First Cobalt refinery output could be doubled

By Canadian Mining Journal Staff / May 28, 2019 / www.mining.com / Article Link

Ausenco Engineering Canada has delivered a study of the refinery in Cobalt, Ontario to Toronto-based First Cobalt Corp. The study says that using third party cobalt hydroxide as feed, the refinery output could be doubled to 5,000 t/y cobalt contained in sulphate.

The estimated cost to double refinery capacity would be C$37.5 million, spent in stages. Any work will first involve eliminating the existing autoclave circuit and debottlenecking the rest of the plant.

Ausenco's scoping level study outlined three restart scenarios, assuming the refinery would treat cobalt hydroxide feed grating at least 30% cobalt. One: the existing equipment could be refurbished at a cost of C$12 million. Two: debottlenecking the existing solvent extraction circuit would cost an additional C$18.4 million. Three: increase liquid-solid separation capacity by adding more filtration capacity and expand the existing building at another cost of C$37.5 million.

First Cobalt has not yet committed to restarting the refinery, and it is in talks with Glencore to supply the feedstock and financing.

(This article first appeared in the Canadian Mining Journal)

Recent News

Silver inventories rebound in UK, output from major producers rises

December 15, 2025 / www.canadianminingreport.com

Silver's three-month outperformance continues

December 15, 2025 / www.canadianminingreport.com

Silver & Copper Supply Distortions Continue

December 08, 2025 / www.canadianminingreport.com

Gold stocks down in risk-on shift

December 08, 2025 / www.canadianminingreport.com

Gold stocks rocket on metal rebound and equities jump

December 01, 2025 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok