For immediate release
18 January 2018
Serabi Gold plc
("Serabi" or the "Company")
Strong fourth quarter production to close the year
Serabi Gold plc (AIM:SRB, TSX:SBI), the Brazilian focused gold mining and development company, is pleased to report its fourth and final quarter production of 9,337 ounces of gold at its Palito/Sao Chico high grade gold operation in the Tapajos region of Para State, Northern Brazil.
HIGHLIGHTS
Mike Hodgson, CEO, said:
"I think it is fair to say we have enjoyed an exciting end to the year. The acquisition of Coringa has been the highlight of the fourth quarter, this being an asset we had been keen to acquire for some time and one that, I feel, will serve the Company well and bring great value over the coming years. Our day-to-day business is gold production, and I am also very pleased to report a very good final quarter, with over 9,300 ounces of gold produced.
"Overall I am delighted with the Company's performance over the second half of the year. Total gold production for the year of 37,000 ounces compares with our initial guidance at the start of 2017 of 40,000 ounces. Approximately 2,000 ounces of this shortfall arose during the second quarter from short term operational problems, now fully resolved, commissioning new underground fleet. Since then, we have seen two strong quarters, with the mine running well and the plant at capacity. We remain mill constrained as the static stockpile levels illustrate and the reported operational statistics for both the third and fourth quarters could not, realistically, have been improved by much. I am, therefore, more than happy with the recent performance and the year end results.
"The fourth quarter saw mine production from both the Palito and Sao Chico orebodies performing well. Average grades were maintained at over 8.0 g/t, and on-going mine development is progressing as planned. I am particularly pleased with how the Sao Chico orebody is shaping up, with the payability of ore development seemingly improving with depth.
"At the Palito orebody, seven veins out of the 25 veins that comprise the total geological resource are now in various stages of development and production. The Pipocas, G3, and Senna veins remain the backbone of our sources of ore, with smaller contributions from the newly developed Jatoba, Mogno, Zonta and G1 veins.
"In the plant, the performance during the quarter was as good as we can reasonably expect. The plant is at full capacity and continues to perform excellently. With approximately 43,300 tonnes of run of mine ore ("ROM") milled this represents a 7.5 per cent improvement on the same quarter in 2016. As I have mentioned in previous reports, the existence of a 15,000 tonne coarse ore stockpile and a further 40,000 tonnes of stockpiled flotation tails (with an average grade of around 3g/t of gold) on surface, is both a source of comfort and frustration.
"During 2018, we will have in place an additional independent conveyor to feed the flotation tails directly into the ball mills, allowing this material to be added directly to the current dry mill feed, and increasing the tonnage of this material that can be treated each month. We hope this operational improvement can be commissioned by the end of January.
"As reported last quarter, the results of our ore sorting test-work on the Palito ore have been excellent and we plan to introduce this to the production flowsheet during 2018. We mine the veins at Palito as selectively as possible, with head grades in excess of 8.0 g/t gold as evidence of this, but the grade of the ore feed entering the plant can be further improved using an ore sorter without compromising ounces. The ore sorter can eliminate significant volumes of waste material that are unavoidably in the ore feed, and consume plant capacity and energy. Regrettably, with the lead time involved, we will not see any real impact until late 2018 at best, but having had a surface coarse-ore stockpile of between 15,000 tonnes and 25,000 tonnes since operations commenced, one can see the operation will otherwise always be plant constrained. Payback of the estimated US$1.2 million cost is expected to be less than 12 months.
"In December, we saw the long awaited start of a surface exploration drill programme. The purpose of the programme is to drill some of the many potential vein extensions identified at Palito. The initial programme is for approximately 8,000 metres but I hope that over the course of the year we will be able to undertake further drilling, including, in particular, a programme at Sao Chico. The Palito orebody hosts a resource that extends over a one kilometre strike length, but sits within a trend and there are now clearly indications that have allowed the veins and their mineralisation to be traced over approximately four kilometres. The continuity, grade and payability of the ore in these veins still needs to be established, but only drilling will determine this. The Sao Chico orebody is completely open along strike with very little information outside the immediate mine limits. Again there are strong indications that substantial strike extensions of the principal vein and adjacent veins are waiting to be defined.
"Ultimately, we have plans that would involve a much more ambitious drilling programme targeting up to two million ounces of total mineral resource across the two ore-zones, with the full programme, totalling 60,000 meters, to be completed in two phases. This initial 8,000 metres forms part of phase one and is a programme we can start comfortably and commit to out of operational cash flow. I will be providing further updates on this programme, as results are generated, during the first quarter of 2018.
"A concern voiced by many investors about junior gold production companies is their ability to consistently, month after month, deliver on production. Serabi has now since the start of 2016 enjoyed eight quarters of regular production and averaged over 9,500 ounces of gold per quarter over this period, which I feel clearly demonstrates our ability to deliver consistency and stability.
"The acquisition of Coringa, it's permitting and development over the forthcoming period along with successful exploration results in 2018 will, we hope, form the basis of significant expansion of gold production for Serabi, as we seek to establish ourselves as a significant gold producer in Brazil with a target of an annualised production rate of 100,000 ounces within the next two years."
Results
Total production for the fourth quarter of 2017 was 9,337 ounces of gold, generated from the processing of 43,345 tonnes of ore at overall average grades of 7.27 g/t of gold, which was sourced from mined ore from the Palito and Sao Chico orebodies, supplemented with lower grade surface stockpiled ROM and flotation tailings. Mined tonnage for the quarter totalled 49,011 tonnes with a grade of 8.25 g/t of gold.
At 31 December 2017, there were coarse ore stocks of approximately 15,000 tonnes of ore with an average grade of 3.0 g/t of gold, and approximately 40,000 tonnes of flotation tails with an average grade of 3.0 g/t of gold. These stockpiles are being consumed, albeit not as quickly as forecast, and for now the operation remains plant constrained.
A total of 2,762 metres of horizontal development has been completed during the quarter, of which approximately 1,410 metres was ore development. The balance is the ramp, cross cuts and stope preparation development.
2018 Production Guidance
Management does not anticipate a major shift in mine performance and therefore hard rock gold production, in 2018 compared with 2017. However, with the ability to process increased levels of stockpiled flotation tails in 2018, management expects that gold production for 2018 will exceed that of 2017 and be up to 40,000 ounces.
Key Operational Information
SUMMARY PRODUCTION STATISTICS FOR THE FOUR QUARTERS TO 31 DECEMBER 2017 | ||||||||||||||
Qtr 1 | Qtr 2 | Qtr 3 | Qtr 4 | Year to Date | Qtr 1 | Qtr 2 | Qtr 3 | Qtr 4 | Total | |||||
2017 | 2017 | 2017 | 2017 | 2017 | 2016 | 2016 | 2016 | 2016 | 2016 | |||||
Horizontal development - Total | Metres | 2,251 | 1,855 | 2,996 | 2,762 | 9,864 | 2,925 | 2,941 | 2,649 | 2,694 | 11,209 | |||
Mined ore - Total | Tonnes | 36,918 | 41,684 | 41,263 | 49,011 | 168,876 | 37,546 | 33,606 | 43,133 | 44,579 | 158,864 | |||
Gold grade (g/t) | 10.12 | 7.80 | 9.80 | 8.25 | 8.92 | 11.02 | 9.56 | 9.61 | 8.94 | 9.74 | ||||
Milled ore | Tonnes | 41,722 | 43,294 | 44,205 | 43,345 | 172,565 | 36,615 | 39,402 | 42,464 | 40,485 | 158,966 | |||
Gold grade (g/t) | 7.62 | 6.29 | 7.28 | 7.27 | 7.11 | 8.58 | 8.17 | 8.08 | 7.60 | 8.11 | ||||
Gold production (1) (2) | Ounces | 9,861 | 8,148 | 9,657 | 9,337 | 37,004 | 9,771 | 9,896 | 10,310 | 9,413 | 39,390 |
This announcement is inside information for the purposes of Article 7 of Regulation 596/2014.
The person who arranged for the release of this announcement on behalf of the Company was Clive Line, Director.
Enquiries:
Serabi Gold plc | |
Michael Hodgson | Tel: +44 (0)20 7246 6830 |
Chief Executive | Mobile: +44 (0)7799 473621 |
Clive Line | Tel: +44 (0)20 7246 6830 |
Finance Director | Mobile: +44 (0)7710 151692 |
Email: contact@serabigold.com | |
Website: www.serabigold.com | |
Beaumont Cornish Limited Nominated Adviser and Financial Adviser | |
Roland Cornish | Tel: +44 (0)20 7628 3396 |
Michael Cornish | Tel: +44 (0)20 7628 3396 |
Peel Hunt LLP UK Broker | |
Ross Allister | Tel: +44 (0)20 7418 8900 |
Chris Burrows | Tel: +44 (0)20 7418 8900 |
Blytheweigh Public Relations | |
Tim Blythe | Tel: +44 (0)20 7138 3204 |
Camilla Horsfall | Tel: +44 (0)20 7138 3224 |
Copies of this announcement are available from the Company's website at www.serabigold.com.
Neither the Toronto Stock Exchange, nor any other securities regulatory authority, has approved or disapproved of the contents of this announcement.
GLOSSARY OF TERMS
The following is a glossary of technical terms:
"Au" means gold.
"assay" in economic geology, means to analyze the proportions of metal in a rock or overburden sample; to test an ore or mineral for composition, purity, weight or other properties of commercial interest.
"development" - excavations used to establish access to the mineralised rock and other workings
"DNPM" is the Departamento Nacional de Produção Mineral.
"grade" is the concentration of mineral within the host rock typically quoted as grammes per tonne (g/t), parts per million (ppm) or parts per billion (ppb).
"g/t" means grams per tonne.
"granodiorite" is an igneous intrusive rock similar to granite.
"igneous" is a rock that has solidified from molten material or magma.
"Intrusive" is a body of igneous rock that invades older rocks.
"on-lode development" - Development that is undertaken in and following the direction of the Vein
"mRL" - depth in metres measured relative to a fixed point - in the case of Palito and Sao Chico this is sea-level. The mine entrance at Palito is at 250mRL.
"saprolite" is a weathered or decomposed clay-rich rock.
"stoping blocks" - a discrete area of mineralised rock established for planning and scheduling purposes that will be mined using one of the various stoping methods.
"vein" is a generic term to describe an occurrence of mineralised rock within an area of non-mineralised rock.
Qualified Persons Statement
The scientific and technical information contained within this announcement has been reviewed and approved by Michael Hodgson, a Director of the Company. Mr Hodgson is an Economic Geologist by training with over 26 years' experience in the mining industry. He holds a BSc (Hons) Geology, University of London, a MSc Mining Geology, University of Leicester and is a Fellow of the Institute of Materials, Minerals and Mining and a Chartered Engineer of the Engineering Council of UK, recognising him as both a Qualified Person for the purposes of Canadian National Instrument 43-101 and by the AIM Guidance Note on Mining and Oil & Gas Companies dated June 2009.
Forward Looking Statements
Certain statements in this announcement are, or may be deemed to be, forward looking statements. Forward looking statements are identified by their use of terms and phrases such as ''believe'', ''could'', "should" ''envisage'', ''estimate'', ''intend'', ''may'', ''plan'', ''will'' or the negative of those, variations or comparable expressions, including references to assumptions. These forward looking statements are not based on historical facts but rather on the Directors' current expectations and assumptions regarding the Company's future growth, results of operations, performance, future capital and other expenditures (including the amount, nature and sources of funding thereof), competitive advantages, business prospects and opportunities. Such forward looking statements reflect the Directors' current beliefs and assumptions and are based on information currently available to the Directors. A number of factors could cause actual results to differ materially from the results discussed in the forward looking statements including risks associated with vulnerability to general economic and business conditions, competition, environmental and other regulatory changes, actions by governmental authorities, the availability of capital markets, reliance on key personnel, uninsured and underinsured losses and other factors, many of which are beyond the control of the Company. Although any forward looking statements contained in this announcement are based upon what the Directors believe to be reasonable assumptions, the Company cannot assure investors that actual results will be consistent with such forward looking statements.
ENDS