Average eight-month time creep too

By Paul Harris / July 29, 2019 / www.mining-journal.com / Article Link

Quality emerges at Galan's blue-chip lithium address

SPONSORED

galan lithium

Quality emerges at Galan's blue-chip lithium addresssponsored-logo

GEM analysed 194 mine development projects undertaken between 1994 and 2014 and found coal projects had the biggest overruns at 32% followed by gold at 31% and copper at 28%. In addition to cost overruns, the study found development time also overran by an average of eight months.

"These are associated to a mix of variables from the design of the project, the company executing it and other macroeconomic variables of the market," said GEM general manager Juan Ignacio Guzman.

Quality emerges at Galan's blue-chip lithium address

SPONSORED

galan lithium

Quality emerges at Galan's blue-chip lithium addresssponsored-logo

Applying these findings to the US$65.7 billion portfolio of development projects Chile's copper agency Cochilco has for the 2018-2027 period, GEM estimates there will be some $17 billion in cost overruns including $11 billion at state copper company Codelco alone.

Codelco, the world's largest copper producer, has some $40 billion of capital investment projects planned through 2028 as it seeks to modernise and extend the life of several of its mines such as Chuquicamata.

Recent News

Gold stocks weaker but outperform slump in other sectors

October 13, 2025 / www.canadianminingreport.com

West Africa-focussed Robex and PDI to merge

October 13, 2025 / www.canadianminingreport.com

Gold stocks outperform equity market gains

October 06, 2025 / www.canadianminingreport.com

Most major producers rise but TSXV gold mixed

October 06, 2025 / www.canadianminingreport.com

Platinum, palladium, copper gain on green China, supply constraints

September 29, 2025 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok