OTTAWA, April 08, 2021 (GLOBE NEWSWIRE) -- Cornerstone Capital Resources Inc. (“Cornerstone” or “the Company”) (TSXV:CGP) (Frankfurt:GWN1) (Berlin:GWN1) (OTC:CTNXF) is pleased to announce the following update on the status of the Pre-feasibility Study (PFS) on the Alpala Project at its Cascabel copper-gold porphyry joint venture project in northern Ecuador (the “Project”) in which Cornerstone has a 15% interest1 financed through to completion of a feasibility study plus 7.5% of the shares of joint venture partner and Project operator SolGold Plc, for a total direct and indirect interest in Cascabel of 21.4%.
The Alpala Project Team and the Project Committee, chaired by Interim CEO Keith Marshall, are making good progress studying potential Alpala mine plans while addressing a number of mine development and metallurgical enhancements as well as potential upsides, and are continuing to target the release of the PFS in late 2021.
The Alpala deposit comprises 2,663 Mt at 0.53% CuEq in the Measured plus Indicated categories and contained metal content of 9.9 Mt Cu, 21.7 Moz Au and 92.2 Moz Ag.2 The deposit measures approximately 900m in height and 500m diameter. Given the size and geometry of the deposit, the Company is quite optimistic that the PFS will demonstrate that it is amenable to underground caving mining methods.
The Company is confident that this revised approach being studied from that which was previously considered is much more beneficial for Cornerstone and SolGold and will deliver significant shareholder value. SolGold is currently expanding its team of experienced technical staff, with the first, Ms. Lisa Park, Head of Metallurgy, having officially joined in recent days.
Key considerations that suggest the superiority of the revised approach currently being studied for the development of the Project include:
The Company is optimistic that the revised mine plan currently being studied as part of the PFS process could deliver similar metal production while mining significantly less material. This could result in potentially significant cost savings. The crushing, processing and waste storage requirements are also expected to be reduced accordingly as would, in this potential scenario, the upfront capex associated with these installations.
Anticipated benefits of the revised approach being studied include lower expected execution risks, lower expected pre-production capital and significantly reduced time to first potential production.
SolGold is also investigating options that could provide further upside to the value of the Project including:
A number of proof-of-concept level studies on these options have been initiated beginning with geotechnical and mining options. These are being followed with more detailed studies and are expected to be included in the designs for downstream processes and infrastructure. These studies are on track for the delivery of the PFS in late 2021.
The Company is of the view that the Alpala resource is one of the most significant copper-gold porphyry discoveries of the last decade. It has the potential to become a key source of future copper supply amid an expected growing medium-term market deficit, reflecting limited new project development, a declining base production and growing demand supported by the shift towards electrification and decarbonization. SolGold and Cornerstone plan to provide further progress updates as the revised PFS advances during the remainder of the year.
Commenting on today’s PFS update, SolGold Interim CEO, Keith Marshall, said:
“The revised mine plan being studied underpins the whole of the Alpala Project. The plan being studied is smaller in scale initially, but a much more selective and simpler approach to mining the deposit. In my view, the big advantages of underground mining over open pit mining are sequencing and selectivity. With underground mining you can target which areas of the orebody you want to mine and when. The previously studied plan was the equivalent of an inverted open pit, with limited selectivity, that would likely have resulted in the mining of larger volumes of waste material.
We are now studying a plan that would introduce an upper extraction level that may offer earlier access to high grade material. We are also considering dual access, through shafts and a decline which might be developed from both ends concurrently. Through the study of the revised approach, we are hopeful of arriving at a plan that will not sterilize any of the resource, furthering SolGold’s goal of developing the resource with a view to the interests of all stakeholders, particularly Ecuador.
I am very encouraged with the progress of the study of this revised approach and I am confident that it should offer a robust but flexible solution to the development of a mine at Alpala.”
Qualified Person
Yvan Crepeau, MBA, P.Geo., Cornerstone's Vice President, Exploration and a qualified person in accordance with National Instrument 43-101, is responsible for supervising the exploration program at the Cascabel project for Cornerstone and has reviewed and approved the information contained in this news release.
About Cornerstone
Cornerstone Capital Resources Inc. is a mineral exploration company with a diversified portfolio of projects in Ecuador and Chile, including the Cascabel gold-enriched copper porphyry joint venture in northwest Ecuador. Cornerstone has a 21.4% direct and indirect interest in Cascabel comprised of (i) a direct 15% interest in the project financed through to completion of a feasibility study and repayable at Libor plus 2% out of 90% of its share of the earnings or dividends from an operation at Cascabel, plus (ii) an indirect interest comprised of 7.5% of the shares of joint venture partner and project operator SolGold Plc. Exploraciones Novomining S.A. (“ENSA”), an Ecuadoran company owned by SolGold and Cornerstone, holds 100% of the Cascabel concession. Subject to the satisfaction of certain conditions, including SolGold’s fully funding the project through to feasibility, SolGold Plc will own 85% of the equity of ENSA and Cornerstone will own the remaining 15% of ENSA.
Further information is available on Cornerstone’s website: www.cornerstoneresources.com and on Twitter. For investor, corporate or media inquiries, please contact ir@cornerstoneresources.ca, or:
Investor Relations:
Mario Drolet; Email: Mario@mi3.ca; Tel. (514) 904-1333
Due to anti-spam laws, many shareholders and others who were previously signed up to receive email updates and who are no longer receiving them may need to re-subscribe at http://www.cornerstoneresources.com.
Cautionary Notice:
This news release may contain ‘Forward-Looking Statements’ that involve risks and uncertainties, such as statements of Cornerstone’s beliefs, plans, objectives, strategies, intentions and expectations. The words “potential,” “anticipate,” “forecast,” “believe,” “estimate,” “intend”, “trends”, “indicate”, “expect,” “may,” “should,” “could”, “project,” “plan,” or the negative or other variations of these words and similar expressions are intended to be among the statements that identify ‘Forward-Looking Statements.’ Although Cornerstone believes that its expectations reflected in these ‘Forward-Looking Statements’ are reasonable, such statements may involve unknown risks, uncertainties and other factors disclosed in our regulatory filings, viewed on the SEDAR website at www.sedar.com. For us, uncertainties arise from the behaviour of financial and metals markets, predicting natural geological phenomena and from numerous other matters of national, regional, and global scale, including those of an environmental, climatic, natural, political, economic, business, competitive, or regulatory nature. These uncertainties may cause our actual future results to be materially different than those expressed in our Forward-Looking Statements. Although Cornerstone believes the facts and information contained in this news release to be as correct and current as possible, Cornerstone does not warrant or make any representation as to the accuracy, validity or completeness of any facts or information contained herein and these statements should not be relied upon as representing its views after the date of this news release. While Cornerstone anticipates that subsequent events may cause its views to change, it expressly disclaims any obligation to update the Forward-Looking Statements contained herein except where outcomes have varied materially from the original statements.
On Behalf of the Board,
Brooke Macdonald
President and CEO
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
_______________
1 See “About Cornerstone” below.
2 See “Cascabel Property NI 43-101 Technical Report, Alpala Porphyry Copper-Gold-Silver Deposit - Mineral Resource Estimation, January 2021” with an Effective date: 18 March 2020 and Amended Date: 15 January 2021 (the “Amended Technical Report”), filed at www.Sedar.com on January 29, 2021: https://cornerstoneresources.com/site/assets/files/5574/2101_cascabel_mre3.pdf