Nemaska receives independent audit report from BBA

By Canadian Mining Journal Staff / April 29, 2019 / www.mining.com / Article Link

Quebec City-based Nemaska Lithium has received the independent audit report it asked Canadian engineering firm BBA to conduct. The results, says the company, validate its own internal cost-to-complete construction assessment as of Feb. 13, 2019.

Looking at the estimated capex, BBA made an assessment slightly lower than did Nemaska, which estimated a further C$375 million is needed to complete the project. BBA also confirmed that the company has made certain internal changes and assigned the appropriate supplementary resources to strengthen control over construction activities and costs.

Nemaska has hired new, seasoned experts to the construction team, and it has streamlined and improved its project control processes. The entire project contract and procurement management function has been brought in house to ensure that contracting strategies are adapted to the current reduced pace of construction.

The audit was conducted at the request of the corporation's board of directors special committee.

(This article first appeared in the Canadian Mining Journal)

Recent News

Gold and silver price ETFs see major net outflows

November 04, 2025 / canadianminingreport.com

Gold stocks decline by less than metal price

November 04, 2025 / www.canadianminingreport.com

A shift to the later stages of gold and silver bull markets

October 27, 2025 / www.canadianminingreport.com

Gold stocks plunge on metal drop

October 27, 2025 / www.canadianminingreport.com

Gold stocks still up after pullback late in the week

October 20, 2025 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok