are not limited to, the impact of a rebranding of the Company, the future development and exploration potential of the Marimaca Project. Actual future results may differ materially. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Forward-looking statements reflect the beliefs, opinions and projections on the date the statements are made and are based upon a number of assumptions and estimates that, while considered reasonable by Marimaca Copper, are inherently subject to significant business, economic, competitive, political and social uncertainties and contingencies. Many factors, both known and unknown, could cause actual results, performance or achievements to be materially different from the results, performance or achievements that are or may be expressed or implied by such forward-looking statements and the parties have made assumptions and estimates based on or related to many of these factors. Such factors include, without limitation: risks related to share price and market conditions, the inherent risks involved in the mining, exploration and development of mineral properties, the uncertainties involved in interpreting drilling results and other geological data, fluctuating metal prices, the possibility of project delays or cost overruns or unanticipated excessive operating costs and expenses, uncertainties related to the necessity of financing, the availability of and costs of financing needed in the future as well as those factors disclosed in the Company’s documents filed from time to time with the securities regulators in the Provinces of British Columbia, Alberta, Saskatchewan, Manitoba, Ontario, New Brunswick, Nova Scotia, Prince Edward Island and Newfoundland and Labrador. Accordingly, readers should not place undue reliance on forward-looking statements. Marimaca Copper undertakes no obligation to update publicly or otherwise revise any forward-looking statements contained herein whether as a result of new information or future events or otherwise, except as may be required by law.

1 All in sustaining costs is defined as cash cost (C1) plus general and administrative expenses, sustaining capital expenditure, deferred stripping, royalties and lease payments and is used by management to evaluate performance inclusive of sustaining expenditure required to maintain current production levels.

2 C1 cash cost includes all mining and processing costs less any profits from by-products and is used by management to arrive at an approximated cost of finished metal.

3 Assumes mining fleet is financed through a lease to own contract structure to minimize upfront capital cost.

4 All in sustaining costs is defined as cash cost (C1) plus general and administrative expenses, sustaining capital expenditure, deferred stripping, royalties and lease payments and is used by management to evaluate performance inclusive of sustaining expenditure required to maintain current production levels.

5 C1 cash cost includes all mining and processing costs less any profits from by-products and is used by management to arrive at an approximated cost of finished metal.

6 Assumes mining fleet is financed using a lease to own contract structure to minimize upfront capital cost.

Primary Logo

Figure 1

2026 Projected All-in-Sustaining Cash Cost Curve
Figure 2

Plan View and Long Section of Mineral Resource Estimate Highlighting High Grade Zones from Surface
Figure 3

Open Pit Development Phases
Figure 4

Life of Mine Production Plan
Figure 5

Open Pit Geometry
Figure 6

Schematic Overview of Heap Leach Solvent Extraction-Electrowinning Processing of Copper Ores at Marimaca
Figure 7

Mass Flow Diagram of Liquids in Heap and ROM Leach
Figure 8

Map Showing Proximity to Key Infrastructure for Marimaca
Figure 9

Mine Site Layout
Figure 10

Non-Paved B-240 Road with Bischofite Covering (Left) and Road to Proposed Plant Site (Right)

Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok