Teck flags costs surge at Chile Quebrada Blanca expansion

By Cecilia Jamasmie / October 28, 2021 / www.northernminer.com / Article Link

Teck Resources (TSX: TECK.A/TECK.B; NYSE: TECK) Canada's largest diversified miner, said this week that while construction of its massive Quebrada Blanca Phase 2 (QB2) expansion project in Chile is two-thirds complete, costs are anticipated to be up to 5% higher than the original US$5.3 billion estimate.

Delivering results for the third-quarter, in which Teck recorded a profit of US$816 million, the Vancouver-based company said despite challenges faced in the past year, production at QB2 is expected to begin in the second half of 2022.

Teck's CEO Don Lindsay cited challenges with "port offshore" and tailings facility construction as the main causes of the cost increase, noting the company will issue updated capital cost guidance on the project in February 2022, when posting its fourth quarter results.

Construction at QB2, slated to produce 300,000 tonnes of copper equivalent per year for the first five years of its life, was suspended in March 2020 when the first cases of Covid-19 appeared in the South American nation. The miner originally expected the work halt to last for two weeks, but as the pandemic overtook much of Chile, it was forced to delay the project through August.

In a call with analysts, Lindsay said QB2 remained a key project as it is expected to double Teck's copper production by 2023. It is expected to extend the ageing deposit's life by 28 years and substantially boost production to 300,000 tonnes of copper a year from 23,400 tonnes in 2017.

The Canadian mining giant is already studying a Phase 3 for the mine, which will double its capacity to 600,000 tonnes of copper a year. The potential extension will make the mine Chile's second-largest copper operation, after Escondida. It will also situate Quebrada Blanca among the world's top five copper mines.

The Quebrada Blanca 2 copper project in Chile. Credit: Teck Resources.

In terms of costs, Phase 3 would require a US$5 billion investment, as it would have to include the installation of a new concentrator.

Copper is one of four business units at Teck besides steelmaking coal, oil and zinc, and is considered a company priority.

Lindsay and members of the senior management team are hosting a virtual site tour of QB2 on November 1 from 1:00 p.m. to 2:00 p.m. Eastern Time.

Recent News

Gold and silver price ETFs see major net outflows

November 04, 2025 / canadianminingreport.com

Gold stocks decline by less than metal price

November 04, 2025 / www.canadianminingreport.com

A shift to the later stages of gold and silver bull markets

October 27, 2025 / www.canadianminingreport.com

Gold stocks plunge on metal drop

October 27, 2025 / www.canadianminingreport.com

Gold stocks still up after pullback late in the week

October 20, 2025 / www.canadianminingreport.com
See all >
Share to Youtube Share to Facebook Facebook Share to Linkedin Share to Twitter Twitter Share to Tiktok