Granada updates resources in feasibility study

By Canadian Mining Journal Staff / December 12, 2018 / www.mining.com / Article Link

A sample of visible gold from the Granada gold mine. (Image: Granada Gold Mine)

QUEBEC - SGS Canada has delivered an updated mineral resource of the Granada gold property near Rouyn-Noranda. Owner Granada Gold Mine, headquartered in Rouyn-Noranda, was also supplied with a revised block model for the entire area.

Pit constrained measured and indicated resources are 22.4 million tonnes grading 1.13 g/t gold and containing 813,000 oz. The inferred resource is 6.9 million tonnes at 2.04 g/t and containing 455,000 oz. of gold. A gold cut-off of 0.4 g/t was used in these calculations.

The Granada gold mine was active in the 1930s before fire destroyed the surface buildings. During that time it produced 50,000 oz. of gold. The company has obtained all the necessary permits to begin the first mining phase as a "rolling start", and stripping has already begun. Initial output will be 25,000 oz. of gold per year, rising eventually to 100,000 oz. per year.

Additional information is available at www.GranadaGoldMine.com.

This story first appeared at Canadian Mining Journal

Recent News

Gold stocks rocket to new highs, valuations no longer inexpensive

August 11, 2025 / www.canadianminingreport.com

Tariff issue caused by potential definition change of traded gold bars

August 11, 2025 / www.canadianminingreport.com

US BLS head removed after revisions to employment data

August 04, 2025 / www.canadianminingreport.com

Gold stocks down even as metal price rises

August 04, 2025 / www.canadianminingreport.com

Copper market distortions driven by new US tariff policies

July 28, 2025 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok