SPONSOREDThe fundraise, at a price of 90.5p per placing share, includes a placing to new and existing institutional investors to raise £35.2 million, La Mancha Investments participating for up to £23.8 million, and BMO Capital Markets underwriting a portion of up to £11.4 million.
A proposed conditional subscription of new shares, together with the fundraise shares, by Glencore International and certain directors, would raise up to about £26.4 million, the company said.
Chaarat makes headway at Kyzyltash
SPONSOREDBedrock gold discovery adds to Kingwest reign
SPONSOREDMining Journal and MiningNews.Net Critical Minerals report
SPONSOREDMetal Bank draws on experience as resource upgrades near
SPONSOREDHorizonte's share price rose 2.58% day on day to 99.5p at market close on 4 October.
Global inflationary pressures, as well as engineering improvements to de-risk the project, have pushed the total capital cost for Araguaia up by 12.6% from the US$477 million originally budgeted in November last year to US$537 million.
"The Fundraise is anticipated to allow the Company to complete the construction of the Project, which remains on schedule for first production in Q1 2024," Horizonte said.
"In addition, the Fundraise will allow the Company to accelerate engineering studies and basic engineering for the development of line 2 at Araguaia, as well as further invest in its decarbonisation strategy for the Project," it added.
Horizonte secured a US$633 million funding package for the construction of the project in November 2021, which included a senior debt facility of about US$346 million.
The company said that it is unable to conduct a retail offering alongside the fundraise due to having offered the maximum number of securities to retail shareholders permissible.
Ore is to be sourced from eight open pits at the mine, with a targeted 0.9 million tonne per annum of ore to go to a central processing and smelting facility. With a 30+-year production schedule, there are approximately 16 months of construction remaining before the initial ramp-up to full-scale production is expected to commence.
A 2018 feasibility study viewed the project to have about US$4.8 billion net cash flow, a post-tax NPV8% of US$1.5 billion, a post-tax IRR of 43%, 2 year payback period, and a cash cost of US$6,794/t Ni.