Mitsubishi Materials says its Indonesia copper smelter declared force majeure on some deliveries

By Reuters / November 29, 2018 / www.mining.com / Article Link

* Japan's Mitsubishi Materials on Thursday said that its Indonesia copper smelting unit, PT Smelting, has declared force majeure on deliveries of products to some customers as maintenance at its plant in the country had been extended.

* The smelter on Oct. 31 went into maintenance that was scheduled for about 30 days, but that has been extended due to a lack of oxygen supply from a neighboring oxygen plant, said a Mitsubishi Materials spokesman.

* The oxygen plant was also conducting maintenance that had to be extended, the spokesman said.

* The extended maintenance at the smelter is expected to cut annual production of copper cathode at the unit by about 20,000 tonnes to about 240,000-250,000 tonnes, the spokesman said.

* He did not say how much copper supply would be affected by force majeure or which customers would be hit.

* He said the smelter was expected to resume partial operations in mid-December, returning to full operation in mid-January.

(Reporting by Yuka Obayashi; Editing by Joseph Radford)

Recent News

Immediate trigger for crash was new Fed Chairman pick

February 02, 2026 / www.canadianminingreport.com

Gold stocks slump on metal price decline

February 02, 2026 / www.canadianminingreport.com

Is the gold market starting to turn 'irrationally exuberant'?

January 26, 2026 / www.canadianminingreport.com

Gold stocks explode up as equity markets languish

January 26, 2026 / www.canadianminingreport.com

Gold stocks outpace flat large caps

January 19, 2026 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok