AUSTRALIA - BHP Group has commissioned the new ramp at its Olympic Dam iron ore-copper-gold mine, and it doubles the haulage capacity for its trucks. The Kalta decline is key to reaching the Southern mine area where BHP is mining high grade copper resources.

BHP spent A$250 million to develop the Southern mine area, and another $40 million on the ramp. The first ore from the area was produced in mid-2017.

The Olympic Dam mine is located 560 km north of Adelaide. There is underground mining as well as a fully integrated processing facility. Copper is recovered in a conventional mill before it is refined. Uranium is recovered through a hydrometallurgical plant. There is also a circuit for precious metals recovery.

Learn more about BHP's global operations at www.BHP.com.

Recent News

Mixed outlook for gold as it remains range bound for past three months

June 30, 2025 / www.canadianminingreport.com

Gold stocks down on flat metal price

June 30, 2025 / www.canadianminingreport.com

Gold stocks down on metal decline

June 23, 2025 / www.canadianminingreport.com

Huge quantifiable rise in geopolitical, economic and trade risks

June 23, 2025 / www.canadianminingreport.com

Platinum clearly ahead of palladium for first time in seven years

June 16, 2025 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok