TORONTO, Feb. 22, 2018 (GLOBE NEWSWIRE) -- Torex Gold Resources Inc. (the "Company" or "Torex") (TSX:TXG) reported today the Company’s financial results for the year ended December 31, 2017.
Fred Stanford, President & CEO of Torex stated: “We are happy to have 2017 behind us, with its ramp-up challenges and illegal blockade, now in the rear-view mirror. I would like to acknowledge the team for their excellent contribution in solving the inevitable ramp-up challenges and for their disciplined execution of the strategy to resume operations under blockade conditions. 2018 will be the year that the team completes the last 10% of the ramp-up and showcases the potential of the ELG asset. It will be a year rich in catalysts with the re-start, completion of the SART plant, completion of the ramp-up of the processing plant and the Sub-Sill, continued exploration results from Sub-Sill, and an updated PEA for Media Luna. It will be a busy and productive year, and we all look forward to getting on with it.” He added – “A special thanks to the great many that have supported the team in a myriad of ways as we worked to by-pass the illegal blockade. That support has enabled the potential that 2018 provides for Torex shareholders, employees, and communities.”
Operations Update:
The processing plant is processing between 10,000 – 15,000 tonnes per day. The three day ball mill liner change has been completed. Recoveries have been on plan at approximately 86%, and grades have averaged 2.3 g/t, as we blend in some of the lower grade ore from the stockpile. Ore is being processed from all three open pits, El Limon, Guajes and El Limon Sur. Approximately 50% of our employees have been called back to work, with the remaining employees expected to be called back by the end of the month. As of last Sunday, 25,000 ounces of gold have been poured since January 16 when the operations re-start was initiated. Cash reserves at the beginning of this week were $118 million, including $14 million set aside for reclamation obligations.
At the February 13 meeting to set a date for the union selection vote, the Labour Board and the two unions agreed to defer the meeting to March 15. While this process unfolds, operations continue to ramp up with excellent support from local communities, unionized employees, staff employees and contractors.
This release should be read in conjunction with the Company's year ended December 31, 2017 Financial Statements and MD&A on the Company's website or on SEDAR.
HIGHLIGHTS
An illegal blockade has been by-passed
Plant ramp-up activities now focused on closing the final 10% gap to design throughput levels
Financing
Maiden ELG Underground mineral reserves and mine plan
Grade and tonnage reconciliation to the reserve model for the ELG Open Pits
Media Luna Project progressing
Financial results
Qualified Persons
Scientific and technical information contained in this news release has been reviewed and approved by Dawson Proudfoot, P.Eng., Vice President, Engineering of Torex Gold Resources Inc. and a Qualified Person under NI 43-101 – Standards of Disclosure for Mineral Projects.
Conference Call
The Company will host a conference call today at 9:00 am (ET) where senior management will discuss the 2017 operational and financial results. Access the conference call as follows:
Webcast access: A live audio webcast of the conference call will be available on the Company’s website at www.torexgold.com.
Telephone access: Please call the numbers below approximately ten minutes prior to the scheduled start of the call. Toronto local or international 1 (416) 915-3239
Toll-Free (North America) 1 800-319-4610
Toll-Free (France) 0 800-900-351
Toll-Free (Switzerland) 0-800-802-457
Toll-Free (United Kingdom) 0 808-101-2791
The webcast will be archived on the Company’s website.
About Torex
Torex is an intermediate gold producer based in Canada, engaged in the exploration, development and operation of its 100% owned Morelos Gold Property, an area of 29,000 hectares in the highly prospective Guerrero Gold Belt located 180 kilometers southwest of Mexico City. The Company’s principal assets are the El Limón Guajes mining complex (the “ELG Mine Complex”), comprised of the El Limón, Guajes and El Limón Sur open pits, the El Limón Guajes underground mine including zones referred to as Sub-Sill, El Limón Deep and 71, and the processing plant and related infrastructure, which is in the commercial production stage as of April 1, 2016, and the Media Luna deposit, which is an early stage development project, and for which the Company issued a preliminary economic assessment in 2015. The property remains 75% unexplored.
For further information, please contact:
TOREX GOLD RESOURCES INC. | |
Fred Stanford President and CEO Tel.: (647) 260-1502 Email: fred.stanford@torexgold.com | Gabriela Sanchez Vice President Investor Relations Tel.: (647) 260-1503 Email: gabriela.sanchez@torexgold.com |
CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS
This press release contains "forward-looking statements" and "forward-looking information" within the meaning of applicable Canadian securities legislation. Notwithstanding the Company's efforts, there can be no guarantee that the Company will not face unforeseen delays or further disruptions of its operations. Forward-looking information also includes, but is not limited to, the expected successful completion of the ramp-up, completion of the SART plant, completion of the ramp-up of the processing plant and the Sub-Sill, exploration results from the Sub-Sill and the completion and timing of an updated PEA for Media Luna and the related in-fill drilling program, the union selection vote, the expected production from the ELG Underground mine plan and related capital requirements, and continued safety and security. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "plans", "expects", "estimates", "intends", "anticipates" or "believes" or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might", or "will be taken", "occur", or "be achieved". Forward-looking information is subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Company to be materially different from those expressed or implied by such forward-looking information, including, without limitation, those risk factors identified in the Company's annual information form and management's discussion and analysis. Forward-looking information is based on the reasonable assumptions, estimates, analysis and opinions of management, made in light of its experience and its perception of trends, current conditions and expected developments, as well as other factors that management believes to be relevant and reasonable in the circumstances at the date that such statements are made, but which may prove to be incorrect. Although the Company believes that the assumptions and expectations reflected in such forward-looking information are reasonable, undue reliance should not be placed on forward-looking information because the Company can give no assurance that such expectations will prove to be correct. There can be no assurance that such information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. The Company does not undertake to update any forward-looking information, except in accordance with applicable securities laws.
1 Refer to “Non-IFRS Financial Performance Measures” in the Company’s December 31, 2017 Management’s Discussion and Analysis for further information and a detailed reconciliation.