Kakula development continues to accelerate

By Staff Reporter / June 04, 2020 / www.mining-journal.com / Article Link

Rupert Resources on a Roll at Ikkari

SPONSORED

Cardinal heading down familiar gold road

SPONSORED

cardinal resources

Cardinal heading down familiar gold roadsponsored-logo

Sarama right in the middle of big exploration, corporate build-up

SPONSORED

sarama resources

Sarama right in the middle of big exploration, corporate build-upsponsored-logo

Exore excels in Cote d'Ivoire

SPONSORED

exore resources

Exore excels in Cote d'Ivoiresponsored-logo

Development crews set another monthly record of 1,868m in May. Underground development remains a priority to have adequate access to be able to mine at the initial 3.8-million-tonnes-per-annum rate when the mine starts production in the September quarter next year.

The mine intends to continue to add more crews over the next year to further accelerate development.

Rupert Resources on a Roll at Ikkari

SPONSORED

Cardinal heading down familiar gold road

SPONSORED

cardinal resources

Cardinal heading down familiar gold roadsponsored-logo

Sarama right in the middle of big exploration, corporate build-up

SPONSORED

sarama resources

Sarama right in the middle of big exploration, corporate build-upsponsored-logo

Exore excels in Cote d'Ivoire

SPONSORED

exore resources

Exore excels in Cote d'Ivoiresponsored-logo

About 10km north of Kakula at the Kamoa deposit, underground mining is ongoing to train new crews of Congolese miners.

Meanwhile, the high-grade copper stockpiles are growing at surface, since the underground development is mainly through ore grading about 8% copper. The company is separating the surface stockpiles according to high, medium, and low grades. The high-grade stockpile holds about 51,000t grading about 5.86% copper, and is expected to expand significantly over the coming months.

BMO Capital Markets analyst Andrew Mikitchook said the progress of delivering long-lead items such as ball mill shells and other large equipment to site would be among the next steps to monitor.

A definitive feasibility study and integrated development plan for the greater Kamoa-Kakula project, incorporating updates for mineral resources, production rates, and economic analysis, remains on track for publication by mid-year.

The Kamoa-Kakula project is a joint venture between Ivanhoe (39.6%), Zijin Mining Group (39.6%), Crystal River Global (0.8%) and the DRC government (20%).

BMO maintains its ‘outperform' rating for Ivanhoe shares (TSX:IVN), with a target price of C$9. Shares have recovered 56% since a mid-March sell-off, adding another 5% Thursday at $3.56, which capitalises it at $4.3 billion (US$3.2 billion).

 

Recent News

Smaller juniors still financed even in more cautious market

January 13, 2025 / www.canadianminingreport.com

Gold stocks shrug off equity market decline on metal gain

January 13, 2025 / www.canadianminingreport.com

Geopolitical risk outlook unclear after US election

January 06, 2025 / www.canadianminingreport.com

Low valuations offer a cushion to mining sector

January 06, 2025 / www.canadianminingreport.com

Polarized gold and iron ore moves, moderate aluminum and copper gains

December 30, 2024 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok