Australia's Newcrest: Cadia mine to return to full production by mid-2018

By Reuters / May 06, 2018 / www.mining.com / Article Link

Australia's biggest gold miner Newcrest Mining Ltd said it expects its flagship Cadia mine to return to full production rates by the end of June.

The miner said it had begun depositing tailings into the Cadia Hill open pit over the weekend, after receiving approval from the New South Wales Department of Planning and Environment last month.

Newcrest restarted processing at Cadia last month after halting operations due to damage to a tailings dam wall in early March.

In April, Newcrest cut full-year gold production guidance to between 2.25 million and 2.35 million ounces, down from 2.4 million to 2.7 million ounces previously, mainly due to damage at the tailings facility.

Newcrest said it continues to review and determine the cause of the Northern Tailings Facility embankment slump.

Reporting by Nicole Pinto in Bengaluru; Editing by Richard Pullin.

Recent News

Gold stocks up on rise in metals and equities

October 14, 2024 / www.canadianminingreport.com

Gold stocks decline on flat metal and mixed equities

October 07, 2024 / www.canadianminingreport.com

Copper price expected to range from flat to slight gain in 2025

October 07, 2024 / www.canadianminingreport.com

China's gold holdings to central bank reserves still low

September 30, 2024 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok