Hydro resumes operations at bauxite mine, Alunorte production to ramp up

October 10, 2020 / www.metalbulletin.com / Article Link

Production at Hydro's Alunorte alumina refinery in Brazil will ramp back up now that maintenance at the Paragominas bauxite mine has finished, the producer said on Friday October 9.

"On October 8, Hydro resumed operation of the pipeline transporting bauxite from Hydro Paragominas bauxite mine to the Hydro Alunorte alumina refinery in Brazil," Hydro said.
Production at Paragominas bauxite mine has resumed and alumina production is now being ramped up at Alunorte, the company said. 

Recent News

Bank of Japan boosts rates, continuing an unwinding carry trade

December 22, 2025 / www.canadianminingreport.com

Gold stocks outperform equity market slide

December 22, 2025 / www.canadianminingreport.com

Silver inventories rebound in UK, output from major producers rises

December 15, 2025 / www.canadianminingreport.com

Silver's three-month outperformance continues

December 15, 2025 / www.canadianminingreport.com

Silver & Copper Supply Distortions Continue

December 08, 2025 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok