After-tax NPV5 of $178.0M & 36% IRR at US$1,400/oz Au
ALL AMOUNTS DISCUSSED ARE DENOMINATED IN U.S. DOLLARS
THUNDER BAY, ON, Jan. 18, 2021 /CNW/ - Premier Gold Mines Limited ("Premier", the "Company") (TSX: PG) (OTCPK: PIRGF) is pleased to announce the updated results of its Preliminary Economic Assessment ("PEA") on the Cove Project at its 100%-owned McCoy-Cove Property ("Project" and "Property") located near Battle Mountain, Nevada.
Highlights of the updated PEA results and life-of-mine plan ("LOM") include:
"The PEA underscores the importance of McCoy-Cove as one of the cornerstone assets in our soon-to-be spun-out i–80 Gold Corp, whose focus will remain the exploration and development of quality gold projects in Nevada, USA", stated Ewan Downie, President and CEO of Premier Gold Mines. "Our go-forward plans for the project includes an exploration ramp to allow an aggressive underground drill program to upgrade and expand mineral resources in advance of a future Feasibility Study and also provide a platform to increase recoverable gold resources and delineate the deposit still open down-plunge".
Project Economics
The Project will process 2.97 million tons at an average grade of 0.303 oz/t Au producing 743,000 ounces of gold over an 8-year period. The cost profile includes an average cash cost (net of by-product credits) of $859 per ounce of gold sold and an AISC of $948 (net of by-product credits) per ounce of gold sold. Annual full year gold production will average 102,000 ounces per year over the 8-year mine life.
The PEA assumes mining of mineral resources in the Helen and Gap deposits only. Potential exists to increase mineral resources as the deposits remain open for expansion. New mineral resources may also be found along the Cove South Deep and 2201 zones and this potential will be reviewed following underground exploration and delineation drilling.
Project after-tax NPV5 is estimated to be $178.0 million at a gold price of US$1,400/oz with a 4.5-year payback from a positive construction decision and an after-tax IRR of 36% as shown in Table 1.
______________________ |
1 Based on a gold equivalent cut-off grade of 0.141 oz/t or 4.83 g/t Au. |
Table 1: Summary of Economic Parameters and PEA Results
Gold price - base case (US$/oz) | 1,400 |
Mine life (years) | 8 |
Maximum mining rate (tons/day) | 1,222 |
Average grade (oz/t Au, g/t Au) | 0.303 / 10.39 |
Average gold recovery (roaster %) | 79.3 |
Average gold recovery (autoclave %) | 85.2 |
Average full year annual gold production (koz) | 102 |
Total recovered gold (koz) | 743 |
Pre-development costs ( M$) | 23.9 |
Mine Construction Capital (M$) | 81.9 |
Sustaining capital (M$) | 25.2 |
Cash cost ($/oz) | 859 |
All-in sustaining cost ($/oz) | 948 |
Project after-tax NPV5% (M$) | 178.3 |
Project after-tax IRR (%) | 36 |
Total undiscounted after-tax cash flow over the life of the Project is estimated to be $230 million. Some $23.9 million in pre-development costs have been excluded from NPV and IRR calculations within the PEA. These pre-development costs relate to advanced exploration, resource conversion, baseline studies and permitting activities to be completed prior to the commencement of mine construction and are considered sunk costs.
Sensitivities of the Project NPV to the gold price and other Project variables are presented in Table 2.
Table 2: After-Tax Sensitivity Analysis to NPV5 and After-Tax IRR
NPV5% | IRR | |||||
PEA Variable | -20% | PEA | +20% | -20% | PEA | +20% |
($ M) | ($ M) | ($ M) | (%) | (%) | (%) | |
Operating Costs | 241 | 178 | 110 | 45 | 36 | 26 |
Capital Costs | 196 | 178 | 160 | 45 | 36 | 30 |
Gold Price | 42 | 178 | 306 | 14 | 36 | 53 |
The PEA is preliminary in nature, it includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the results of the PEA will be realized.
Location
The McCoy-Cove Property is located immediately south of Nevada Gold Mines' Phoenix Mine, 32 miles south of the Town of Battle Mountain, in Lander County, Nevada. The Property hosts the historic Cove mine, operated by Echo Bay Mines Ltd. (Echo Bay) between 1987 and 2001, that produced 2.6 million ounces of gold and 100 million ounces of silver and the historic McCoy mine that produced more than 600,000 ounces of gold.
The property benefits from significant historic geological datasets, local and regional infrastructure that include its proximity to paved highways, electric power, and pre-existing mine infrastructure. Premier is proud of its relationships within local communities including the Town of Battle Mountain, which provides important manpower and services to the Property and serves as the location of its regional office.
Geology & Mineral Resources
The McCoy-Cove Property is in the central Nevada portion of the Basin and Range Province, which underwent regional extension during the Tertiary period that created the present pattern of alternating largely fault bounded ranges separated by alluvial filled valleys. The property lies west of the central part of the Battle Mountain-Eureka Trend and hosts four distinct mineralization type Carlin-style, polymetallic sheeted veins, carbonate replacement (Manto), and skarn. The Helen, CSD Gap and CSD deposits are Carlin-style deposits while the 2201-VG zone is comprised of steeply dipping polymetallic sheeted veins.
The Cove (Gap) deposit remains open for expansion down-plunge and the 2201 zone remains open along strike and at depth.
Mineral resources were constrained using a gold equivalent cut-off grade of 0.141 oz/t Au. The Project mineral resources are summarized in Table 3.
Table 3: Mineral Resource Estimate
Tons (000) | Tonnes(t) | Au(oz/ton) | Au(g/t) | Ag(oz/ton) | Ag(g/t) | Au ozs | Ag ozs | ||
Indicated | |||||||||
Helen | 614 | 557 | 0.356 | 12.2 | 0.100 | 3.4 | 219 | 62 | |
Gap | 176 | 160 | 0.345 | 11.8 | 0.431 | 14.8 | 61 | 76 | |
CSD | 319 | 289 | 0.224 | 7.7 | 2.528 | 86.7 | 71 | 806 | |
2201 | - | - | - | - | - | ||||
Total Indicated | 1,110 | 1,007 | 0.316 | 10.9 | 0.850 | 29.1 | 351 | 943 | |
Inferred | |||||||||
Helen | 1,585 | 1,438 | 0.324 | 11.1 | 0.116 | 4.0 | 514 | 184 | |
Gap | 1,815 | 1,646 | 0.309 | 10.6 | 0.448 | 15.4 | 561 | 813 | |
CSD | 552 | 501 | 0.198 | 6.8 | 2.205 | 75.6 | 109 | 1,218 | |
2201 | 310 | 282 | 0.546 | 18.7 | 1.127 | 38.7 | 169 | 350 | |
Total Inferred | 4,262 | 3,867 | 0.317 | 10.9 | 0.602 | 20.6 | 1,353 | 2,565 | |
|
Mining
The mine will be accessed by a single ramp extending from the surface (elevation 4,625 ft) to the lowest extent of planned mining (elevation 3,430 ft). The access ramp will be large enough to accommodate 30- ton trucks. A series of raises will provide secondary egress and ventilation. A mining contractor will extract the mineralization using drift and fill mining methods at an average rate of 1,180 tons per day.
Metallurgy & Processing
Metallurgical testing was completed by SGS Laboratories under the direction of Jacobs Engineering on behalf of Premier. Composite samples from the Helen and Gap zones underwent whole ore cyanidation testing, roasting and calcine cyanidation tests, and pressure oxidation with cyanidation of the residues. Results indicate that Gap mineralization responds better with pressure oxidation while the Helen mineralization performs better with roasting. Recoveries were assigned to each mineralized lens from the associated composite test results. The recoveries stated herein represent a weighted average value for all mineralization contained in the mine plan of 82.5% for gold and 67.1% for silver.
There are three roasting facilities and two pressure oxidation facilities located in northern Nevada which are amenable to processing the Cove mineralization. The PEA incorporates toll-milling arrangements with associated over-the-road trucking costs for both process methods.
Infrastructure
General infrastructure for the Project will include:
Pre-Development and Capital Costs
The breakdown of pre-development and capital costs is provided in Table 4.
Table 4: Pre-Development and Capital Cost
Pre-Development | Mine Construction | Sustaining | |
Environmental and Permitting | 2.5 | 1.0 | 1.0 |
Helen Dewatering | 0 | 14.8 | 0 |
Gap Dewatering | 0 | 28.7 | 0 |
Electrical Service and Powerline | 0.2 | 3.1 | - |
Mine Development Helen | 8.3 | 17.9 | 13.9 |
Mine Development Gap | - | 0.3 | 9.2 |
Mine Facilities | 1.3 | 6.2 | 0.9 |
Pre-Production Expense | 6.1 | 1.7 | 0 |
Mobile Equipment | - | - | - |
Resource Conversion Drilling | 4.4 | - | - |
Contingency (15% Excluding Drilling and Development) | 1.2 | 8.4 | 0.3 |
Total *columns may not add due to rounding | 23.9 | 81.9 | 25.2 |
Sustaining capital is required during operations for mine development, dewatering, and other underground infrastructure.
Operating Costs
The average operating cost is $859/oz Au or $215/t milled over the LOM. The AISC, which includes royalties, closure, reclamation, and sustaining capital costs, averages $948/oz Au. Table 5 presents the LOM operating costs.
Table 5: Life-of-Mine Operating Cost Summary
Category | Total Costs | Unit Cost | Cost per Ounce |
Mining | 296 | 99.53 | 398 |
Transportation & Processing | 219 | 73.82 | 295 |
Electrical Power | 41 | 13.76 | 55 |
G&A, Royalties and Net Proceeds tax | 89 | 29.96 | 120 |
By Product Credits | (6) | (2.04) | (8) |
Total Operating Cost | 639 | 215.01 | 859 |
Closure & Reclamation | 15 | 5.15 | 21 |
Income Tax | 25 | 8.50 | 34 |
Sustaining Capital | 25 | 7.77 | 34 |
All-in Sustaining Cost | 704 | 237.08 | 948 |
Permitting
The McCoy-Cove Project is fully permitted under an Environmental Assessment ("EA") to develop an exploration ramp, complete underground diamond drilling, and to test mine up to 120,000 tons of potentially economic mineralization. The PEA assumes that a new EA will be required to dewater ahead of mining in the Helen Zone. It is expected that an Environmental Impact Statement ("EIS") will be required to dewater ahead of mining. Collection of baseline data, permitting, and bonding for the EIS is expected to be completed in Q2 2024. These timelines may be accelerated pending the interpretation and implementation of recent guidelines given to regulatory agencies by the federal government in the United States.
Next Steps
The focus for the remainder of 2021 and 2022 includes laboratory and economic evaluations of alternative processing methods, optimizing the mine plan with the hydrological model, completion of baseline studies needed to kick off an EIS, and beginning development of an exploration decline to support underground diamond drilling to upgrade and increase mineral resources. Completion of these activities and a feasibility study will occur in 2023-24.
A technical report for the McCoy-Cove Project supporting the results of the PEA will be prepared in accordance with National Instrument 43-101 and will be filed on SEDAR at www.sedar.com and on the Company's websites within 45 days.
All abbreviations used in this press release are available by following this link (click here).
Qualified Person & QA/QC
Scientific and technical information in this press release has been reviewed and approved by Dagny Odell, P.E. (NV Lic#13708) of Practical Mining LLC, an "independent qualified person" within the meaning of National Instrument 43–101.
Qualified Person
Practical Mining LLC., under the supervision of Dagny Odell, P.E., Laura Symmes, SME, and Robert Raponi, P. Eng. each being Qualified Persons within the meaning National Instrument (NI) 43-101, was the lead consultant for the updated PEA.
All abbreviations used in this press release are available by following this link (click here).
Non-IFRS Measures
The Company has included certain terms and performance measures commonly used in the mining industry that are not defined under International Financial Reporting Standards ("IFRS") within this document. These Non-IFRS measures include but are not limited to cash cost per ounce sold, all in sustaining cost ("AISC") per ounce sold. Non–IFRS measures do not have any standardized meaning prescribed under IFRS, and therefore, they may not be comparable to similar measures employed by other companies. The data presented is intended to provide additional information and should not be considered in isolation or as a substitute for measures prepared in accordance with IFRS. Readers should refer to the Company's Management Discussion and Analysis under the heading "Non-IFRS Measures" for a more detailed discussion of how such measures are calculated.
Certain statements in this release constitute "forward-looking statements" or "forward-looking information" within the meaning of applicable securities laws. Such statements and information involve known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of the company, its projects, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. Such statements can be identified by the use of words such as "may", "would", "could", "will", "intend", "expect", "believe", "plan", "anticipate", "estimate", "scheduled", "forecast", "predict" and other similar terminology, or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved. These statements reflect the Company's current expectations regarding future events, performance and results and speak only as of the date of this release.
Such forward-looking statements include but are not limited to the updated results of the Preliminary Economic Assessment on the Project, such as future estimates of internal rates of return, net present value, future production, estimates of cash cost, proposed mining plans and methods, mine life estimates, cash flow forecasts, metal recoveries, estimates of capital and operating costs, timing for permitting and environmental assessments and the size and timing of phased development of the Project. Furthermore, with respect to this specific forward-looking information concerning the development of the Project, the company has based its assumptions and analysis on certain factors that are inherently uncertain. Uncertainties include: (i) the adequacy of infrastructure; (ii) geological characteristics; (iii) metallurgical characteristics of the mineralization; (iv) the ability to develop adequate processing capacity; (v) the price of gold and silver; (vi) the availability of equipment and facilities necessary to complete development; (vii) the cost of consumables and mining and processing equipment; (viii) unforeseen technological and engineering problems; (ix) accidents; * currency fluctuations; (xi) changes in regulations; (xii) the compliance by joint venture partners with terms of agreements; (xiii) the availability and productivity of skilled labour; (xiv) the regulation of the mining industry by various governmental agencies; (xv) the ability to raise sufficient capital to develop such projects; (xiv) changes in project scope or design; and (xv) political factors.
Forward-looking statements and information involve significant risks and uncertainties, should not be read as guarantees of future performance or results and will not necessarily be accurate indicators of whether or not such results will be achieved. A number of factors could cause actual results to differ materially from the results discussed in the forward-looking statements or information, including, but not limited to, the factors discussed below and elsewhere in this release, as well as unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; the failure of parties to contracts with the company to perform as agreed; social or labour unrest; changes in commodity prices; and the failure of exploration programs or studies to deliver anticipated results or results that would justify and support continued exploration, studies, development or operations.
Although the forward-looking statements contained in this release are based upon what management of the company believes are reasonable assumptions, the company cannot assure investors that actual results will be consistent with these forward-looking statements. These forward-looking statements are made as of the date of this release and are expressly qualified in their entirety by this cautionary statement. Except as required under applicable securities laws, the company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this release.
The Company's actual results could differ materially from those anticipated in these forward-looking statements as a result of the factors described herein and set out in the "Risks and Risk Management" section in the company's Q3 2020 MD&A and under the heading "Risk Factors" in its current annual information form
SOURCE Premier Gold Mines Limited
View original content to download multimedia: http://www.newswire.ca/en/releases/archive/January2021/18/c3556.html