VANCOUVER, British Columbia, July 31, 2019 (GLOBE NEWSWIRE) -- Macarthur Minerals Limited (TSX-V: MMS) (the “Company” or “Macarthur”) is pleased to provide an update to Shareholders outlining an active and significant second quarter 2019 in the ongoing development of the Company’s Lake Giles Iron Ore Projects and exploration activities across the lithium, gold, nickel and cobalt projects in Western Australia and Nevada, USA.
SECOND QUARTER HIGHLIGHTS
Mr Cameron McCall, Executive Chairman of Macarthur Minerals commented:
“The uptick in the iron ore price to US$122.60/tonne continues to drive major momentum in the iron ore industry. Premiums for high grade ore and discounting of lower grade ore have contracted during 2019 but remain well above 2018 spot prices.
The Company’s focus on delivering a product of +65% Fe will create price support when the iron ore industry returns to an oversupply market environment and continues to engage with potential strategic partners to create short-term cash flow and deliver the Lake Giles Iron Project through to production.
The Company assessed the recoverable value of the projects to be in excess of historical capitalised costs. The impairment change of $55,851,937 raised in 2016 has been reversed as reported in its audited annual report for year ended March 31, 2019 filed in July 29, 2019. The Iron Ore projects’ book value reflects the historical costs of exploration and evaluation expenditure capitalised in accordance with the Company’s accounting policy and Australian accounting standards and IFRS.
IRON ORE
In the second quarter, the key project advancements have been the completion of the following:
The Lake Giles PEA rationalised the Ularring Hematite and Moonshine Projects into a combined project resulting in substantial cost savings and efficiencies. The key highlights1 are summarised below:
With the closure of the financing, the Company is now focused on completing the BFS to support debt funding for project construction.
NON-IRON ASSETS
This year, Macarthur’s focus has been on the West Australian Iron Ore assets. To support this strategy, the Company ventured out the gold and lithium tenements in the Pilbara region to ASX listed Australian explorer, Fe Limited (“FEL”). FEL has the ability to earn up to 75% of these Projects through exploration and staged cash payments to Macarthur. During the quarter FEL commenced exploration on the areas and will undertake substantial geochemistry and ground mapping across this portfolio of projects during the next quarter.
This joint venture arrangement allows the Company to focus solely on the Lake Giles Iron Ore portfolio which is the Company’s flagship project.
About Fe Limited
Fe Limited (ASX: FEL) is a listed mineral exploration Company that holds or has rights or interests in various projects and tenements prospective for battery metals, copper, iron ore, gold and base metals located in Australia. The Company is focused on the exploration of battery metal projects. In March 2019, FEL entered into an agreement to acquire the Pippingarra Lithium Project and the Marble Bar Lithium Project (Project) from Mercury Resources Group Pty Ltd. These areas complement the tenement portfolio of Macarthur Minerals, establishing a 1800 square kilometre exploration footprint in the important Lithium and Gold region of Western Australia.
PILBARA GOLD PROJECTS
Macarthur holds a large parcel of Pilbara acreage consisting of the Hillside, Panorama and Bonnie Scot tenements, all with significant gold potential.
The Panorama and Bonnie Scot tenements cover an extensive area of the Mt Roe Basalts and Hardey Formation that have demonstrated potential for hosting conglomerate gold. The recent soil sampling program has now identified prospective target follow-up exploration areas.
A SkyTEM geophysical survey was conducted over the Hillside tenements to identify key areas that could be the source of the high-grade gold and copper samples taken during the soil sampling program. This type of survey assists in the identification of deep conductors such as clusters of massive sulphide-hosted base metal deposits. This program identified 18 priority geophysical targets that concentrate to known mineralisation.
PILBARA HARD ROCK LITHIUM
Macarthur’s Pilbara lithium portfolio covers an area of ~1,281 square kilometers, have regulatory exploration licence approval and cover similar geological settings to that of “world class” Pilbara lithium deposits and producing spodumene mines. These areas are included in the earn-in Joint Venture program that is targeting battery metal deposits. These areas have been added to during 2019 with the lithium potential tenements held by Fe Limited.
NEVADA, USA REYNOLDS SPRINGS PROJECT
Macarthur holds 210 unpatented mining claims at its Reynolds Springs Lithium Brine Project in the Railroad Valley, Nevada, USA. Analysis of geochemical soil sampling found up to 405ppm Li.
Macarthur conducted further review of several historic well logs drilled on the claims and identified numerous conductive, faulted zones that indicate the presence of a brine aquifer.
NEXT STEPS
Macarthur will actively advance, with our key partners, its iron ore assets in Western Australia. Preparation and planning are well underway for the infill drilling of the Moonshine magnetite deposit and a Bankable Feasibility Study of the Lake Giles Iron Project. Further, the Company will work closely with Fe Limited to advance exploration of its high-quality lithium, gold and base metal tenements in the Pilbara region.
ABOUT MACARTHUR MINERALS LIMITED (TSX-V: MMS, OTCQB: MMSDF)
Macarthur is an iron ore development, gold and lithium exploration company that is focused on bringing to production its Western Australia iron ore projects. The Lake Giles Iron Ore Project includes the 80 million tonne Ularring hematite resource (approved for development) and the 710 million tonne Moonshine magnetite resource. Macarthur has prominent (~1,281 square kilometer tenement area) gold, lithium and nickel exploration interests in Pilbara region of Western Australia. In addition, Macarthur has lithium brine Claims in the emerging Railroad Valley region in Nevada, USA.
MACARTHUR MINERALS LIMITED “Cameron McCall” Cameron McCall, Executive Chairman | On behalf of the Board of Directors, Company contact Joe Philips, CEO and Director Email: jphilips@macarthurminerals.com Telephone: +61 448899427 Website: www.macarthurminerals.com |
THIS NEWS RELEASE IS NOT FOR DISTRIBUTION TO UNITED STATES SERVICES OR
FOR DISSEMINATION IN THE UNITED STATES
Caution Regarding Forward Looking Statements
Certain of the statements made and information contained in this press release may constitute forward-looking information and forward-looking statements (collectively, “forward-looking statements”) within the meaning of applicable securities laws. The forward-looking statements in this press release reflect the current expectations, assumptions or beliefs of the Company based upon information currently available to the Company. With respect to forward-looking statements contained in this press release, assumptions have been made regarding, among other things, the timely receipt of required approvals, the reliability of information, including historical mineral resource or mineral reserve estimates, prepared and/or published by third parties that are referenced in this press release or was otherwise relied upon by the Company in preparing this press release. Although the Company believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and no assurance can be given that these expectations will prove to be correct as actual results or developments may differ materially from those projected in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include fluctuations in exchange rates and certain commodity prices, uncertainties related to mineral title in the project, unforeseen technology changes that results in a reduction in iron ore demand or substitution by other metals or materials, the discovery of new large low cost deposits of iron ore, uncertainty in successfully returning the project into full operation, and the general level of global economic activity. Readers are cautioned not to place undue reliance on forward-looking statements due to the inherent uncertainty thereof. Such statements relate to future events and expectations and, as such, involve known and unknown risks and uncertainties. The forward-looking statements contained in this press release are made as of the date of this press release and except as may otherwise be required pursuant to applicable laws, the Company does not assume any obligation to update or revise these forward-looking statements, whether as a result of new information, future events or otherwise.
1 Press Release filed June 17, 2019, titled “Macarthur Files Technical Report for Lake Giles Iron Ore Project”