BlueRock achieves 80 t/h crushing target at Kareevlei

By Marleny Arnoldi      / August 24, 2018 / www.miningweekly.com / Article Link

The crushing circuit at BlueRock Diamonds’ Kareevlei mine, in the Northern Cape, is now processing at its targeted production level of around 80 t/h following the installation of a second cone crusher and the implementation of optimisation initiatives.

In June, BlueRock discovered a fault in the circuit’s cone crusher, which led to processing being stopped for around ten days. While the fault was being rectified, a rented crusher was installed on site at modest additional cost.

Advertisement

The original cone crusher is now refurbished and operating in tandem with the rented crushing unit, increasing the throughput capacity in the secondary crushing process.

The 80 t/h processing capability will contribute to producing stockpiled material to alleviate the production challenges usually present in the rainy period from January to April.

Advertisement

Recent News

Big Gold has another strong quarter, but some signs growth cooling

May 12, 2025 / www.canadianminingreport.com

Gold stocks nearly regain highs on rising metal price

May 12, 2025 / www.canadianminingreport.com

Gold stocks down as risk on move continues

May 05, 2025 / www.canadianminingreport.com

Mixed outlook for resources on new Canadian government

May 05, 2025 / www.canadianminingreport.com

Gold's Bull Market Pullbacks

April 28, 2025 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok