BlueRock achieves 80 t/h crushing target at Kareevlei

By Marleny Arnoldi      / August 24, 2018 / www.miningweekly.com / Article Link

The crushing circuit at BlueRock Diamonds’ Kareevlei mine, in the Northern Cape, is now processing at its targeted production level of around 80 t/h following the installation of a second cone crusher and the implementation of optimisation initiatives.

In June, BlueRock discovered a fault in the circuit’s cone crusher, which led to processing being stopped for around ten days. While the fault was being rectified, a rented crusher was installed on site at modest additional cost.

Advertisement

The original cone crusher is now refurbished and operating in tandem with the rented crushing unit, increasing the throughput capacity in the secondary crushing process.

The 80 t/h processing capability will contribute to producing stockpiled material to alleviate the production challenges usually present in the rainy period from January to April.

Advertisement

Recent News

Gold stocks lead the large cap miners by far over H1/25

July 07, 2025 / www.canadianminingreport.com

Gold stocks up as the metal price and equities gain

July 07, 2025 / www.canadianminingreport.com

Mixed outlook for gold as it remains range bound for past three months

June 30, 2025 / www.canadianminingreport.com

Gold stocks down on flat metal price

June 30, 2025 / www.canadianminingreport.com

Gold stocks down on metal decline

June 23, 2025 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok