Alrosa considers going underground at Jubilee

By Tasneem Bulbulia      / March 02, 2020 / www.miningweekly.com / Article Link

Russian miner Alrosa’s investment committee has approved financing for preliminary engineering studies at the Jubilee diamond mine, to provide up-to-date information to decide on the construction of an underground mine.

The Jubilee pipe of the Aikhal division is currently being mined by openpit methods.

Advertisement

In 2019, the company considered technical specifications and decided to start preliminary works to set the stage for design and engineering of the prospective underground mine to extract reserves from deeper horizons of the pipe (from -100 m to -680 m levels).

The approved complex of studies include preparation of engineering surveys and feasibility studies for the underground mine and infrastructure. The financing for this phase is budgeted at around ?, 1/2 63-million.

Advertisement

At a pit depth of 480 m, Jubilee has a mining capacity of 5.2-million tonnes a year.

According to the current production plan, it will operate until 2034 with a pit deepening to 720 m (corresponds to -100 m mark).

The company expects to get the feasibility study for the Jubilee underground mine construction, as well as updated resources and reserves, in 2022.

A final decision on the project implementation will be based on these documents.

Recent News

Gold stocks rocket on metal rebound and equities jump

December 01, 2025 / www.canadianminingreport.com

Silver supply shortage continues

December 01, 2025 / www.canadianminingreport.com

Several new entrants to TSXV large gold, including producer Asante

November 24, 2025 / www.canadianminingreport.com

Gold stocks down on metal decline, equity market slide

November 24, 2025 / www.canadianminingreport.com

Largest gold producers see strong Q3/25 earnings

November 17, 2025 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok