Appian Capital's Serrote copper-gold project in Brazil to start output in H2 2021

July 15, 2020 / www.metalbulletin.com / Article Link

Execution works at the copper-gold Serrote project, operated by Minera????o Vale Verde (MVV), have reached 60% completion and is planned to start production in the second half of 2021, MVV's parent company Appian Capital Advisory said on Tuesday July 14.

The project is located in the Brazilian northeastern state of Alagoas, and has an expected production capacity of 20,000 tonnes per year of copper equivalent through 14 years of mine life. First blast to develop the open-pit mine was carried out on June 20, Appian added.

Serrote was initially planned to start commercial operations in the first half of 2021, Appian Brazil's chief executive officer Paulo Castellari told Fastmarkets in August 2019. "It...

Recent News

Some mining stocks exposed to Burkina Faso take major hit

September 02, 2025 / www.canadianminingreport.com

Gold stocks again hit new highs

September 02, 2025 / www.canadianminingreport.com

Gold stocks reach new highs on metal price gain

August 25, 2025 / www.canadianminingreport.com

Rise in gold stocks propels TSXV Mining

August 25, 2025 / www.canadianminingreport.com

Market sees gold sector nearing full value overall after target upgrades

August 18, 2025 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok