Flooded Nornickel copper, nickel mines' restart delayed; company forecasts output losses

March 17, 2021 / www.metalbulletin.com / Article Link

The world's largest producer of high-grade nickel expects to restore full capacity at its flooded mines in Siberia in the next 3-4 months but revised its metal production volumes to reflect the mining halt, it said on March 16.

Nornickel's Oktyabrsky and Taimyrsky mines have been closed since February 24 following an inflow of groundwater into the two mines.
The nickel production shortfall should be 65,000 tonnes for copper, 35,000 tonnes for nickel and 22 tonnes for the platinum metal groups, Nornickel said.
The company's Norilsk Division, which oversees the two mines in the Siberian region, has developed a plan where the Oktyabrsky mine - with a capacity of 5 million tonnes per year of ore output - would gradually ramp-up in the second half of April into May as a best case scenario, it said.

The Taimyrsky mine - with...

Recent News

Gold stocks reach new highs on metal price gain

August 25, 2025 / www.canadianminingreport.com

Rise in gold stocks propels TSXV Mining

August 25, 2025 / www.canadianminingreport.com

Market sees gold sector nearing full value overall after target upgrades

August 18, 2025 / www.canadianminingreport.com

Gold stocks gain even as metal pulls back

August 18, 2025 / www.canadianminingreport.com

Gold stocks rocket to new highs, valuations no longer inexpensive

August 11, 2025 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok