Retransmission-Serengeti Announces Positive PEA Results: 21% IRR Pre-tax for Kwanika Copper-Gold Project

2017-04-04 / @marketwired

 

VANCOUVER, BRITISH COLUMBIA--(Marketwired - April 4, 2017) - Serengeti Resources Inc. (TSX VENTURE:SIR)(FRANKFURT:34S) announces the completion of an independent NI 43-101 compliant Preliminary Economic Assessment ("PEA") for its 95% owned Kwanika copper-gold porphyry project located in the Quesnel Trough of North-Central British Columbia, Canada. The results of the PEA demonstrate the potential technical and economic viability of establishing a new copper-gold mine and mill complex on the property.

PEA Highlights:

  • Pre-tax NPV7% of CDN $324 million, 21.1% IRR, 15 year mine life.
  • Life of mine (LOM) metal production of 601 million pounds copper, 676,300 ounces gold, and 2.66 million ounces silver in concentrates.
  • Annual metal production of 50.4 million pounds of copper, 70,100 ounces of gold, and 181,100 ounces of silver in concentrates for the first eight years.
  • Initial capital cost of CDN $476 million plus LOM sustaining capital of $37 million for a 15,000 tpd (5.4 million tpa) mill and combined open pit, underground mining operation.
  • Projected C1 (Direct cash cost of production per pound of copper net of gold, silver credits) of US$0.70/lb/Cu for first eight years or US$1.20/lb LOM

"We are very pleased to have achieved this important milestone for the Kwanika project," commented David W. Moore, Serengeti President & CEO. "Kwanika represents an opportunity to develop a midsize green field copper-gold project in an excellent location and proven jurisdiction. Furthermore there remains excellent potential to expand and upgrade the resources considered in this study, both in the Central and South Zones. The results of this PEA have confirmed what the partnership believed was the possibility for higher grade production from the Central Zone at Kwanika and the resultant positive impact on project economics. Given the economic value we have demonstrated in this PEA, we expect our partners Daewoo Minerals Canada will elect to fund the next $7 million expenditure to earn an additional 30% interest in the project and we look forward to working with them in advancing the Kwanika project towards production," stated Moore.

PEA BASE CASE ECONOMIC RESULTS

Parameter Unit Base Case
Capital Cost CDN$ M $476
Sustaining Capital LOM CDN$ M $37
Average Op Cost/tonne CDN$ $21.15
Pre-Tax Net Revenue CDN$ M $710.1
Pre-Tax NPV7% CDN$ M $324.4
Pre-Tax IRR and Payback 21.1% and 3.7 years
Post-Tax Net Revenue CDN$ M $475.1
Post-Tax NPV7% CDN$ M $191.2
Post-Tax IRR and Payback 16.6% and 4.0 years
Metal Price Cu US$/lb $2.90
Au US$/oz $1,270
Ag US$/oz $19.00
Exchange Rate US$/CDN$ 0.77

PEA SUMMARY PRODUCTION STATISTICS

Category Units First 8 Years LOM
Tonnes Milled Kt 43,201 78,855
Average Grade Cu % 0.466 0.381
Au g/t 0.539 0.357
Ag g/t 1.391 1.398
Metal Production Cu M lbs 403.462 600.635
Au Moz 0.561 0.673
Ag Moz 1.449 2.659
Throughput tpd 15,000
Mine Life Yrs 15
Net Cash Cost of Production (C1)* per lb Cu US$ $0.70 $1.20
* Net Direct Cash Cost (C1) is an industry standard measure that represents the cash cost incurred at each processing stage, from mining through to recoverable metal delivered to market, less net by-product credits.
Direct Cash Costs cover: Mining, ore freight and milling costs; Mine-site administration and general expenses; Concentrate freight, smelting and smelter general and administrative costs; Marketing costs (freight and selling).

Gold, Silver credits contribute 64.3% to revenue in the first eight years or 53.0% LOM at the Kwanika project.

The PEA prepared by Moose Mountain Technical Services ("MMTS") is based on the resource model presented in the December 2016 NI43-101 technical report titled "Independent Technical Report for the Kwanika Copper-Gold Project Canada", authored by SRK Consulting (Canada) Inc. (See NR 2017-01, January 4th, 2017 or access the report through www.sedar.com for full details). SRK's Resource Estimate used a confining pit and underground shapes to define contiguous mineralization with reasonable prospects for eventual economic extraction. The resource therein is shown in the following table:

MINERAL RESOURCE STATEMENT* KWANIKA CENTRAL ZONE

Category Quantity
(x1000
Tonnes)
Cut-off
Cu Eq
(%)
Grade Contained Metal
Cu
(%)
Au
(g/t)
Ag
(g/t)
Cu
(000's lb)
Au
(000's oz)
Ag
(000's oz)
Pit Constrained
Indicated 101,500 0.13 0.31 0.32 0.96 697,200 1,040 3,120
Inferred 31,900 0.13 0.17 0.14 0.59 118,500 140 610
Underground
Indicated 29,700 0.27 0.34 0.36 1.05 222,300 350 1,010
Inferred 7,900 0.27 0.23 0.17 0.68 39,800 40 170

MINERAL RESOURCE STATEMENT* KWANIKA SOUTH ZONE

Category Quantity Grade Contained Metal
(x1000
Tonnes)
Cu
(%)
Au
(g/t)
Ag
(g/t)
Mo
(%)
Cu
(000's lb)
Au
(000's oz)
Ag
(000's oz)
Mo
(000's lb)
Inferred 33,300 0.26 0.08 1.64 0.01 191,400 80 1,760 7,470
* Pit constrained mineral resources are reported in relation to a conceptual Whittle pit shell and underground resources are reported within the area for potential underground development. Mineral resources are not mineral reserves and do not have demonstrated economic viability. All figures are rounded to reflect the relative accuracy of the estimate. All composites have been capped where appropriate.
** Pit constrained mineral resources are reported at a copper equivalent cut-off of 0.13% and underground resources are reported at 0.27%. The cut-offs are based on prices of US$3.00 per pound of copper, US$1,300 per ounce of gold, US$20 per ounce of silver, US$9.00 per lb of molybdenum and assumed recoveries of 89% for copper, 70% for gold, 75% for silver, and 60% for molybdenum.

The MMTS mining study has focused on a higher grade core of the deposit and delineated combined open pit and underground designs on the Central and South zones as follows:

Open Pit in Central and South zones

Zone Category Tonnage Cu Au Ag
(Kt) (%) (g/t) (g/t)
Central Indicated 11,752 0.372 0.387 1.076
Inferred 208 0.278 0.170 0.785
South Inferred 24,819 0.265 0.076 1.630
Note: NSR cut-off used is Cdn$11.90/tonne with a provision for mining loss of 5% and dilution of 2%

Underground Delineated Resource on the Central zone as follows:

Zone Category Tonnage Cu Au Ag
(Kt) (%) (g/t) (g/t)
Block Cave Indicated 41,410 0.455 0.522 1.364
Inferred 666 0.271 0.168 0.720
Note: To account for mining loss and dilution all material within the within stope shapes are included with no cut-off grade applied

The mine plan generates the following throughput over the 15 year operating mine life.

Mine Production /
Total tonnes milled (Kt)
Cu (%) Au (g/t) Ag (g/t)
First 8 Years* 43,201 0.466 0.539 1.391
LOM 78,855 0.381 0.357 1.398
* Included in the LOM quantities

All mineralized material classified as Indicated (67%) and Inferred (33%) Mineral Resources has been considered in the mine plan. The PEA is preliminary in nature and it includes inferred mineral resources that are considered too speculative geologically to have the economic consideration applied to them that would enable them to be characterized as mineral reserves. Mineral resources that are not mineral reserves, do not have demonstrated economic viability and there is no certainty that the results of the PEA will be realized.

Economic Analysis

Economic evaluations were generated incorporating forecasts for metal prices and US$/CDN$ exchange rate. The Base Case is a medium term forecast meant to be comparable to other recent Canadian projects. The Spot Price case is from March 1, 2017, and the Alternate Case is 10% above the Base Case. Results are shown in the following table:

Parameter Unit Base Case Spot Price Alternate
Metal Price
Copper US$/lb 2.90 2.71 3.19
Gold US$/oz 1,270 1,258 1,397
Silver US$/oz 19.00 18.47 20.90
Exchange Rate US$/CDN$ 0.77 0.75 0.77
Economic Results (Pre-Tax)
Net Revenue CDN$ M 710.1 635.3 1,040.5
NPV5% CDN$ M 411.1 361.7 635.3
NPV7% CDN$ M 324.4 282.0 519.1
NPV8% CDN$ M 286.5 247.0 468.4
NPV10% CDN$ M 219.9 185.6 379.5
IRR % 21.1 19.6 27.8
Payback years 3.7 3.9 3.0
Parameter Unit Base Case Spot Price Alternate
Economic Results (After-Tax)
Net Revenue CDN$ M 475.1 426.2 692.0
NPV5% CDN$ M 255.2 222.49 404.2
NPV7% CDN$ M 191.2 162.7 321.4
NPV8% CDN$ M 163.2 136.6 285.3
NPV10% CDN$ M 113.9 90.6 221.8
IRR % 16.6 15.3 22.1
Payback years 4.0 4.2 3.3

Project Development Plan

The proposed project is to develop a green-fields copper-gold-silver deposit with a combination of open pit and block cave underground mining for the Central Zone and open pit mining for the South Zone combined with conventional milling and flotation concentration methods. The production rate assumed is 15,000 tonnes per day with a forecast mine life of 15 years. Mineral concentrate would be trucked approximately 190 kilometers to a rail load-out facility in Fort St. James, rail to Prince Rupert, and ocean transport to Asian smelters. Forestry Service Roads and the existing Kemess mine power line which is connected to the power grid, are in the local area which reduces the offsite infrastructure costs. A traditional tailings storage facility (TSF) will be augmented by using all open pit waste to buttress the dam to increase the factor of safety and a separate water storage dam and water treatment plant are included, so that surplus water can be discharged safely to the environment and not stored in the TSF.

Forecast mine production statistics are summarized in the following table:

Metal First 8 Years
Grade Recovery
%
Total Metal
Production
Annual Metal
Production
Copper (%) 0.466 91 403,462 K lbs 50,433 K lbs
Gold (g/t) 0.539 75 561.2 K oz 70.1 K oz
Silver (g/t) 1.391 75 1,449 K oz 181.1 K oz
Metal LOM (Life of Mine)
Grade Recovery
%
Total Metal
Production
Annual Metal
Production
Copper (%) 0.381 89/91 600,635 K lbs 40,042K lbs
Gold (g/t) 0.357 70/75 676.3 K oz 45.1 K oz
Silver (g/t) 1.398 75 2,659 K oz 177.3 K oz

Assumed capital and operating costs for the operation are as follows (in CDN$):

  • Initial capital of $476.2 million including open pit pre-stripping mining costs, the start of underground access development, and construction of the processing plant, site infrastructure, construction of a tailings storage facility, access and power with a contingency of $61.0 million
  • LOM sustaining capital cost of $ 36.6 million is predominately for underground equipment when the Block Cave production starts early in the operating schedule. Ongoing underground development is included in operating costs. An additional $46.3 million is also included in operating costs for final reclamation and closure. Future studies will develop a more cost effective allocation of the costs of these activities, when more project details from the environmental studies, permitting obligations, and progressive reclamation details are known.

Open pit operation and equipment will be contractor supplied and well as underground development. Underground operations will be an owners' team for mucking and hauling from the extraction level of the Block cave.

  • Total weighted operating cost of $21.15/ tonne processed including: open pit mining $2.97 / tonne mined; LOM open pit strip ratio of 1.69, underground block cave mining $11.73 / tonne mined; mill and tailings $9.00 / tonne; G&A $1.95 / tonne

Recommendations for Further Work and Opportunities to Enhance Value

The independent consultants have recommended advancing the project to a higher level of study leading to a Pre-Feasibility Study and eventually to a Feasibility Study. The immediate work will require field work and data gathering for Pre-Feasibility engineering and baseline environmental studies in preparation for consultation with First Nations, sustainability discussions with local stakeholders and preparations for permit applications with regulators. This will include additional drilling to improve the modelled resource classification, geotechnical drilling, starting long duration waste rock characterization studies, and background environmental field surveys.

Furthermore as demonstrated by K-177 drilled in the course of the 2016 program, potential exists to significantly increase gold and to a lesser extent, copper grades, within the high grade domain of the Central Zone by drilling additional holes oriented perpendicular to the deposit's E-W long axis. K-16-179 also opened up the NW corner of Central Zone for expansion and deepening of this hole is recommended along with additional drill holes in this area. Finally the recent mine modelling as part of the PEA has demonstrated that several areas of better grade exist below the currently planned South Zone pits which with additional drilling could be brought into a future mine plan.

Daewoo Deal Terms

This PEA was completed as part of a program funded by Daewoo Minerals Canada, whereby Daewoo earned a 5% project interest by paying Serengeti $400,000 and spending $800,000 on the project within the first year. Daewoo may earn an additional 30% interest in the project, by electing within 90 days of completion of the PEA report, to fund an additional $7 million over the next two year period. Serengeti remains as project operator and is entitled to charge a 10% operator fee on expenditures beyond the initial $1.2 million. Serengeti is entitled to an NSR royalty if its project interest is diluted below 50% and also retains the right to enter into precious metal streaming transactions subject to certain off-take rights to Daewoo (see NR 2016-03, April 6th, 2016 for full details).

National Instrument 43-101 Disclosure.

The Kwanika PEA was prepared by Moose Mountain Technical Services (MMTS) under the direction of Jim Gray, P.Eng., a Qualified Person (as defined under National Instrument 43-101) who is independent of Serengeti and has reviewed and approved this news release. Marek Nowak, P. Eng. and Chad Yuhasz, P. Geo. of SRK Consulting (Canada) completed the NI 43-101 resource assessment report included in this PEA and are Qualified Persons and independent of Serengeti .

Experts contributing to this study include AMEC Consulting who produced a Caveability Assessment of the Kwanika Project and SGS Metallurgical Services Ltd. who have conducted a preliminary metallurgical test program on the Central Zone.

An updated national Instrument 43-101 Technical Report on the Kwanika Project describing the results of the PEA will be filed on SEDAR and be available on Serengeti's website at www.serengetiresources.com within 45 days.

David W. Moore, P.Geo., Serengeti Resources Inc. President & CEO is the Company's designated QP for this news release and has reviewed and validated that the information contained in the release is consistent with that provided by the QP's responsible for the PEA.

About Serengeti Resources Inc.

Serengeti is a mineral exploration company managed by an experienced team of professionals with a solid track record of exploration success. The Company is currently advancing its Kwanika copper-gold project in partnership with Daewoo Minerals Canada and exploring its extensive portfolio of properties in the highly prospective Quesnel Trough of British Columbia. A number of these other projects are available for option or joint venture and additional information can be found on the Company's website at www.serengetiresources.com.

ON BEHALF OF THE BOARD

David W. Moore, P. Geo., President, CEO and Director

Cautionary Statement

This document contains "forward-looking statements" within the meaning of applicable Canadian securities regulations. All statements other than statements of historical fact herein, including, without limitation, statements regarding exploration plans and other future plans and objectives, are forward-looking statements that involve various risks and uncertainties. There can be no assurance that such statements will prove to be accurate and future events and actual results could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from our expectations as well as a comprehensive list of risk factors are disclosed in the Company's documents filed from time to time via SEDAR with the Canadian regulatory agencies to whose policies we are bound. Forward-looking statements are based on the estimates and opinions of management on the date the statements are made, and we do not undertake any obligation to update forward-looking statements should conditions or our estimates change, other than as required by law and readers are further advised not to place undue reliance on forward-looking statements. The information in this News Release related to the Kwanika Copper/Gold Project was derived from the PEA. Statements pertaining to projected revenues and cash flows, quantity and grade of mineralized materials, estimated mineral prices are forward-looking statements. The Company cautions that this PEA is preliminary in nature, and is based on technical and economic assumptions which will be evaluated in further studies. The PEA is based on the current (as at January 2017) Kwanika estimated resource model, which consists of material in both the indicated and inferred classifications. Inferred mineral resources are considered too speculative geologically to have technical and economic considerations applied to them. The current basis of project information is not sufficient to convert the mineral resources to mineral reserves, and mineral resources that are not mineral reserves do not have demonstrated economic viability. Accordingly, there can be no certainty that the results estimated in the PEA will be realized.

Neither the TSX Venture Exchange nor its Regulation Services Provider accepts responsibility for the adequacy or accuracy of this release.

Investor Relations:
Paradox Public Relations
514-341-0408 or Toll free (in North America) 1-866-460-0408
info@paradox-pr.ca

Serengeti Resources Inc.
604-605-1300
info@serengetiresources.com
www.serengetiresources.com

Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok