ArcelorMittal Kryvyi Rih prepares to modernize BF No9, capacity to rise by 36%

July 17, 2021 / www.metalbulletin.com / Article Link

Ukraine's ArcelorMittal Kryvyi Rih has begun modernization of its blast furnace (BF) No9. The BF has a current capacity of 3.7 million tonnes per year of hot metal but the reconstruction will increase capacity by 35.7%, to 4.5 million tpy, sources told Fastmarkets.

The BF modernization aims to optimize raw materials consumption.
The works should be finalized by the end of 2023. Total investment in the project is estimated to be $270 million.

"Pulverized coal fuel will be used instead of expensive natural gas. The total consumption of fuel - gas, coal and coke - will decrease so the prime...

Recent News

Monetary-driven precious metals outperform major base metals

September 09, 2024 / www.canadianminingreport.com

Gold stocks hit by plunging equities markets

September 09, 2024 / www.canadianminingreport.com

Gold stocks down as metal and equities momentum fades

September 02, 2024 / www.canadianminingreport.com

Another Kazatomprom guidance announcement shakes uranium price

September 02, 2024 / www.canadianminingreport.com

Major monetary drivers still supporting gold

August 26, 2024 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok