TORONTO, April 10, 2018 (GLOBE NEWSWIRE) -- Kerr Mines Inc. (TSX:KER) (OTC:KERMF) (FRA:7AZ1) (“Kerr” or the “Company”) is pleased to announce the results of the independent Pre-Feasibility study (“PFS”, “Study”) and resource update prepared by Hard Rock Consulting, LLC in accordance with National Instrument 43-101 (“NI 43-101”) for its past producing Copperstone Mine in Arizona, USA. On the momentum of a very successful 2017 Phase I exploration program and this PFS, the Company is pleased to confirm updated gold resources and positive economics at the Company’s Copperstone Mine in Arizona.
|
Copperstone PFS Highlights (all values US$ unless otherwise noted):
“The results of this PFS display the strong near-term production opportunity for the Copperstone Mine and robust returns for our investors. This is just the beginning," says Martin Kostuik, President. “The impressive exploration upside displayed by the 2017 Phase I program, the historical production of over 500,000 gold ounces and the potential to generate solid positive cash flows by identifying the first four years of gold production, all point toward the opportunity of many more years, beyond the Study timeframe, of profitable production. In fact, there are 100,000 gold ounces of M&I mineral resources that were not included in the P&P mineral resources, part of which are immediately accessible for drilling and potential inclusion.” Kostuik continued, “Our intention is to finance the initial capital through corporate debt. We are currently engaged in discussions focused on non-dilutive financing options with several lending groups to finalize our forthcoming production decision. Furthermore, we shall continue our efforts to enhance shareholder value by pursuing other value-adding activities such as conducting an intense 2018 exploration program which is designed to increase mine life”
Geology and Mineral Resource Estimate
The updated Mineral Resource Estimate was developed by Hard Rock Consulting, LLC (“HRC”). In order to support the mineral resource estimate, Kerr completed over 8,100 meters of infill and step-out drilling in the summer and fall of 2017.
The Copperstone deposit is a mid-Tertiary, detachment fault related gold deposit. Mineralization is predominantly controlled by the northwest trending shallow angle Copperstone fault and shear zone. These structures are not confined to any lithologic unit, although the majority of the mineralization is hosted in quartz latite porphyry. Breccia textures as well as chloritization, silicification, and hematite and specularite flooding are reliable indications of gold mineralisation.
On February 24th, 2018, HRC completed an updated mineral resource estimate. The last NI 43-101 resource report on the Copperstone Project was released in 2011, the estimate used a gold capping grade of 5 troy ounces per short ton and was domained primarily by gold grades. In order to support the mineral resource update, Kerr completed over 8,100 meters of infill and step-out drilling in the summer and fall of 2017. Since the 2011 report, the drillhole database includes 9,062 additional meters and an additional 5,552 gold grade determinations. HRC applied a more aggressive and restrictive capping analysis resulting in a more conservative model than previous estimates.
The drill hole database was vetted to identify missing values, duplicate records, interval overlap errors, from-to data exceeding maximum collar depth, and special (i.e. non-numeric or less than zero) values. Errors identified by the mechanical audit were reviewed with Kerr staff and resolved prior to modelling and calculation of the mineral resource estimate. In addition, 665 holes of historic core drill logs totaling 83,265 meters were re-interpreted for alteration and digitized for inclusion into the 2017 resource estimate program database. A random manual check of 10% of the assay database against original certificates was conducted by HRC. The error rate within the database is considered to be less than 1% based on the number of samples spot checked. Identified errors were corrected prior to modelling and calculation of the mineral resource estimate.
Gold grades were constrained within estimation domains modelled with 3D wireframe solids. Estimation domains follow the overall northwest, shallowly dipping structural trends, and were defined by drillhole interval selections of gold grades greater than or equal to 3.43 g/tonne (0.100 troy ounces per short ton, “oz/ton”). Domains were reviewed in 3D to ensure the models agree with the overall geologic interpretation and maintained continuity along strike and down dip. Samples were composited inside estimation domains to a target length of 1.5 meters. Composite gold grades within each domain were reviewed for statistically high outliers, which were then constrained and capped. The capping analysis considered each domain separately and a global gold cap was not used. Semi-variograms from composites were used to inform the search ellipse. Densities were determined inside and outside estimation domains by lithology from drill core.
Of 959 drill holes included in the mineral resource estimate, 716 drillholes intersected mineralised domains. 2,748 composites were used to interpolate grade into 6.1 x 6.1 x 1.5-meter (20 x 20 x 5 feet) blocks rotated and oriented along strike and down dip and sub-blocked to a minimum block size 6.1 x 1.5 x 0.3 meters (20 x 5 x 1 feet) using an ordinary kriging algorithm. Blocks mined out by open pit and underground operations were removed from the resource estimate.
HRC concludes that the sample preparation, security and analytical procedures are appropriate and adequate for the purpose of this Technical Report. The sample methods and density are appropriate, and the samples are of sufficient quality to comprise a representative, unbiased database.
Zachary J. Black, SME-RM, a Resource Geologist with HRC is responsible for the mineral resource estimate presented herein. Estimated blocks were classified as either Measured, Indicated, or Inferred, in accordance with CIM definition standards adopted by CIM Counsel on May 10, 2014, based on the minimum distance from composites to the block, the number of composites used to estimate a block, and the geologic/geospatial support for the domain. The mineral resources are confined of material exceeding the cut-off grade of 3.43 g/tonne (0.100 oz/ton) within coherent wireframe models. The cutoff is based on the following assumptions: a long-term gold price of $1,375/oz; assumed mining cost of $74/ton, process costs of $40/ton, general and administrative and property/severance tax costs of $14/ton, refining costs of $4.65/oz and metallurgical recovery for gold of 95%.
Mineral Resource Classification | Tonnes ('000's) | Tons ('000's) | Gold Grade grams/tonne oz/ton | Contained Gold ('000 oz) | |
Measured | 478.1 | 527.0 | 8.33 | 0.243 | 128.0 |
Indicated | 646.7 | 712.9 | 7.12 | 0.208 | 148.0 |
Measured + Indicated | 1,124.8 | 1,239.8 | 7.63 | 0.223 | 276.1 |
Inferred | 666.0 | 734.1 | 6.81 | 0.198 | 145.7 |
Mine Plan and Mineral Reserves
A detailed mine plan was engineered using only Measured & Indicated Resources. Mechanized overhand cut and fill was chosen as the preferred mining method. Datamine’s® Minable Stope Optimizer (MSO) was used to generate the stopes utilizing a metal price of $1,250/oz for gold and a 3.77 g/tonne (0.111 oz/ton) gold cutoff.
The mine plan for the Project includes approximately 802,000 tonnes of ore grade material to be extracted by underground mining in 4.4 years. The mine production schedule calls for ore production of 544 tonnes per day and 762 tonnes of ore processed per mill working day, 5 days per week. Mining recoveries of 95% were applied and overall dilution factors averaged 25.3%. Dilution factors are calculated based on internal stope dilution calculations and external dilution factors of 10%. The Table below presents the annual mining schedule based on these assumptions. Due to the historic underground mining that has taken place on the property in 2012 and 2013 and the exploration drift put in by Kerr in the summer of 2017 there is a reduced amount of development required to get the mine up to full production.
Production Schedule | Study Totals | Year -1 | Year 1 | Year 2 | Year 3 | Year 4 | Year 5 |
MINE PRODUCTION | |||||||
Ore Mined (tonnes) | 802,048 | 52,089 | 207,331 | 219,449 | 170,688 | 144,070 | 8,421 |
Au Grade (g/tonne) | 6.79 | 7.22 | 6.70 | 6.86 | 6.63 | 6.83 | 6.82 |
Mine Development (meters) | 13,295 | 1,002 | 5,153 | 3,613 | 1,940 | 1,476 | 111 |
Development Waste (tonnes) | 487,159 | 40,203 | 202,717 | 139,695 | 57,501 | 43,750 | 3,292 |
Total Tonnes Mined | 1,289,207 | 92,292 | 410,047 | 359,145 | 228,189 | 187,821 | 11,713 |
Dr. Dermot Ross-Brown from Tierra Group International, Ltd completed a review of the past geotechnical studies and visited the current underground workings in order to provide an estimate of the required ground support and maximum opening sizes for the mine plan. Main ramp development headings are planned at 4.2m x 4.2m, ore access drifts are planned at 3.7m x 3m and stope heights are planned at 3.7m with a maximum width of 4.9m.
In order to select the preferred mining method, several trade-offs were conducted as part of the pre-feasibility study. The results are summarized below:
Mr. Jeffery Choquette, P.E., MMSA QP Member, of HRC is responsible for the mineral reserve estimate presented herein. The Proven and Probable mineral reserves for the Study as of April 1st, 2018 are summarized in the Table below.
Mineral Reserve Classification | Tonnes ('000's) | Tons ('000's) | Diluted Gold Grade grams/tonne oz/ton | Contained Gold ('000 oz) | |
Proven | 346.7 | 382.2 | 7.30 | 0.213 | 81.4 |
Probable | 455.4 | 501.9 | 6.40 | 0.187 | 93.7 |
Total Proven + Probable | 802.0 | 884.1 | 6.79 | 0.198 | 175.1 |
Processing
Kerr Mines and HRC contracted Resource Development Inc (RDI) who provided new metallurgical testing of the Copperstone deposit, confirmed prior metallurgical testwork and economically evaluated processing options. Metallurgical test work focused on the A, B, C, and D zones of the Copperstone Zone. Testing also confirmed bond work indexes, abrasion and density values. The production and sale of a doré bar versus sale of a gold concentrate has much lower offtake costs. Listed below is a description and results for three processing options:
Flotation Producing a Concentrate: This is the approach taken by the previous operators. The flotation concentrate is estimated to assay ± 500 g/tonne Au and would be sold to a broker or smelter. A marketing study is needed to determine the marketability and cost of sales for this grade of gold concentrate. The flotation circuit would consist of rougher flotation followed by two stages of cleaners to produce the required grade of concentrate. This confirms historical testwork and production results. Recoveries for gold from flotation for high grade saleable concentrate averaged 88%.
Flotation and Cyanide Leach of the Concentrate: The objective of this process is to produce a rougher concentrate maximizing recovery of gold, then leach the concentrate and produce a doré bar. Recoveries for gold from flotation concentrate produced for final leach averaged 90%. Testing for final recovery of gold from leaching the flotation concentrate is inconclusive and further testing is required.
Whole Ore Leach: WOL utilizes direct cyanidation leaching of the entire ore feed. This option also includes the production of a doré bar. WOL resulted in gold extraction of 88% to 97%. There exists an opportunity to decrease the Processing Cash Operating cost below the Study results with further cyanide consumption testwork, which is in progress.
WOL of Copperstone ore exhibits the highest operating costs of the three options but the increase in recoveries and elimination of concentrate smelter charges make this option economically superior. In addition, the existing processing plant will be simplified by eliminating both the course gold circuit and one of the mills. WOL leach was chosen as the base case processing scenario for the Study. The block flow sheet is shown below.
A photo accompanying this announcement is available at http://resource.globenewswire.com/Resource/Download/2d81a247-51f9-410e-8fab-ffba1554a736
Copper may be a by-product of mining economic gold ores and extracting the copper during the processing of the economic gold ore at the Copperstone Mine is at the early stages of being evaluated. The economics of monetizing copper as a by-product are potentially attractive as the cash costs of production are shared with the cash cost of producing the primary product – gold. Further exploration drilling, assaying and modelling work of copper bearing gold ore is required. Metallurgical testing for the economic extraction of copper is ongoing, but currently incomplete, and further testing is required. Copper may be incorporated into a compliant mineral resource dependent upon favorable metallurgical results, and a complete review of copper data for adequacy.
Project Case Economic Results
The Project Case for the Study includes mine mobile equipment financing costs with no financing cost applied to the remaining Initial Capital. Capital costs were developed for the plant upgrade, infrastructure needs, and mining. The table below shows the estimated initial capital costs for the upgrade and restart of the Copperstone Mine using the optimal project case of a WOL processing scheme and owner operated mining, with an equipment capital lease for mine equipment financing. The capital costs reflect the in-place infrastructure, buildings, and equipment which is a beneficial aspect of the Copperstone Mine.
Initial Capital | $USM |
Mine | 5.99 |
Mine Development & Infill Drilling | 5.38 |
Mill Upgrades | 3.52 |
Indirects, EPCM, Owners Cost | 4.02 |
Contingency | 3.83 |
Total Initial Capital | 22.74 |
The capital lease for the mining equipment is based on a major equipment manufacturer’s quote which includes a 3-year term at 10% interest and a 25% down payment. For this option, principal and interest payments reduce cash required from initial financing activity and gross capital costs are booked as assets on the balance sheet.
Economic analysis of the Project case uses a 3.77 gold g/tonne (0.111 oz/ton) cut-off grade and a gold price of US$1,250/oz, which is the 36-month trailing average price and $50/oz less than the closing spot price at the end of December 2017. The tables below summarize the results.
Before Tax | After Tax | |||||
$USM | 19.12 | Net Present Value (10.0%) | $USM | 17.91 | ||
% | 41.7 | % | Internal Rate of Return | % | 40.1 | % |
Yrs | 2.26 | Payback Period | Yrs | 2.27 |
Study Totals | Year -2 | Year -1 | Year 1 | Year 2 | Year 3 | Year 4 | Year 5 | ||||||||||
Gold Ounces in Doré | oz | 166,172 | 7,349 | 38,790 | 39,939 | 38,722 | 39,619 | 1,753 | |||||||||
Gross Revenue | $US | 207,714,250 | 9,186,375 | 48,487,000 | 49,923,625 | 48,402,250 | 49,523,375 | 2,191,625 | |||||||||
Cash Operating Costs | $US | (113,665,069 | ) | (4,615,312 | ) | (28,769,608 | ) | (27,427,293 | ) | (26,210,707 | ) | (24,553,976 | ) | (2,088,173 | ) | ||
Royalties | $US | (4,154,287 | ) | (183,728 | ) | (969,740 | ) | (998,473 | ) | (968,045 | ) | (990,468 | ) | (43,833 | ) | ||
Production Taxes | $US | (816,507 | ) | (57,138 | ) | (164,391 | ) | (169,687 | ) | (187,617 | ) | (237,674 | ) | - | |||
Total Operating Costs | $US | (118,635,863 | ) | (4,856,178 | ) | (29,903,739 | ) | (28,595,453 | ) | (27,366,369 | ) | (25,782,118 | ) | (2,132,006 | ) | ||
Operating Margin (EBITDA) | $US | 89,078,387 | 4,330,197 | 18,583,261 | 21,328,172 | 21,035,881 | 23,741,257 | 59,619 | |||||||||
Sustaining Capital/Closure | $US | (26,235,313 | ) | (500,000 | ) | (1,380,499 | ) | (13,314,127 | ) | (8,890,011 | ) | (4,261,740 | ) | (269,937 | ) | 2,381,000 | |
Site All-In Sustaining Cost* | $US | (144,871,176 | ) | (500,000 | ) | (6,236,677 | ) | (43,217,866 | ) | (37,485,464 | ) | (31,628,109 | ) | (26,052,055 | ) | 248,994 | |
Investment Capital | $US | (22,737,126 | ) | (603,670 | ) | (22,133,457 | ) | ||||||||||
Site All-In-Cost* | $US | (167,608,303 | ) | (1,103,670 | ) | (28,370,134 | ) | (43,217,866 | ) | (37,485,464 | ) | (31,628,109 | ) | (26,052,055 | ) | 248,994 | |
Cash Flow, pre-Tax | $US | 40,105,947 | (1,103,670 | ) | (19,183,759 | ) | 5,269,134 | 12,438,161 | 16,774,141 | 23,471,320 | 2,440,619 | ||||||
Interest Expense | $US | (1,865,121 | ) | (450,161 | ) | (853,257 | ) | (474,699 | ) | (87,003 | ) | ||||||
State & Federal Income Tax | $US | (1,961,421 | ) | (623,798 | ) | (2,662,724 | ) | 1,325,101 | |||||||||
Free Cash Flow | $US | 36,279,406 | (1,103,670 | ) | (19,633,920 | ) | 4,415,877 | 11,963,463 | 16,063,340 | 20,808,596 | 3,765,720 | ||||||
Cumulative Free Cash Flow | $US | (1,103,670 | ) | (20,737,589 | ) | (16,321,713 | ) | (4,358,250 | ) | 11,705,090 | 32,513,686 | 36,279,406 | |||||
Study Life of Mine | Yrs | 4.4 | |||||||||||||||
* no corp cost |
The lifespan of the project in the Study is estimated to be 5.4 years: one year of pre-production and construction, and 4.4 years of full operations. Approximately 175,093 oz of gold are projected to be mined, with 166,172 oz of gold recovered and produced for sale. An accumulated cash basis capital investment of $48.9 million, including initial capital, contingency, sustaining capital and reclamation is projected. Following the All-In Sustaining Cost (“AISC”) guidelines, Study life of mine average base case Cash Operating Cost is projected to be $684/oz of gold sold, before credits for silver sales. The Study life of mine average Site All-in Sustaining Cost (including royalties, production taxes and sustaining capital/closure), before credits for silver sales, is expected to be $875/oz.
LOM Average Operating Costs | ||
$US/ tonne Processed | $US/ oz Gold | |
Mining | 84.33 | 407.04 |
Processing | 39.98 | 192.99 |
Site G&A | 15.45 | 74.61 |
Transportation and Refining | 1.94 | 9.39 |
Cash Operating Cost | 141.70 | 684.03 |
All-In Sustaining Cost | 183.58 | 874.83 |
Mineral resources were incorporated in the model only if classified as Proven or Probable Reserves according to CIM definitions. A throughput of 762 tonnes per day five days per week is the base case processing rate, and operations and capital factors were developed from this basis. Recovery for gold is expected to average 95% for the Project case. Construction of the facilities is projected to conclude at the end of year -1.
The Project, like almost all precious metals projects, is very responsive to changes in the price of its chief commodity, gold. From the base case, a change in the average gold price of US$50/oz Au would change the NPV-10 by approximately $5 million. After-tax economic results with sensitivity to gold price below.
Gold Price$/oz | Net Cash Flow $M | NPV 10% $M | IRR % | Payback Yrs | Payback Multiple | |
1,100 | 14.25 | 3.27 | 15.34 | 3.3 | 1.6 | |
1,150 | 22.24 | 8.51 | 23.90 | 3.0 | 2.0 | |
1,200 | 29.51 | 13.37 | 32.11 | 2.6 | 2.4 | |
1,250 | 36.28 | 17.91 | 40.12 | 2.3 | 2.7 | |
1,300 | 43.19 | 22.53 | 48.42 | 2.0 | 3.1 | |
1,350 | 49.98 | 27.07 | 56.88 | 1.8 | 3.5 | |
1,400 | 56.65 | 31.50 | 65.24 | 1.6 | 3.9 |
Equity Case Economic Results
The Equity case for the Study assumes no equipment financing and no financing cost for Initial Capital. The first table below shows the estimated initial capital costs for the upgrade and restart of the Copperstone Mine using the Equity model case of a WOL processing scheme and owner operated mining without mine equipment financing. The corresponding tables for this case are also below.
Initial Capital | $USM |
Mine | 17.53 |
Mine Development & Infill Drilling | 5.38 |
Mill Upgrades | 3.52 |
Indirects, EPCM, Owners Cost | 4.02 |
Contingency | 3.83 |
Total Initial Capital | 34.28 |
Before Tax | After Tax | |||||
$USM | 19.14 | Net Present Value (10.0%) | $USM | 17.78 | ||
% | 35 | % | Internal Rate of Return | % | 34 | % |
Yrs | 2.27 | Payback Period | Yrs | 2.28 |
Study Totals | Year -2 | Year -1 | Year 1 | Year 2 | Year 3 | Year 4 | Year 5 | ||||||||||
Gold Ounces in Doré | oz | 166,172 | 7,349 | 38,790 | 39,939 | 38,722 | 39,619 | 1,753 | |||||||||
Gross Revenue | $US | 207,714,250 | 9,186,375 | 48,487,000 | 49,923,625 | 48,402,250 | 49,523,375 | 2,191,625 | |||||||||
Cash Operating Costs | $US | (113,665,069 | ) | (4,615,312 | ) | (28,769,608 | ) | (27,427,293 | ) | (26,210,707 | ) | (24,553,976 | ) | (2,088,173 | ) | ||
Royalties | $US | (4,154,287 | ) | (183,728 | ) | (969,740 | ) | (998,473 | ) | (968,045 | ) | (990,468 | ) | (43,833 | ) | ||
Production Taxes | $US | (816,507 | ) | (57,138 | ) | (164,391 | ) | (169,687 | ) | (187,617 | ) | (237,674 | ) | ||||
Total Operating Costs | $US | (118,635,863 | ) | (4,856,178 | ) | (29,903,739 | ) | (28,595,453 | ) | (27,366,369 | ) | (25,782,118 | ) | (2,132,006 | ) | ||
Operating Margin (EBITDA) | $US | 89,078,387 | 4,330,197 | 18,583,261 | 21,328,172 | 21,035,881 | 23,741,257 | 59,619 | |||||||||
Sustaining Capital/Closure | $US | (14,695,063 | ) | (500,000 | ) | (9,698,927 | ) | (4,896,252 | ) | (1,710,947 | ) | (269,937 | ) | 2,381,000 | |||
Site All-In Sustaining Cost* | $US | (133,330,926 | ) | (500,000 | ) | (4,856,178 | ) | (39,602,666 | ) | (33,491,705 | ) | (29,077,316 | ) | (26,052,055 | ) | 248,994 | |
Investment Capital | $US | (34,277,376 | ) | (603,670 | ) | (33,673,707 | ) | ||||||||||
Site All-In Cost* | $US | (167,608,303 | ) | (1,103,670 | ) | (38,529,885 | ) | (39,602,666 | ) | (33,491,705 | ) | (29,077,316 | ) | (26,052,055 | ) | 248,994 | |
Cash Flow, pre-Tax | $US | 40,105,947 | (1,103,670 | ) | (29,343,510 | ) | 8,884,334 | 16,431,920 | 19,324,934 | 23,471,320 | 2,440,619 | ||||||
Interest Expense | $US | ||||||||||||||||
State & Federal Income Tax | $US | (2,215,684 | ) | (878,061 | ) | (2,662,724 | ) | 1,325,101 | |||||||||
Free Cash Flow | $US | 37,890,263 | (1,103,670 | ) | (29,343,510 | ) | 8,884,334 | 16,431,920 | 18,446,873 | 20,808,596 | 3,765,720 | ||||||
Cumulative Free Cash Flow | $US | (1,103,670 | ) | (30,447,179 | ) | (21,562,846 | ) | (5,130,926 | ) | 13,315,947 | 34,124,543 | 37,890,263 | |||||
Study Life of Mine | Yrs | 4.4 | |||||||||||||||
* no corp cost |
LOM Average Operating Costs | ||
$US/ tonne Processed | $US/ oz Gold | |
Mining | 84.33 | 407.04 |
Processing | 39.98 | 192.99 |
Site G&A | 15.45 | 74.61 |
Transportation and Refining | 1.94 | 9.39 |
Cash Operating Cost | 141.70 | 684.03 |
All-In Sustaining Cost | 169.19 | 805.38 |
Infrastructure and Permitting
The Copperstone Mine benefits from extensive existing infrastructure development including 3,000 meters of underground development with two portals to access the underground mine from the bottom of the historic open pit mine. Supporting the underground development are electrical equipment, compressors and ventilation. Also present are a mineral processing plant with crush/grind and flotation capable of +762 tonnes per day, a tailings storage facility expandable, within existing permits, to contain the Study life of mine ore tailings; and other surface infrastructure including line power, office buildings, maintenance shop, fuel bay, wash rack, assay lab, warehouse and a dry. The entire mine-site layout is compact with the underground operations proximal to the process plant, tailings facility and site buildings.
All permits are in place for operations with the infrastructure as described above. Modifications to existing permits are underway for the Study case of WOL, and also for the ability to discharge ground water from the underground workings to a water storage/evaporation pond near the crest of the open pit.
A photo accompanying this announcement is available at http://resource.globenewswire.com/Resource/Download/d11adb09-f555-4ee2-b371-5e0f78bb3d2c
2018 Phase-II Exploration Program
The 2017 Phase-I exploration program was developed to provide a pathway for increasing resources in both the Copperstone and Footwall zones. The program advanced knowledge of mineralizing controls of ore zones at the Copperstone Mine and provided a pathway for adding resources by confirming mineralization, improving continuity and increasing mineralized extents along continued open trends in both the Copperstone and Footwall Zones. The 2017 program is the foundation of the PFS economics and forthcoming production decision.
Building upon the outcomes of 2017 drilling and PFS, the 2018 Phase-II exploration drilling program is aimed at increasing mine life beyond the Study mine life through upgrading and increasing resources. The objectives of the 2018 program are extension of known gold zones and addition of Inferred mineralization near existing development.
Copperstone 2018 Phase-II Drilling Plan:
Drilling location targets for additions and conversions are associated with structural, alteration and lithologic controls which have demonstrated to have significant support for mineralization. Drilling targets also include areas of magnetite skarns and replaced limestones which often demonstrate significant upside potential in near mine extents. The funding of this Phase-II program is not included in the PFS.
Qualified Persons
Qualified Person | Company | QP Responsibility/Role |
Mr. Zachary Black, RM-SME | Hard Rock Consulting, LLC | Mineral Resources |
Ms. J.J. Brown, P.G. | Hard Rock Consulting, LLC | Geology, Environment Studies and Permitting, Site visit |
Mr. Jeffery Choquette, P.E. | Hard Rock Consulting, LLC | Mineral Reserves, Mining Methods and Economic Analysis |
Mr. Deepak Malhotra, Ph.D. | Resource Development, Inc. | Mineral Processing and Plant Design |
Contributing Person | Company | Responsibility/Role |
Mr. Dermot Ross-Brown, Ph.D. | Tierra Group International, Ltd | Mine Geotechnical |
Mr. Matt Bachman, P.E. | Paterson and Cooke | Mine Backfill Design |
Mr. David Abranovic, P.E. | Environmental Resources Management | Permitting and Environmental |
Mr. Scott M. Bruno, P.E. | BODEC, Inc. | Mine Electrical |
Mr. Michael R. Smith, RM-SME | Geological Professional Services, LLC | Mine Ore Control and Quality Assurance, Quality Control |
The technical information in this news release has been prepared in accordance with the Canadian regulatory requirements set out in NI 43-101 and reviewed and approved by HRC. The qualified persons responsible for preparing the Copperstone PFS are named above. All of whom act as independent consultants to the Company, are Qualified Persons as define by National Instrument 43-101 and have reviewed and approved the contents of this new release.
HRC is a client focused consultancy comprised of a formal collaboration of industry professionals including geologists, engineers, and business advisors who offer a wealth and variety of professional experience - and a passion to gain more. As a team, HRC takes pride in our ability to apply practical solutions to real-world project challenges, whether in the field or in the office, for projects in North America and around the world. www.hardrock-consulting.com
A technical report in support of the Pre-Feasibility Study prepared in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) will be filed on SEDAR (www.sedar.com) within 45 days of this news release. Readers are strongly encouraged to review the final technical report in its entirety.
About Kerr Mines Inc.
Kerr Mines is a North American gold development and exploration company currently advancing the 100% owned, fully permitted past-producing Copperstone Mine project. Copperstone is a high-grade gold project located along a detachment fault mineral belt in mining-friendly Arizona. The project demonstrates significant upside exploration potential within a 4,775-hectare (11,800 acres) land package that includes a production history of over 500,000 ounces of gold. The Company’s current focus is on maximizing Copperstone’s potential by defining and expanding current resources and strengthening the mine’s economics leading to project financing and a production decision.
For further information contact:
Claudio Ciavarella
Chief Executive Officer
cciavarella@kerrmines.com
416-855-9305
Cautionary Note Regarding Forward Looking Statements
This news release contains forward-looking statements, including current expectations on the timing of the commencement of production and the rate of production, if commenced. These forward-looking statements entail various risks and uncertainties that could cause actual results to differ materially from those reflected in these forward-looking statements. Such statements are based on current expectations, are subject to a number of uncertainties and risks, and actual results may differ materially from those contained in such statements. These uncertainties and risks include, but are not limited to, the strength of the Canadian economy; the price of gold; operational, funding, and liquidity risks; the degree to which mineral resource estimates are reflective of actual mineral resources; and the degree to which factors which would make a mineral deposit commercially viable are present; the risks and hazards associated with underground operations. Risks and uncertainties about Kerr Mines’ business are more fully discussed in the Company's disclosure materials, including its annual information form and MD&A, filed with the securities regulatory authorities in Canada and available at www.sedar.com and readers are urged to read these materials. Kerr Mines assumes no obligation to update any forward-looking statement or to update the reasons why actual results could differ from such statements unless required by law.
Neither TSX nor its Regulation Services Provider (as that term is defined in the policies of the TSX) accepts responsibility for the adequacy or accuracy of this release and no stock exchange, securities commission or other regulatory authority has approved or disapproved the information contained herein.
Cautionary Note to US Investors Regarding Mineral Reporting Standards: The Company has prepared its disclosure in accordance with the requirements of securities laws in effect in Canada, which differ from the requirements of US securities laws. Terms relating to mineral resources in this press release are defined in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects under the guidelines set out in the Canadian Institute of Mining, Metallurgy, and Petroleum Standards on Mineral Resources and Mineral Reserves. The Securities and Exchange Commission (the “SEC”) permits mining companies, in their filings with the SEC, to disclose only those mineral deposits that a company can economically and legally extract or produce. The Company uses certain terms, such as, “measured mineral resources”, “indicated mineral resources”, “inferred mineral resources” and “probable mineral reserves”, that the SEC does not recognize (these terms may be used in this press release and are included in the public filings of the Company which have been filed with securities commissions or similar authorities in Canada).