VANCOUVER, British Columbia, March 27, 2023 (GLOBE NEWSWIRE) -- MAG Silver Corp. (TSX / NYSE American: MAG) (“MAG”, or the “Company”) announces the Company’s audited consolidated financial results for the year ended December 31, 2022. For details of the audited consolidated financial statements, Management's Discussion and Analysis, Annual Information Form and Annual Report on Form 40-F for the year ended December 31, 2022, please see the Company’s filings on SEDAR (www.sedar.com) or on EDGAR (www.sec.gov).
All amounts herein are reported in $000s of United States dollars (“US$”) unless otherwise specified.
KEY HIGHLIGHTS (on a 100% basis unless otherwise noted)
OPERATIONAL (on a 100% basis unless otherwise noted)
CORPORATE
EXPLORATION
JUANICIPIO PROJECT UPDATE
Underground Mine Production
With the Juanicipio plant now in the commissioning and ramp-up phase, excess mineralized material from the Juanicipio Project continues to be campaign processed, subject to capacity availability, at the nearby Saucito and Fresnillo plants (both 100% owned by Fresnillo). Metals are refined and sold on commercial terms under long-term off-take agreements with an affiliate of Fresnillo. During the year and quarter ended December 31, 2022, approximately 63% and 70% respectively, of the total tonnage processed was through the Saucito plant. The Saucito plant flowsheet better resembles that of the Juanicipio flowsheet and will provide valuable metallurgical information as production ramps up at Juanicipio.
In the year ended December 31, 2022, a total of 646,148 tonnes of mineralized development and stope material were processed through the Fresnillo plants. The resulting payable metals sold and processing details are summarized in Table 1 below.
Table 1: Mineralized Material Processed at Fresnillo’s Processing Plants (100% basis)
Year Ended December 31, 2022 (646,148 tonnes processed) | Year Ended December 31, 2021 Amount $ | |||
Payable Metals | Quantity | Average Per Unit $ | Amount $ | |
Silver | 8,697,372 ounces | 21.70 per oz | 188,722 | 71,369 |
Gold | 20,268 ounces | 1,823 per oz | 36,958 | 10,702 |
Lead | 4,487 tonnes | 0.95 per lb. | 9,380 | 2,387 |
Zinc | 6,758 tonnes | 1.57 per lb. | 23,398 | 4,849 |
TCRCs and other processing costs | (42,722) | (12,768) | ||
Provisional revenue adjustment related to 2020 sales (1) | - | (1,146) | ||
Net Revenue | 215,736 | 75,393 | ||
Mining and transportation costs | (61,985) | (15,329) | ||
Depreciation and amortization | (20,913) (2) | - | ||
Gross Profit | 132,838 | 60,064 |
(1) Provisional revenues for 2020 were finalized in Q1 2021 resulting in negative adjustment to net revenue of $1,146.
(2) The underground mine is now in stopes with mineralized development and stope material being processed through Fresnillo’s plants and refined and sold. The mine was considered readied for its intended use on January 1, 2022.
In the three months ended December 31, 2022, a total of 165,786 tonnes of mineralized development and stope material were processed through the Fresnillo plants. The resulting payable metals sold and associated processing details are summarized in Table 2 below. The sales and treatment charges for tonnes processed in Q4 2022 were recorded on a provisional basis and will be adjusted in the first quarter of 2023 based on final assay and pricing adjustments in accordance with the offtake contracts.
Table 2: Mineralized Material Processed at Fresnillo’s Processing Plants (100% basis)
Three Months Ended December 31, 2022 (165,786 tonnes processed) | Q4 2021 Amount $ | |||
Payable Metals | Quantity | Average Per Unit $ | Amount $ | |
Silver | 1,825,680 ounces | 22.59 per oz | 41,235 | 34,877 |
Gold | 4,903 ounces | 1,848 per oz | 9,061 | 6,531 |
Lead | 1,058 tonnes | 0.94 per lb. | 2,184 | 1,300 |
Zinc | 1,673 tonnes | 1.35 per lb. | 4,975 | 2,729 |
TCRCs and other processing costs | (11,574) | (6,069) | ||
Net Revenue | 45,881 | 39,368 | ||
Mining and transportation costs | (15,877) | (7,593) | ||
Depreciation and amortization | (5,861) (1) | - | ||
Gross Profit | 24,143 | 31,775 |
(1) The underground mine is now in stopes with mineralized development and stope material being processed through Fresnillo’s plants and refined and sold. The mine was considered readied for its intended use on January 1, 2022.
The average silver head grade for the mineralized development and initial stope material processed in the year and three months ended December 31, 2022 was 520 g/t and 415 g/t, respectively (year and three months ended December 31, 2021 was 470 g/t and 542 g/t, respectively). As per plan, and mine ramp-up, this increased grade for year 2022 reflects more stoped vein material being processed. Metal recovery and concentrate grades are in line with expectations from the initial metallurgical test work conducted on Valdecañas mineralized material.
Processing Plant Construction & Outlook
The Juanicipio Project team delivered the 4,000 tpd processing plant for commissioning in the fourth quarter of 2021. However, as previously reported, in late 2021, the Comisión Federal de Electricidad (“CFE”), a state-owned electrical company, notified Fresnillo that approval to complete the tie-in to the national power grid could not yet be granted and the mill commissioning timeline would therefore be extended. This delay primarily related to staffing effects related to the COVID-19 pandemic on the state-owned electrical company. To mitigate the effect on cash flow generation from the Juanicipio Project while CFE approvals were pending, Fresnillo made available unused plant capacity at its Saucito and Fresnillo operations to process mineralized material produced at the Juanicipio Project during this period, matching commissioning and ramp up tonnages that were previously expected, where possible. On December 28, 2022 the Company announced its receipt of CFE approval, the completion of the electrical tie-in to the national power grid and the envisioned commissioning of the 4,000 tpd processing facility. Commissioning commenced in early January 2023 with feed of lower grade mineralized material to the grinding mills. Mineralized material has been conveyed to the fine ore bin and stockpiled for commissioning and ramp-up operations. Processing of higher grade material is envisioned once the plant is fully commissioned and operating at steady state levels.
With the plant now in the commissioning and ramp-up phase, final project capital costs are expected to wind down as Juanicipio approaches full commercial production and associated free cash flow generation. Additional funding requirements related to market conditions, delayed ramp up to nameplate capacity, tax payments or additional sustaining capital in excess of the operating cash flow generated is expected to be funded by further cash calls required from Fresnillo and MAG.
FINANCIAL RESULTS – YEAR ENDED DECEMBER 31, 2022
As at December 31, 2022, MAG had working capital of $29,232 (December 31, 2021: $57,761) including cash of $29,955 (December 31, 2021: $56,748) and no long-term debt. As well, as at December 31, 2022, Juanicipio had a negative working capital of $1,395 including cash of $1,102 (MAG’s attributable share is 44%).
The Company’s net income for the year ended December 31, 2022 amounted to $17,644 (December 31, 2021: $6,025) or $0.18/share (December 31, 2021: ($0.06)/share). MAG recorded its 44% income from equity accounted investment in Juanicipio of $40,767 (December 31, 2021: $15,686) which included MAG’s 44% share of net income from the sale of pre-production development and stope material as well as loan interest earned on mining assets brought into use (see Table 3 below).
Table 3: MAG’s share of income from its equity accounted Investment in Juanicipio
December 31, | December 31, | |||
2022 | 2021 | |||
Gross profit from processing mineralized development material (see Underground Mine Production — Juanicipio Project above) | $132,838 | $60,064 | ||
Consulting and administrative expenses | (8,436) | (1,929) | ||
Extraordinary mining duty | (349) | (337) | ||
Exchange losses and other | (7,458) | (1,363) | ||
Net income before tax | 116,595 | 56,435 | ||
Income tax expense | (26,348) | (20,784) | ||
Net income for the year (100% basis) | 90,247 | 35,651 | ||
MAG's 44% share of income | 39,709 | 15,686 | ||
Loan interest on mining assets - MAG 44% | 1,058 | - | ||
MAG's 44% share of income from equity accounted Investment in Juanicipio | $40,767 | $15,686 |
Qualified Person: All scientific or technical information in this press release including assay results referred to, and Mineral Resource estimates, if applicable, is based upon information prepared by or under the supervision of, or has been approved by Dr. Peter Megaw, Ph.D., C.P.G., a Certified Professional Geologist who is a “Qualified Person” for purposes of National Instrument 43-101, Standards of Disclosure for Mineral Projects (“National Instrument 43-101” or “NI 43-101”). Dr. Megaw is not independent as he is an officer and a paid consultant of MAG.
About MAG Silver Corp. (www.magsilver.com)
MAG Silver Corp. is a growth-oriented Canadian development and exploration company focused on becoming a top-tier primary silver mining company by exploring and advancing high-grade, district scale, precious metals projects in the Americas. Its principal focus and asset is the Juanicipio Project (44%), being developed with Fresnillo Plc (56%), the operator. The project is located in the Fresnillo Silver Trend in Mexico, the world's premier silver mining camp, where the operator is currently advancing underground mine development and commissioning a 4,000 tonnes per day processing plant. Underground mine production of mineralized development material commenced in Q3 2020, and an expanded exploration program is in place targeting multiple highly prospective targets at Juanicipio. MAG is also executing multi-phase exploration programs at the Deer Trail 100% earn-in Project in Utah and the recently acquired Larder Lake Project, located in the historically prolific Abitibi region of Canada.
Neither the Toronto Stock Exchange nor the NYSE American has reviewed or accepted responsibility for the accuracy or adequacy of this press release, which has been prepared by management.
Certain information contained in this release, including any information relating to MAG’s future oriented financial information, are “forward-looking information” and “forward-looking statements” within the meaning of applicable Canadian and United States securities legislation (collectively herein referred as “forward-looking statements”), including the “safe harbour” provisions of provincial securities legislation, the U.S. Private Securities Litigation Reform Act of 1995, Section 21E of the U.S. Securities Exchange Act of 1934, as amended and Section 27A of the U.S. Securities Act. Such forward-looking statements include, but are not limited to:
When used in this release, any statements that express or involve discussions with respect to predictions, beliefs, plans, projections, objectives, assumptions or future events of performance (often but not always using words or phrases such as “anticipate”, “believe”, “estimate”, “expect”, “intend”, “plan”, “strategy”, “goals”, “objectives”, “project”, “potential” or variations thereof or stating that certain actions, events, or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved, or the negative of any of these terms and similar expressions), as they relate to the Company or management, are intended to identify forward-looking statements. Such statements reflect the Company’s current views with respect to future events and are subject to certain known and unknown risks, uncertainties and assumptions.
Forward-looking statements are necessarily based upon estimates and assumptions, which are inherently subject to significant business, economic and competitive uncertainties and contingencies, many of which are beyond the Company’s control and many of which, regarding future business decisions, are subject to change. Assumptions underlying the Company’s expectations regarding forward-looking statements contained in this release include, among others: MAG’s ability to carry on its various exploration and development activities including project development timelines, the timely receipt of required approvals and permits, the price of the minerals produced, the costs of operating, exploration and development expenditures, the impact on operations of the Mexican tax regime, MAG’s ability to obtain adequate financing, outbreaks or threat of an outbreak of a virus or other contagions or epidemic disease will be adequately responded to locally, nationally, regionally and internationally.
Although MAG believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. These forward-looking statements involve known and unknown risks, uncertainties and many factors could cause actual results, performance or achievements to be materially different from any future results, performance or achievements that may be expressed or implied by such forward-looking statements including amongst other: commodities prices; changes in expected mineral production performance; unexpected increases in capital costs or cost overruns; exploitation and exploration results; continued availability of capital and financing; general economic, market or business conditions; risks relating to the Company’s business operations; risks relating to the financing of the Company’s business operations; risks relating to the development of the Juanicipio Project and the minority interest investment in the same; risks relating to the Company’s property titles; risks related to receipt of required regulatory approvals; pandemic risks (and COVID-19); supply chain constraints and general costs escalation in the current inflationary environment heightened by the invasion of Ukraine by Russia; risks relating to the Company’s financial and other instruments; operational risk; environmental risk; political risk; currency risk; market risk; capital cost inflation risk; risk relating to construction delays; the risk that data is incomplete or inaccurate; the risks relating to the limitations and assumptions within drilling, engineering and socio-economic studies relied upon in preparing economic assessments and estimates, including the 2017 PEA; as well as those risks more particularly described under the heading “Risk Factors” in the Company’s most recent Annual Information Form dated March 27, 2023 available under the Company’s profile on SEDAR at www.sedar.com.
Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described herein. This list is not exhaustive of the factors that may affect any of the Company’s forward-looking statements. The Company’s forward-looking statements are based on the beliefs, expectations and opinions of management on the date the statements are made and, other than as required by applicable securities laws, the Company does not assume any obligation to update forward-looking statements if circumstances or management’s beliefs, expectations or opinions should change. For the reasons set forth above, investors should not attribute undue certainty to or place undue reliance on forward-looking statements.
Please Note: Investors are urged to consider closely the disclosures in MAG's annual and quarterly reports and other public filings, accessible through the Internet at www.sedar.com and www.sec.gov.
LEI: 254900LGL904N7F3EL14
For further information on behalf of MAG Silver Corp. Contact Michael J. Curlook, Vice President, Investor Relations and Communications Phone: (604) 630-1399 Website: www.magsilver.com Toll Free: (866) 630-1399 Email: info@magsilver.com