VANCOUVER, British Columbia, Aug. 07, 2023 (GLOBE NEWSWIRE) -- MAG Silver Corp. (TSX / NYSE American: MAG) (“MAG”, or the “Company”) announces the Company’s unaudited financial results for the three months ended June 30, 2023. For details of the unaudited condensed interim consolidated financial statements and Management's Discussion and Analysis for the three and six months ended June 30, 2023, please see the Company’s filings on SEDAR+ (www.sedarplus.ca) or on EDGAR (www.sec.gov).
All amounts herein are reported in $000s of United States dollars (“US$”) unless otherwise specified (C$ refers to Canadian dollars).
KEY HIGHLIGHTS (on a 100% basis unless otherwise noted)
OPERATIONAL (on a 100% basis unless otherwise noted)
CORPORATE
EXPLORATION
JUANICIPIO PROJECT UPDATE
Underground Mine Production
On a 100% basis, after completion of the start-up phase, approximately 4.4 million ounces of silver have been produced from the Juanicipio processing facility from March 2023 to the end of June 2023, and production is expected to continue to increase steadily through Q3 2023 where it is envisioned the processing facility will be running at nameplate of 4,000 tpd. An Operator Services Agreement became effective upon the declaration of commercial production, whereby Fresnillo and its affiliates will continue to operate the mine. Subject to available capacity, excess mineralized material from Juanicipio may continue to be processed at the Fresnillo and Saucito processing plants (both 100% owned by Fresnillo), with the lead (silver-rich) and zinc concentrates treated at market terms under offtake agreements with Met-Mex (an affiliate of Fresnillo).
In the three months ended June 30, 2023, a total of 377,018 tonnes of mineralized development and stope material were processed through the Juanicipio, Saucito and Fresnillo plants. The resulting payable metals sold and associated processing details are summarized in Table 1 below. The sales and treatment charges for tonnes processed in Q2 2023 were recorded on a provisional basis and will be adjusted in the third quarter of 2023 based on final assay and pricing adjustments in accordance with the offtake contracts.
Table 1: Mineralized Material Processed at Juanicipio, Saucito and Fresnillo Plants (100% basis)
Three Months Ended June 30, 2023 (377,018 tonnes processed) | Q2 2022 Amount $ | |||||||
Payable Metals | Quantity | Average Per Unit $ | Amount $ | |||||
Silver | 4,877,460 ounces | 23.69 per oz | 115,555 | 47,070 | ||||
Gold | 9,537 ounces | 1,957.47 per oz | 18,668 | 9,388 | ||||
Lead | 3,066 tonnes | 0.94 per lb. | 6,367 | 2,135 | ||||
Zinc | 4,582 tonnes | 1.07 per lb. | 10,807 | 6,199 | ||||
TCRCs and other processing costs | (16,622 | ) | (9,568 | ) | ||||
Net Revenue | 134,775 | 55,224 | ||||||
Production and transportation costs | (57,571 | ) | (12,717 | ) | ||||
Depreciation and amortization (1) | (17,400 | ) | (5,245 | ) | ||||
Gross Profit | 62,804 | 37,262 |
(1) The underground mine was considered readied for its intended use on January 1, 2022, whereas the Juanicipio processing facility started commissioning and ramp-up activities in January 2023, achieving commercial production status on June 1, 2023.
The average silver head grade for the mineralized material processed in the three months ended June 30, 2023 was 498 g/t (three months ended June 30, 2022: 567 g/t). The lower head grade was impacted by lower development material as well as the processing of lower grade stockpiles which were earmarked for the commissioning and ramp-up phase of the Juanicipio processing facility. Since completing its start-up phase in March 2023, the Juanicipio processing facility has been operating at approximately 85% of its design capacity of 4,000 tpd with silver recovery consistently above 88%.
Processing Facility Construction & Outlook
Commissioning commenced in early January 2023 with feed of lower grade mineralized material to the grinding mills. Processing of higher-grade material commenced in April with commensurate improvements in silver recovery and associated concentrate grades. The Juanicipio processing facility has been operating at approximately 85% of its nameplate of 4,000 tpd with silver recovery consistently above 88%. On June 5, 2023 the Company announced that following a successful commissioning period, the Juanicipio mine, processing facility and other vital systems were operating in line with, or rapidly approaching design capacity, and therefore declared full commercial production effective June 1, 2023.
With the processing facility completed and commercial production declared on June 1, 2023, all major construction activities have now been completed and Juanicipio is demonstrating its ability to sustain ongoing production levels. Additional funding requirements related to market conditions (i.e. lower metal prices or higher inflation driving higher costs for instance), or for additional capital in excess of the operating cash flow generated may need to be funded by further cash calls required from Fresnillo and MAG.
FINANCIAL RESULTS – THREE MONTHS ENDED JUNE 30, 2023
As at June 30, 2023, MAG had working capital of $51,600 (December 31, 2022: $29,232) including cash of $52,664 (December 31, 2022: $29,955) and no long-term debt. As well, as at June 30, 2023, Juanicipio had working capital of $94,289 including cash of $8,539 (MAG’s attributable share is 44%).
The Company’s net income for the three months ended June 30, 2023 amounted to $19,390 (June 30, 2022: $7,562) or $0.19/share (June 30, 2022: $0.08/share). MAG recorded its 44% income from equity accounted investment in Juanicipio of $22,419 (June 30, 2022: $12,347) which included MAG’s 44% share of net income from operations as well as loan interest earned on loans advanced to Juanicipio (see Table 2 below).
Table 2: MAG’s share of income from its equity accounted Investment in Juanicipio
Three months ended | ||||
June 30, | June 30, | |||
2023 | 2022 | |||
$ | $ | |||
Sales | 134,775 | 55,224 | ||
Cost of sales: | ||||
Production cost | (54,571 | ) | (12,717 | ) |
Depreciation and amortization | (17,400 | ) | (5,245 | ) |
Gross profit (see Underground Mine Production – Juanicipio Project above) | 62,804 | 37,262 | ||
Consulting and administrative expenses | (4,158 | ) | (1,376 | ) |
Extraordinary mining and other duties | (1,377 | ) | (109 | ) |
Interest expenses | (4,886 | ) | (740 | ) |
Exchange gains (losses) and other | 32 | 763 | ||
Net income before tax | 52,415 | 35,800 | ||
Income tax (expense) benefit | (6,349 | ) | (8,439 | ) |
Net income (100% basis) | 46,066 | 27,361 | ||
MAG’s 44% portion of net income | 20,269 | 12,039 | ||
Interest on Juanicipio loans - MAG's 44% | 2,150 | 308 | ||
MAG’s 44% equity income | 22,419 | 12,347 |
Qualified Person: All scientific or technical information in this press release including assay results referred to, and Mineral Resource estimates, if applicable, is based upon information prepared by or under the supervision of, or has been approved by Dr. Peter Megaw, Ph.D., C.P.G., a Certified Professional Geologist who is a “Qualified Person” for purposes of National Instrument 43-101, Standards of Disclosure for Mineral Projects (“National Instrument 43-101” or “NI 43-101”). Dr. Megaw is not independent as he is an officer and a paid consultant of MAG.
About MAG Silver Corp. (www.magsilver.com)
MAG Silver Corp. is a growth-oriented Canadian exploration company focused on advancing high-grade, district scale precious metals projects in the Americas. MAG is emerging as a top-tier primary silver mining company through its (44%) joint venture interest in the 4,000 tonnes per day Juanicipio Mine, operated by Fresnillo plc (56%). The mine is located in the Fresnillo Silver Trend in Mexico, the world's premier silver mining camp, where in addition to underground mine production and processing of high-grade mineralised material, an expanded exploration program is in place targeting multiple highly prospective targets. MAG is also executing multi-phase exploration programs at the Deer Trail 100% earn-in Project in Utah and the 100% owned Larder Project, located in the historically prolific Abitibi region of Canada.
Neither the Toronto Stock Exchange nor the NYSE American has reviewed or accepted responsibility for the accuracy or adequacy of this press release, which has been prepared by management.
Certain information contained in this release, including any information relating to MAG’s future oriented financial information, are “forward-looking information” and “forward-looking statements” within the meaning of applicable Canadian and United States securities legislation (collectively herein referred as “forward-looking statements”), including the “safe harbour” provisions of provincial securities legislation, the U.S. Private Securities Litigation Reform Act of 1995, Section 21E of the U.S. Securities Exchange Act of 1934, as amended and Section 27A of the U.S. Securities Act. Such forward-looking statements include, but are not limited to:
When used in this release, any statements that express or involve discussions with respect to predictions, beliefs, plans, projections, objectives, assumptions or future events of performance (often but not always using words or phrases such as “anticipate”, “believe”, “estimate”, “expect”, “intend”, “plan”, “strategy”, “goals”, “objectives”, “project”, “potential” or variations thereof or stating that certain actions, events, or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved, or the negative of any of these terms and similar expressions), as they relate to the Company or management, are intended to identify forward-looking statements. Such statements reflect the Company’s current views with respect to future events and are subject to certain known and unknown risks, uncertainties and assumptions.
Forward-looking statements are necessarily based upon estimates and assumptions, which are inherently subject to significant business, economic and competitive uncertainties and contingencies, many of which are beyond the Company’s control and many of which, regarding future business decisions, are subject to change. Assumptions underlying the Company’s expectations regarding forward-looking statements contained in this release include, among others: MAG’s ability to carry on its various exploration and development activities including project development timelines, the timely receipt of required approvals and permits, the price of the minerals produced, the costs of operating, exploration and development expenditures, the impact on operations of the Mexican tax regime, MAG’s ability to obtain adequate financing, outbreaks or threat of an outbreak of a virus or other contagions or epidemic disease will be adequately responded to locally, nationally, regionally and internationally.
Although MAG believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. These forward-looking statements involve known and unknown risks, uncertainties and many factors could cause actual results, performance or achievements to be materially different from any future results, performance or achievements that may be expressed or implied by such forward-looking statements including amongst other: commodities prices; changes in expected mineral production performance; unexpected increases in capital costs or cost overruns; exploitation and exploration results; continued availability of capital and financing; general economic, market or business conditions; risks relating to the Company’s business operations; risks relating to the financing of the Company’s business operations; risks relating to the development of the Juanicipio Project and the minority interest investment in the same; risks relating to the Company’s property titles; risks related to receipt of required regulatory approvals; pandemic risks (and COVID-19); supply chain constraints and general costs escalation in the current inflationary environment heightened by the invasion of Ukraine by Russia; risks relating to the Company’s financial and other instruments; operational risk; environmental risk; political risk; currency risk; market risk; capital cost inflation risk; risk relating to construction delays; the risk that data is incomplete or inaccurate; the risks relating to the limitations and assumptions within drilling, engineering and socio-economic studies relied upon in preparing economic assessments and estimates, including the 2017 PEA; as well as those risks more particularly described under the heading “Risk Factors” in the Company’s most recent Annual Information Form dated March 27, 2023 available under the Company’s profile on SEDAR at www.sedar.com.
Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described herein. This list is not exhaustive of the factors that may affect any of the Company’s forward-looking statements. The Company’s forward-looking statements are based on the beliefs, expectations and opinions of management on the date the statements are made and, other than as required by applicable securities laws, the Company does not assume any obligation to update forward-looking statements if circumstances or management’s beliefs, expectations or opinions should change. For the reasons set forth above, investors should not attribute undue certainty to or place undue reliance on forward-looking statements.
Please Note: Investors are urged to consider closely the disclosures in MAG's annual and quarterly reports and other public filings, accessible through the Internet at www.sedar.com and www.sec.gov.
LEI: 254900LGL904N7F3EL14
For further information on behalf of MAG Silver Corp. Contact Michael J. Curlook, Vice President, Investor Relations and Communications Phone: (604) 630-1399 Website:www.magsilver.com Toll Free:(866) 630-1399 Email: info@magsilver.com