VANCOVUER, BC / ACCESSWIRE / July 13, 2020 / Rockhaven Resources Ltd. (TSXV:RK) ("Rockhaven") is pleased to announce the results of an updated Preliminary Economic Assessment ("PEA") for its 100%-owned and road-accessible Klaza Deposit, located in the Dawson Range Gold Belt of southern Yukon.
PEA Highlights:
Highlights from the PEA, with a base case gold price of US$1,450/oz and an exchange rate of C$1.00 equal to US$0.72 are as follows (all figures in Canadian Dollars unless otherwise stated):
"This study demonstrates that Rockhaven's Klaza Deposit could support a mine with a long life and robust economics," stated Matt Turner, President and CEO of Rockhaven. "Since the last economic study was completed in 2016, closer spaced drilling has better defined the upper portions of the deposit, resulting in higher average grades in a superior resource category. We are very pleased with the results of this PEA and look forward to continuing to add value through additional discoveries while advancing the deposit through Pre-Feasibility. At its current ~C$35 million market capitalization, Rockhaven offers investors one of the most compelling valuations in the sector."
AMC Mining Consultants (Canada) Ltd. (mineral resource, mining, infrastructure and financial analysis) was contracted to conduct the PEA in cooperation with Blue Coast Metallurgy Ltd. (metallurgy and processing), Knight Piesold Ltd (tailings and waste management). The PEA is based on the updated Mineral Resource estimate from the Klaza Deposit (see Klaza Property Technical Report dated June 5, 2018).
The reader should be cautioned that the PEA is preliminary in nature. It includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves. There is no certainty that the results of the PEA will be realized.
Economic Results and Sensitivities
Tables I and II show economic results with varying metal prices and assumptions, and summarize projected production.
Table I: Klaza Combined Open Pit and Underground Mining - Key Economic Assumptions and Results
Klaza | Unit | Value |
Total Mineralized Rock Mined | kt | 7,464 |
Gold Grade1 | g/t | 3.4 |
Silver Grade1 | g/t | 79 |
Lead Grade1 | % | 0.6% |
Zinc Grade1 | % | 0.7% |
AuEQ Grade2 | g/t | 4.43 |
Gold Recovery1 | % | 95% |
Silver Recovery1 | % | 90% |
Lead Recovery1 | % | 80% |
Zinc Recovery1 | % | 80% |
Gold Price | US$/oz | 1,450 |
Silver Price | US$/oz | 17.00 |
Lead Price | US$/lb | 0.95 |
Zinc Price | US$/lb | 1.00 |
Payable Gold Metal3 | oz | 751,472 |
Payable Silver Metal3 | Moz | 13.8 |
Payable Lead Metal3 | Mlbs | 50.0 |
Payable Zinc Metal3 | Mlbs | 50.1 |
Payable Gold Equivalent | Oz | 980,561 |
Total Net Revenue | $M | 1,975 |
Initial Capital Costs | $M | 244 |
Sustaining Capital Costs | $M | 114 |
Operating Costs (Total)4 | $/t | 111.8 |
Operating Cash Cost (AuEQ2) | US$/oz AuEQ | 612.6 |
Total All In Sustaining Cost (AuEQ2) | US$/oz AuEQ | 875.3 |
Mine Life | Yrs | 12 |
Payback Period (Pre-tax) | Yrs | 3.9 |
Payback Period (Post-tax) | Yrs | 4.2 |
Cumulative Net Cash Flow (pre-tax) | $M | 783 |
Pre-tax NPV(5%) | $M | 529 |
Pre-tax IRR | % | 45 |
Post-tax NPV(5%) | $M | 378 |
Post-tax IRR | % | 37 |
1. LOM average
2. Gold equivalent values for mining purposes assume base case metal prices and recoveries used in the PEA and are calculated using the following formula: AuEQ=1*Au+Ag/107.82+Pb/4.14+Zn/4.68
3. Overall payable % includes treatment, transport, refining costs and selling costs
4. Includes mine operating costs, milling, and mine G&A
Table II: Klaza Economic Sensitivity Analysis (Post-tax)
-20% | BASE CASE | +20% | ||||||||
Variable | Unit | Value | NPV | IRR | Value | NPV | IRR | Value | NPV | IRR |
Gold | US$/oz | $1,160 | $211 | 24% | $1,450 | $378 | 37% | $1,740 | $540 | 49% |
Silver | US$/oz | $13.60 | $343 | 35% | $17.00 | $20.40 | $407 | 39% | ||
Mining Cost | $/t | $44.1 | $417 | 39% | $55.14 | $66.2 | $334 | 34% | ||
Processing Cost | $/t | $33.3 | $406 | 39% | $41.30 | $50.0 | $344 | 35% | ||
LOM Capital | $M | $286 | $456 | 60% | $380 | $429 | $280 | 23% |
Capital and Operating Costs
The Klaza project has been envisioned as a combined open-pit and underground mining operation. Open-pit mining is anticipated to be completed by a contract mining company while the underground operation will be owner-operator with the equipment owned and personnel employed by Rockhaven.
Grid electrical power will provide the majority of the electrical power to the project over the life of the mine. An on-site camp is envisioned to house mine and mill personnel.
Table III: Total Capital Cost Estimate
Description | Cost ($M) |
Underground development | 115 |
Flotation tailings storage & residue tailings storage | 17 |
Underground mine infrastructure | 21 |
Mobile equipment | 32 |
Processing plant | 103 |
Surface infrastructure | 16 |
Capital indirects | 10 |
Contingency | 32 |
Additional 5% sustaining for equipment rebuilds | 12 |
Total capital cost | 358 |
Initial capital | 244 |
Sustaining capital | 114 |
Table IV: Total Operating Cost Estimate
Description | Cost ($/t) |
Mining cost | 55.14 |
Processing cost | 41.64 |
General and Administration cost | 15.00 |
Total operating cost | 111.78 |
Mining
Open-pit mining is anticipated to commence in Year 1 and produce a total of 1,181 kt of mineralized rock over three years. Peak open-pit production will be 598 kt in Year 2. A total of 6,283 kt of mineralized rock is anticipated to be produced from underground operations over the 12-year mine life, beginning in Year 1. Peak underground production will be 688 kt in Years 5 through 7.
Underground mining will be accomplished using mechanized longhole open stoping on 25 m sub-levels. A minimum stope width of 3.0 m was used in this study with dilution of 0.25 m in the hanging wall and 0.1 m in the footwall. Underground access will be achieved via four separate declines for the each of the four main zones. The Central Klaza decline will start from the base of the open-pit.
Waste rock will be used to backfill underground stopes as they are mined and to construct the tailings dams. The remainder will be disposed of in waste dumps on surface.
Processing & Metallurgy
The Klaza process consists of comminution by crushing followed by semi-autogenous grinding and ball milling, with the ground product feeding a conventional sequential flotation circuit producing lead, zinc and arsenopyrite concentrates. The arsenopyrite concentrate is treated by pressure oxidation (POX), followed by cyanide leaching of the POX residue to recover the gold. Precious metals are also leached from the lead concentrate to increase the overall gold recovery to doré and enhance saleability of the concentrate. Final products from this process are precious-metal-rich lead and zinc concentrates as well as gold and silver as doré.
The processing plant will operate year-round at a rate of approximately 1,900 tonnes per calendar day, and will achieve full throughput by Year 2. The average LOM feed grade is projected to be 3.40 g/t Au, 79 g/t Ag, 0.6% lead and 0.7% zinc.
Base metal concentrates will be dewatered and containerized for shipment to smelters. Flotation tailings will be thickened and sent to a conventional tailings impoundment, and the leached pressure oxidation residue will flow through cyanide destruction and be sent to a double-lined hydromet residue storage facility.
Although this study assumes a relatively small 250 tpd onsite POX circuit would be used, an arsenopyrite concentrate could be produced for shipment to a smelter in Nevada or China. This was not considered in this study at this time but will be investigated as the project advances.
Process water will primarily be sourced from underground dewatering and surface run-off, with make-up from the nearby Klaza River as necessary.
Metallurgical testwork to support the PEA has been conducted on several composites from the Western Klaza, Central Klaza and Western BRX zones, as well as a Project-Wide Composite comprising a blend of material from these zones. Testwork included grinding, flotation and pressure oxidation work.
Opportunities to Enhance Value
This updated PEA reaffirms Rockhaven's commitment to enhancing value at the Klaza project through engineering studies and resource expansion and definition. It has highlighted several key areas that can provide significant key opportunities to further enhance the value of the Klaza project. These opportunities include:
Mineral Resources
The basis for the PEA is the Mineral Resource estimate completed by AMC Mining Consultants (Canada) Ltd. in the NI 43-101 report with an effective date of June 5, 2018 entitled "Technical Report Describing Updated Diamond Drilling, Metallurgical Testing and Mineral Resources on the Klaza Property, Yukon, Canada" which is filed on SEDAR.
A summary of this resource estimate is shown in Table V:
Table V: Mineral Resource Estimate Summary, June 5, 20181,5
Tonnes | Grade | Contained Metal | |||||||||
Au | Ag | Pb | Zn | AuEQ4 | Au | Ag | Pb | Zn | AuEQ4 | ||
(kt) | (g/t) | (g/t) | (%) | (%) | (g/t) | (koz) | (koz) | (klb) | (klb) | (koz) | |
Indicated3 | 4,457 | 4.8 | 98 | 0.7 | 0.9 | 6.3 | 686 | 14,071 | 73,268 | 92,107 | 907 |
Inferred3 | 5,714 | 2.8 | 76 | 0.6 | 0.7 | 3.9 | 507 | 13,901 | 77,544 | 89,176 | 725 |
1 CIM Definition Standards (2014) were used for reporting the Mineral Resources. Using drilling results to December 31, 2017. The Qualified Persons are Adrienne Ross, P.Geo. of AMC Mining Consultants (Canada) Ltd, and Nicholas Ingvar Kirchner, FAusIMM, MAIG. of AMC Mining Consultants Pty Ltd.
2 Near surface Mineral Resources are constrained by an optimized pit shell at a metal prices of US$1,400/oz Au, US$19/oz Ag, US$1.10/lb Pb, and US$1.25/lb Zn at an exchange rate of $0.80 US to $1.00 Canadian.
3 Cut-off grades applied to the pit-constrained and underground resource are 1.0 g/t and 2.3 g/t AuEQ respectively.
4 Gold equivalent values for the Mineral Resources assume US$1,400/oz Au, US$19/oz Ag, US$1.10/lb Pb, and US$1.25/lb Zn, and variable recoveries for the different metals.
5 Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
The Klaza Gold-Silver-Lead-Zinc Project
The Klaza property is 100% owned by Rockhaven Resources Ltd. and covers an area of 287 km2. It is favourably located within the southern part of Yukon's Dawson Range Gold Belt, in an area that hosts an historical gold mine, rich placer gold deposits and key infrastructure such as road access.
The Klaza property is located 50 km west of the village of Carmacks and is road accessible by a two-wheel drive road from the Klondike Highway. Rockhaven's exploration since it acquired the project in late 2009 has included over 100,000 m of diamond drilling and 24,000 m excavator trenching.
Drilling at the Klaza property has identified eleven main mineralized zones and numerous subsidiary structures which have a cumulative mineralized strike length greater than 10 km. The zones are hosted within a 1.8 km-wide structural corridor consisting of Mid-Cretaceous granitic country rocks. Low to intermediate sulphidation veins host gold, silver, lead and zinc mineralization.
Qualified Persons
A Technical Report supporting the PEA in accordance with National Instrument 43-101 will be filed on SEDAR (www.sedar.com) within 45 days.
The PEA was prepared under the direction of AMC Mining Consultants (Canada) Ltd. by independent industry consultants, all of whom are Qualified Persons (QP) under terms of NI 43-101 and have reviewed the technical content of this press release and approved its dissemination. QPs contributing to the PEA are listed in the following table.
Qualified Person | Position | Company | Sections of Report |
Dr A Ross, P.Geo.(BC), | Principal Geologist | AMC Mining Consultants | 1 (part), 11 ,12, 14 (part) 25 |
Mr I Kirchner, FAusIMM, | Principal Geologist | AMC Mining Consultants | 1 (part) and 14 (part) |
Mr C Martin, C.Eng. | Principal Metallurgist | Blue Coast Metallurgy Ltd. | 1 (part), 13, 17 (part), 19, 25 |
Mr M Dumala, P.Eng. | Senior Engineer and | Archer, Cathro & | 1 (part), 3 (part), 4-10, 23, 24, |
Mr G Methven, P.Eng. | Principal Mining | AMC Mining Consultants | 1 (part), 2, 3 (part), 15, 16 |
Mr M Molavi, P.Eng. | Principal Mining | AMC Mining Consultants | 1 (part), 18, 25 (part), 26 |
Mr D Warren, P.Eng. | Principal Mining | AMC Mining Consultants | 1 (part), 16 (part), 21 (part), |
Mr B Borntraeger, P.Eng. | Specialist | Knight Piésold Ltd. | 1 (part), 17 (part), 26 (part) |
All other technical information, not pertaining to the PEA, in this news release has been reviewed and approved by Matthew R. Dumala, P.Eng., of Archer, Cathro & Associates (1981) Limited and Rockhaven's designated QP.
The Qualified Persons under the terms of National Instrument 43-101 have reviewed the technical content of this press release for the Klaza property and have approved its dissemination.
About Rockhaven
Rockhaven Resources Ltd. is a mineral exploration company focused on growth through the advancement of its Klaza project. For additional information concerning Rockhaven or its Klaza project please visit Rockhaven's website at www.rockhavenresources.com.
Matthew Turner
President, CEO and Director
Rockhaven Resources Ltd.
T:604-687-2522
mturner@rockhavenresources.com
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
SOURCE: Rockhaven Resources Ltd.