ArcelorMittal Kryvyi Rih prepares to modernize BF No9, capacity to rise by 36%

July 17, 2021 / www.metalbulletin.com / Article Link

Ukraine's ArcelorMittal Kryvyi Rih has begun modernization of its blast furnace (BF) No9. The BF has a current capacity of 3.7 million tonnes per year of hot metal but the reconstruction will increase capacity by 35.7%, to 4.5 million tpy, sources told Fastmarkets.

The BF modernization aims to optimize raw materials consumption.
The works should be finalized by the end of 2023. Total investment in the project is estimated to be $270 million.

"Pulverized coal fuel will be used instead of expensive natural gas. The total consumption of fuel - gas, coal and coke - will decrease so the prime...

Recent News

Gold's Bull Market Pullbacks

April 28, 2025 / www.canadianminingreport.com

Gold stocks down on metal drop

April 28, 2025 / www.canadianminingreport.com

Investment banks ahead of the gold price, institutions still behind

April 21, 2025 / www.canadianminingreport.com

Gold stocks up, juniors outperform on small cap strength

April 21, 2025 / www.canadianminingreport.com

Gold stocks rebound to new highs

April 14, 2025 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok