TMAC Resources Inc. (TSX: TMR) (“TMAC” or the “Company”) provides its fourth quarter operations update and production results. In the fourth quarter 2017 TMAC sold 17,350 ounces of gold, realizing $28.1 million (US$22.1 million) at an average realized gold price of US$1,275 per ounce.
Terry MacGibbon, Executive Chairman of TMAC, stated, “TMAC continues to systematically work through the Doris plant to improve plant operations towards design throughput and recovery levels. All of the hard work and dedication over the past many months, by all the plant workers, has resulted in significant improvements, with the recovery for November and December at an average of 76% and throughput in December averaging 84% of design. Two of the three key improvement areas identified during last summer’s plant work shop, a dewatering cone to reduce excess water in the concentrate treatment plant and new resin beads in the resin columns, were addressed during the fourth quarter. The third key improvement area, a new cyclone distributor head, has been fabricated and will be installed shortly.”
Mr. MacGibbon added, “At the Doris mine, underground development continues with the ramp to Doris Connector, our next mining area, well underway, and with the ramp continuing to the Doris BTD zone for future stope access and diamond drill platforms. Ore grade, dilution and mining conditions continued to be as expected with production mining being regulated to coincide with plant throughput capacity.”
He added, “The Hope Bay property continues to be permitted in a timely and efficient manner. Permits are in hand to conduct mining at Doris and surface exploration over the entire 80 km by 20 km Hope Bay property. Both the Madrid and Boston deposits have advanced exploration permits which allow underground exploration and bulk sampling. The final environmental impact studies for production at Madrid and Boston were submitted in late 2017 and we are awaiting the results of the conformity review by the Nunavut Impact Review Board and the Nunavut Water Board. The above advancements position TMAC to ramp up to full mine and plant production and continue exploration efforts.”
2017 AND FOURTH QUARTER PRODUCTION HIGHLIGHTS
Table 1: Summary of production highlights |
|||||||||
Description | Units |
Nine months |
Three months |
Year ended |
|||||
Mining: | |||||||||
Ore mined | tonnes | 97,200 | 53,500 | 150,700 | |||||
Waste mined | tonnes | 197,000 | 66,100 | 263,100 | |||||
Total mined | tonnes | 294,200 | 119,600 | 413,800 | |||||
Average grade | g/t | 12.6 | 9.4 | 11.5 | |||||
Contained ounces | ounces | 39,500 | 16,200 | 55,700 | |||||
Development | metres | 4,080 | 984 | 5,064 | |||||
Processing: | |||||||||
Ore processed | tonnes | 139,300 | 69,600 | 208,900 | |||||
Grade | g/t | 12.0 | 13.7 | 12.6 | |||||
Contained gold | ounces | 53,960 | 30,700 | 84,660 | |||||
Recovery | % | 64 | 72 | 67 | |||||
Gold produced | ounces | 34,410 | 22,220 | 56,630 | |||||
Gold sold | ounces | 29,640 | 17,350 | 46,990 | |||||
Stockpile: | |||||||||
Ore on surface | tonnes | 82,700 | 66,600 | 66,600 | |||||
Average grade | g/t | 16.6 | 13.8 | 13.8 | |||||
Contained gold | ounces | 44,000 | 29,400 | 29,400 | |||||
USD production(1) | |||||||||
Gold sold | $US millions | 37.6 | 22.1 | 59.7 | |||||
Average realized sales price | $US/oz | 1,267 | 1,275 | 1,270 | |||||
Average spot price of gold(2) | $US/oz | 1,268 | 1,275 | 1,266 | |||||
CAD production(1) | |||||||||
Average exchange rate | CAD/USD | 1.31 | 1.27 | 1.30 | |||||
Gold sold | $ millions | 48.7 | 28.1 | 76.8 | |||||
Average realized sales price | $/oz | 1,643 | 1,622 | 1,635 | |||||
Average spot price of gold(2) | $/oz | 1,635 | 1,622 | 1,638 | |||||
(1) Includes both pre and post-commercial production
(2) London PM
fix
PROCESSING PLANT UPDATE
TMAC personnel have continued to systematically troubleshoot the issues affecting the Plant’s operational availability and recovery, and demonstrated improvement in the fourth quarter. Throughput of the concentrator line (“CL”) was improved by focusing on consistent operational practices and optimization of the high pressure jig. The team achieved a milestone of 84% throughput of design capacity in December. A traditional “spider head” cyclone distributor has been delivered to site and is expected to be installed in the Plant shortly. This modification is expected to increase gold recoveries within the first CL.
In the concentrate treatment portion of the Plant (the “CTP”), a dewatering cone to keep excess water from the CL side of the Plant out of the CTP was installed in early November and significantly improved the water balance. Concentrate grinding and leaching optimization is now the focus of the team with an expectation of further improving gold recovery. Also in November, new resin was delivered to the site and a second resin column was activated for gold adsorption. With the second resin column in operation, as well as more frequent “stripping” of the two resin columns, gold solution recovery is performing better. The fouling of resin continues to be an important issue that needs to be managed through good operational practices; however, it is currently being mitigated. Research continues on arriving at a longer-term solution for the fouling, including warm acid washes, as well as research and testing of other resin products with better anti-fouling properties.
It is expected that the modifications to cyclone design, in combination with a focus on grinding and leaching optimization, will result in an improvement in total recoveries later in the first quarter of 2018. Overall recoveries are the product of recoveries from the CL and CTP sections of the Plant.
2018 OBJECTIVES
Doris operations and capital expenditure:
Exploration:
Environment and permitting:
Madrid and Boston:
Management continues to pursue the opportunity to replace the cash collateralized letters of credit issued for environmental rehabilitation security with surety bonds. Surety bonds could release approximately $25 million of cash currently deposited as collateral for letters of credit as well as additional environmental reclamation security that is expected to be placed with various entities during 2018. If surety bonds are obtained, the additional cash would allow for the initial investment in Madrid that includes the acquisition of equipment, the initiation of surface infrastructure and the commencement of underground development required in 2018 to extract a bulk sample in 2019.
CONFERENCE ATTENDANCE
January 17 – 18, 2018
Terry MacGibbon, Executive Chairman, will present on Wednesday, January 17, 2018 at 10:00 am ET at the TD Securities’ 2018 Mining Conference to be held in Toronto, ON, Canada on January 17 - 18, 2018.
ABOUT TMAC RESOURCES
TMAC holds a 100% interest in Hope Bay located in the Kitikmeot region of Nunavut, Canada. TMAC is an emerging gold producer with the Doris mine pouring first gold in the first quarter of 2017 and achieving commercial production in the second quarter of 2017. The Madrid and Boston properties are expected to commence production in 2020 and 2022, respectively. The Company has an experienced, expert board of directors combined with exploration, development and operating teams with extensive track records of discovering, developing and operating high grade, profitable underground mines. TMAC’s shares trade on the Toronto Stock Exchange under the trading symbol TMR.
SCIENTIFIC AND TECHNICAL INFORMATION
Scientific and technical information contained in this document was reviewed and approved by Gil Lawson, P.Eng., Chief Operating Officer of TMAC, a “Qualified Person” as defined by National Instrument 43-101 – Standards of Disclosure for Mineral Projects.
FORWARD-LOOKING INFORMATION
This release contains "forward-looking information” within the meaning of applicable securities laws that is intended to be covered by the safe harbours created by those laws. “Forward-looking information” includes statements that use forward-looking terminology such as “may”, “will”, “expect”, “anticipate”, “believe”, “continue”, “potential” or the negative thereof or other variations thereof or comparable terminology. Such forward-looking information includes, without limitation, bringing the timing for bringing Madrid and Boston into production and the rate of ramp up at Doris throughout 2018.
Forward-looking information is not a guarantee of future performance and management bases forward-looking statements on a number of estimates and assumptions at the date the statements are made. Furthermore, such forward-looking information involves a variety of known and unknown risks, uncertainties and other factors, which may cause the actual plans, intentions, activities, results, performance or achievements of the Company to be materially different from any plans, intentions, activities, results, performance or achievements expressed or implied by such forward-looking information. See “Risk Factors” in the Company’s Annual Information Form, dated February 23, 2017, filed on SEDAR at www.sedar.com for a discussion of these risks.
View source version on businesswire.com: http://www.businesswire.com/news/home/20180116005707/en/