New ramp at BHP's Olympic Dam doubles capacity

By Canadian Mining Journal Staff / December 18, 2018 / www.mining.com / Article Link

AUSTRALIA - BHP Group has commissioned the new ramp at its Olympic Dam iron ore-copper-gold mine, and it doubles the haulage capacity for its trucks. The Kalta decline is key to reaching the Southern mine area where BHP is mining high grade copper resources.

BHP spent A$250 million to develop the Southern mine area, and another $40 million on the ramp. The first ore from the area was produced in mid-2017.

The Olympic Dam mine is located 560 km north of Adelaide. There is underground mining as well as a fully integrated processing facility. Copper is recovered in a conventional mill before it is refined. Uranium is recovered through a hydrometallurgical plant. There is also a circuit for precious metals recovery.

Learn more about BHP's global operations at www.BHP.com.

This story first appeared at Canadian Mining Journal

Recent News

Market sees gold sector nearing full value overall after target upgrades

August 18, 2025 / www.canadianminingreport.com

Gold stocks gain even as metal pulls back

August 18, 2025 / www.canadianminingreport.com

Gold stocks rocket to new highs, valuations no longer inexpensive

August 11, 2025 / www.canadianminingreport.com

Tariff issue caused by potential definition change of traded gold bars

August 11, 2025 / www.canadianminingreport.com

US BLS head removed after revisions to employment data

August 04, 2025 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok