TORONTO, July 14, 2022 (GLOBE NEWSWIRE) -- Wesdome Gold Mines Ltd. (TSX: WDO) (“Wesdome” or the “Company”) today announces second quarter (“Q2”) 2022 production results. All figures are in Canadian dollars unless otherwise stated.
Duncan Middlemiss, President and CEO commented, “During Q2, there were a number of one-time operational issues that impacted production at both sites. At Eagle River, production was lower than budget due to a manufacturing defect on a new hoist rope, resulting in two weeks of lower productivity as ore was trucked to surface and a second new rope was sourced. Additionally, one of the leach tanks at the mill, which was previously scheduled to be replaced later this year, failed in mid-June, impacting nearly one week of mill production. Once both issues were resolved we were able to mine and process the significantly higher-grade ore planned for June, however gold sales were lower as processing and refinement of this ore slipped into Q3.
At Kiena, the global supply chain challenges which delayed delivery of the underground equipment in Q1, have also delayed delivery of key electrical components for the completion of the paste backfill plant. Consequently, the mining rate has been slower to ramp up which now puts us approximately 3-4 months behind our original 2022 plan.
While we previously indicated production in 2022 was expected to be heavily weighted to the second half of the year, the Company is currently re-evaluating its 2022 production guidance and we will be in a position to release our expectations for the remainder of the year with our Q2 Financials on August 10.”
Amounts are denominated in Canadian dollars | Second Quarter | Year-to-Date | ||||||||||
2022 | 2021 | Variance | % +/(-) | 2022 | 2021 | Variance | % +/(-) | |||||
Ore milled (tonnes) | ||||||||||||
Eagle River | 59,964 | 63,057 | (3,093) | (5%) | 113,181 | 116,596 | (3,415) | (3%) | ||||
Mishi | 7,685 | 9,347 | (1,662) | (18%) | 19,558 | 26,567 | (7,009) | (26%) | ||||
Kiena | 26,478 | 0 | 26,478 | 0% | 47,640 | 0 | 47,640 | 0% | ||||
94,127 | 72,404 | 21,723 | 30% | 180,379 | 143,163 | 37,216 | 26% | |||||
Head grade (grams per tonne, “g/t”) | ||||||||||||
Eagle River | 9.6 | 15.1 | (5.5) | (36%) | 10.6 | 14.1 | (3.5) | (25%) | ||||
Mishi | 2.8 | 2.4 | 0.4 | 17% | 3.3 | 2.4 | 0.9 | 38% | ||||
Kiena | 10.6 | 0.0 | 10.6 | 0% | 9.3 | 0.0 | 9.3 | 0% | ||||
Gold production (ounces) | ||||||||||||
Eagle River | 17,756 | 29,836 | (12,080) | (40%) | 37,090 | 51,232 | (14,142) | (28%) | ||||
Mishi | 570 | 539 | 31 | 6% | 1,735 | 1,707 | 28 | 2% | ||||
Kiena | 8,914 | 0 | 8,914 | 0% | 14,026 | 0 | 14,026 | 0% | ||||
Total Gold Production | 27,240 | 30,375 | (3,135) | (10%) | 52,851 | 52,939 | (88) | (0%) | ||||
Production sold (ounces)3 | 26,000 | 28,500 | (2,500) | (9%) | 54,000 | 50,957 | 3,043 | 6% | ||||
Revenue from gold sales ($ millions)4 | $61.9 | $63.8 | ($1.9) | (3%) | $128.5 | $109.7 | $18.8 | 17% | ||||
Average realized price per ounce2 | $2,380 | $2,239 | 141 | 6% | $2,379 | $2,232 | 147 | 7% | ||||
Notes:
Technical Disclosure
The technical content of this release has been compiled, reviewed and approved by Frederic Langevin, Eng, Chief Operating Officer, a "Qualified Person" as defined in National Instrument 43-101 -Standards of Disclosure for Mineral Projects.
COVID-19
The health and safety of our employees, contractors, vendors, and consultants is the Company’s top priority. In response to the COVID-19 outbreak, Wesdome has adopted all public health guidelines regarding safety measures and protocols at all of its mine operations and corporate office. These protocols are still in place at all sites despite the loosening of some provincial public health guidelines. In addition, our internal COVID-19 Taskforce continues to monitor developments and implement policies and programs intended to protect those who are engaged in business with the Company.
Through care and planning, to date the Company has successfully maintained operations, however there can be no assurance that this will continue despite our best efforts with the emergence of new, highly contagious variants such as Omicron. To date, the company has been impacted by this most recent variant outbreak, with employees at both operations and corporate office becoming infected which may negatively impact our ability to maintain projected timelines and objectives. Consequently, the Company’s actual future production and production guidance is subject to higher levels of risk than usual. We are continuing to closely monitor the situation and will provide updates as they become available.
ABOUT WESDOME
Wesdome is Canadian focused gold producer with two high grade underground assets in Canada, the Eagle River mine in Ontario and the recently re-started Kiena mine in Quebec. The Company also retains meaningful exposure to the Moss Lake gold deposit in Ontario through its equity position in Goldshore Resources Inc. The Company’s primary goal is to responsibly leverage this operating platform and high-quality brownfield and greenfield exploration pipeline to build Canada’s next intermediate gold producer. Wesdome trades on the Toronto Stock Exchange under the symbol “WDO,” with a secondary listing on the OTCQX under the symbol “WDOFF.”
For further information, please contact:
Duncan Middlemiss | or | Lindsay Carpenter Dunlop |
President and CEO | VP Investor Relations | |
416-360-3743 ext. 2019 | 416-360-3743 ext. 2025 | |
duncan.middlemiss@wesdome.com | lindsay.dunlop@wesdome.com | |
220 Bay St, Suite 1200 | ||
Toronto, ON, M5J 2W4 | ||
Toll Free: 1-866-4-WDO-TSX | ||
Phone: 416-360-3743, Fax: 416-360-7620 | ||
Website: www.wesdome.com |
PDF available: http://ml.globenewswire.com/Resource/Download/cbbf7438-3924-4973-8e93-c8e954d6593c