DICOT, UK / ACCESSWIRE / March 17, 2021 / Altus Strategies Plc (AIM:ALS)(TSXV:ALTS)(OTCQX:ALTUF) announces the completion of a strategic review ("Strategic Review") by independent consultants Mining Plus UK Ltd ("Mining Plus"), on the Company's 97% owned high-grade Bikoula iron ("Fe") project ("Bikoula" or the "Project") located in southern Cameroon. The Strategic Review will be used to determine the next steps for the development of the Project.
Highlights:
Steven Poulton, Chief Executive of Altus, commented:
"We are pleased to report that independent consulting firm Mining Plus has completed a strategic economic review of the Company's high grade Bikoula iron project in southern Cameroon. The Project hosts a substantial colluvial iron weathered blanket, which rests above a primary iron deposit. The Strategic Review examined the processing, product specification and transportation options for Bikoula and will assist the Company in advancing the Project through next stages of development.
‘'As previously reported, preliminary metallurgical test-work on representative samples from Bikoula has yielded a high grade 62.26% Fe concentrate, using gravity separation alone. With only 25% of the 13 km long strike length of Bikoula having been tested to date, we believe the Project has considerable exploration upside potential. Recent infrastructure improvements in the region, including a containerised deep-water port at Kribi as well as significant road improvements, are expected to further enhance the economics of the Project.
"The Project's economics are supported by the price of iron ore, which has traded above US$100/tonne since June 2020. The Company believes Bikoula represents an attractive standalone iron asset and we look forward to providing an update on the Project in due course."
Bikoula: Strategic Review
Mining Plus was engaged by the Company to produce an in-depth Strategic Review of the Project, analysing the work completed to date to create an updated financial model. The Strategic Review incorporates the potential positive impacts from recent infrastructure upgrades in Cameroon, including the completion of the deep water port at Kribi (located 350 km to the west of the Project) and the construction of new roads.
Mining Plus modelled the likely capital and operational expenditures, including transportation costs from the Project by road to Kribi. The likely product specification, processing routes and shipping options (including via container) were also reviewed. The Strategic Review will now be used by the Company to determine the next steps for developing the Project, including the potential to undertake a resource expansion drilling programme.
Bikoula: Project Summary
The 194 km2 Bikoula Project comprises the contiguous Bikoula and Ndjele exploration licences which are 99 km2 and 95 km2 in size respectively. Both of these licences were selected based on the presence of a significant magnetic anomaly coincident with historically mapped Banded Iron Ore Formation ("BIF"). The BIFs form the westerly strike extension of the Nkout iron deposit and are approximately 160 km northwest of the Mbalam iron deposit. A high resolution airborne magnetic survey completed by the Company has identified numerous priority drill targets.
Bikoula: Colluvial Blanket
Mineralisation at Bikoula comprises a blanket of colluvial haematite, which is typically mapped as 200-300m wide and reaches up to 500m wide in places. The colluvial blanket is located at surface and is typically up to 10m deep and reaches up to 23.7m based on drill undertaken by Altus. In places, it rests directly above a horizon of supergene enriched haematite, which in turn sits above a significant BIF.
Bikoula: Historic Work
As previously reported, Altus has undertaken systematic drilling and surface pitting over approximately 25% of the 13 km long Libi Hills Prospect.
Historic drilling by Altus
As previously reported, Altus has to date completed 48 diamond drill holes, totalling approximately 3,900m, at Bikoula. Over half of the holes intersected at least 20m of >40% Fe. Significant intersections (considered approximate true width) include:
JORC Mineral Resource Estimate
The Project hosts an iron deposit which is the subject of an historic independent Mineral Resource Estimate ("MRE") prepared by Coffey Mining South Africa (Pty) Ltd entitled "Mineral Resource Estimation and Classification of the Bikoula Iron Ore Project in Cameroon" dated April 2014 which Altus believes remains relevant and reliable. The MRE is reported in accordance with the JORC Code (the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves) under which an "inferred resource" is considered substantially similar to NI 43-101.
Table 1. JORC Inferred MRE (non-43-101), dated April 2014 (non-beneficiated)
Zone | Rock Type | Tonnes | Fe | SiO2 | P | TiO2 | Al2O3 | S | LOI3 |
Libi | Colluvium | 39,000,000 | 43.0 | 13.1 | 0.09 | 0.8 | 14.8 | 0.04 | 9.3 |
Supergene | 5,000,000 | 52.7 | 14.3 | 0.07 | 0.7 | 5.1 | 0.02 | 4.1 | |
Lombo | Colluvium | 1,000,000 | 43.6 | 22.0 | 0.09 | 0.4 | 8.1 | 0.03 | 6.2 |
Supergene | 1,000,000 | 38.9 | 35.3 | 0.08 | 0.2 | 4.4 | 0.02 | 3.4 | |
Total | 46,000,000 | 44.2 | 13.9 | 0.08 | 0.7 | 13.4 | 0.03 | 8.5 |
Notes:
The key assumptions, parameters, and methods used to prepare the MRE were:
A Qualified Person has not done sufficient work to classify the historical MRE as a current mineral resource and Altus is not treating the historical MRE as a current mineral resource. However, it remains relevant to the Project and Altus believes it is also reliable. To verify the Historical Mineral Resource so that it can be considered a current mineral resource, a qualified resource consultant would need to review historical drilling data and prepare a mineral resource estimate in accordance with current resource methodology.
Metallurgical testwork
As previously reported, the colluvial and supergene mineralisation from Bikoula has been tested by Bureau Veritas (Perth) and SGS (Truro), respectively, and returned positive results, indicating a yield of 62.26% Fe concentrate from gravity separation alone.
Illustrations
The following figures have been prepared by Altus and relate to the disclosures in this announcement and are visible in the version of this announcement on the Company's website (www.altus-strategies.com) or in PDF format by following this link: https://altus-strategies.com/site/assets/files/5062/altus_nr_-_bikoula_17_march_2021.pdf
Bikoula Project: Location
The 194 km2 Bikoula Project, comprising the Bikoula and Ndjele exploration licences, is located in southern Cameroon, approximately 150 km southeast of the capital city of Yaoundé. The Project is accessible via a network of predominantly paved roads which also connect the Project to the recently constructed deep-water container port at Kribi. Bikoula is situated within 30 km from a proposed trans-Cameroon railway line that aims to service a number of iron deposits in the region, including the Mbalam and Nkout deposits, the latter of which is located directly along strike of the Project.
Bikoula Project: Geology
The Bikoula project was selected based on the presence of a significant magnetic geophysical signature. The Project area is underlain by the Ntem Unit of the Archaean Ntem Complex which is comprised of two main ‘series' - an intrusive group comprising tonalities and granodiorites, as well as a banded group made up of deformed granulitic gneisses. In addition, the complex hosts a number of discontinuous greenstone belts that are typically sheared and faulted, containing paragneisses, amphibolites, pyroxenites and banded iron formations.
Within the Project, metasedimentary rocks represent an interbedded sequence of exhalative chemical sediments and clastic units which weather near surface and grade into primary banded iron formations at depth. These steeply dipping iron-rich units trend along an approximately NW-SE strike and are sporadically cut by a number of E-W and NE-SW trending faults. Colluvial iron mineralisation at Bikoula comprises a blanket of unconsolidated weathered supergene BIF clasts, with grains of oxidised magnetite and depleted levels of silica. The colluvial material is usually found as a layer of variable thickness above BIF.
Qualified Person
The technical disclosure in this regulatory announcement has been approved by Steven Poulton, Chief Executive of Altus. A graduate of the University of Southampton in Geology (Hons), he also holds a Master's degree from the Camborne School of Mines (Exeter University) in Mining Geology. He is a Fellow of the Institute of Materials, Minerals and Mining and has over 20 years of experience in mineral exploration and is a Qualified Person under the AIM rules and NI 43-101.
For further information you are invited to visit the Company's website www.altus-strategies.com or contact:
Altus Strategies Plc | Tel:+44 (0) 1235 511 767 |
SP Angel (Nominated Adviser) | Tel: +44 (0) 20 3470 0470 |
SP Angel (Broker) | Tel: +44 (0) 20 3470 0471 |
Yellow Jersey PR (Financial PR & IR) | Tel: +44 (0) 20 3004 9512 |
About Altus Strategies Plc
Altus Strategies (AIM: ALS, TSX-V: ALTS & OTCQX: ALTUF) is a mining royalty company generating a diversified and precious metal focused portfolio of assets. The Company's focus on Africa and differentiated approach, of generating royalties on its own discoveries as well as through financings and acquisitions with third parties, has attracted key institutional investor backing. The Company engages constructively with all stakeholders, working diligently to minimise its environmental impact and to promote positive economic and social outcomes in the communities where it operates. For further information, please visit www.altus-strategies.com.
Cautionary Note Regarding Forward-Looking Statements
Certain information included in this announcement, including information relating to future financial or operating performance and other statements that express the expectations of the Directors or estimates of future performance constitute "forward-looking statements". These statements address future events and conditions and, as such, involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the statements. Such factors include, without limitation, the completion of planned expenditures, the ability to complete exploration programmes on schedule and the success of exploration programmes. Readers are cautioned not to place undue reliance on the forward-looking information, which speak only as of the date of this announcement and the forward-looking statements contained in this announcement are expressly qualified in their entirety by this cautionary statement.
Where the Company expresses or implies an expectation or belief as to future events or results, such expectation or belief is based on assumptions made in good faith and believed to have a reasonable basis. The forward-looking statements contained in this announcement are made as at the date hereof and the Company assumes no obligation to publicly update or revise any forward-looking information or any forward-looking statements contained in any other announcements whether as a result of new information, future events or otherwise, except as required under applicable law or regulations.
TSX Venture Exchange Disclaimer
Neither the TSX Venture Exchange nor the Investment Industry Regulatory Organisation of Canada accepts responsibility for the adequacy or accuracy of this release.
Market Abuse Regulation Disclosure
Certain information contained in this announcement would have been deemed inside information for the purposes of Article 7 of Regulation (EU) No 596/2014 ("MAR") until the release of this announcement.
Glossary of Terms
The following is a glossary of technical terms:
"BIF" means Banded Iron Formation
"grade(s)" means the quantity of ore or metal in a specified quantity of rock
"Fe" means iron
"JORC Code" means the 2012 edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves" prepared by the Joint Ore Reserves Committee of the Australasian Institute of Mining and Metallurgy, Australian Institute of Geoscientists and Minerals Council of Australia. The JORC Code is an acceptable foreign code for purposes of NI 43-101.
"km" means kilometres
"m" means metres
"MRE" means Mineral Resource Estimate
"NI 43-101" means National Instrument 43-101 "Standards of Disclosure for Mineral Projects" of the Canadian Securities Administrators
"Qualified Person" means a person that has the education, skills and professional credentials to qualify as a qualified person under NI 43-101
SOURCE: Altus Strategies PLC